RERA projects in Panhala (M Cl)

1 project under 1 MahaRERA registration, registered 2019–2019. 100% have a completion date extended beyond the one promised.

1RERA projects
1Registrations
0Completion still due1 past their completion date
18 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20191

Projects in Panhala (M Cl)

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Pristine Green VillasS Yashwant DevelopersP530000219358 Aug 201930 Dec 202230 Jun 2024Extended 18 mo0

Other localities in Panhala

Most active promoters

By projects registered here, as named on MahaRERA.

  1. S Yashwant Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology