RERA projects in Panhala (M Cl)
1 project under 1 MahaRERA registration, registered 2019–2019. 100% have a completion date extended beyond the one promised.
1RERA projects
1Registrations
0Completion still due1 past their completion date
18 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2019 | 1 |
Projects in Panhala (M Cl)
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Pristine Green VillasS Yashwant Developers | P53000021935 | 8 Aug 2019 | 30 Dec 2022 | 30 Jun 2024 | Extended 18 mo | 0 |
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology