RERA projects in Kolhapur
869 projects under 881 MahaRERA registrations across 51 localities, registered 2017–2026. 41% have a completion date extended beyond the one promised.
District
869RERA projectsin 51 localities
881Registrationssome projects hold several
299Completion still due488 past their completion date
4 monthsMedian extension beyond promised date41% of registrations extended
35Regulatory caseson 35 projects
1,120Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 189 |
| 2018 | 53 |
| 2019 | 49 |
| 2020 | 62 |
| 2021 | 59 |
| 2022 | 103 |
| 2023 | 89 |
| 2024 | 63 |
| 2025 | 57 |
| 2026 | 63 |
Projects in Kolhapur
869 projects registered with MahaRERA in this district and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Gateway ResidenciesSiddhivinayak Developers | PR1150002502203 | 29 Jan 2026 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Growing GraceAmit Bapu Lokhande | PR1150002502205 | 29 Jan 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Sadguru PlazaMadhuri Shrikant Shirale | PM1150002502200 | 29 Jan 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| WaterlilyLife Style Developers | PR1150002502206 | 29 Jan 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| SkylineShree Constructions | PR1150002502192 | 27 Jan 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Redekar CrownHankare Patil Landmarks | PM1150002502161 | 22 Jan 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| The Indira PalatialShree Mahalaxmi Realty | PM1150002502156 | 22 Jan 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| 339 Tapasya NiwaraM/s Niwara Builders & Developers | PR1150002502133 | 21 Jan 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Ideal EliteIdeal Properties | PR1150002502143 | 21 Jan 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Maheshwari HeightsSubhash Ramgopal Maheshwari | P53000081087 | 16 Jan 2026 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Mahapadma AvenueM S Infrastructure | PM1150002501829 | 19 Dec 2025 | 1 Nov 2029 | 1 Mar 2030 | Extended 4 mo | 0 |
| Emmanuel CornerstoneSantosh Mohan Arawattigi | P53000081072 | 16 Dec 2025 | 31 Oct 2032 | 28 Feb 2033 | Extended 4 mo | 0 |
| The ClayNarayan Auto Works | PR1150002501777 | 15 Dec 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| The Grand PinnacleSairaj Builders And Developers | PM1150002501767 | 15 Dec 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| One EarthDeshpande Infra | PR1150002501739 | 10 Dec 2025 | 31 Dec 2032 | 30 Apr 2033 | Extended 4 mo | 0 |
| Sky HeightsKirtikumar Balasaheb Masute | PR1150002501532 | 21 Nov 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Niranjan HeightsProprietor B S Developers SABIHA FIROJ SHIKALAGAR | PM1150002501276 | 20 Oct 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| The ApexShiv Siddhi Buildcon | PM1150002501268 | 20 Oct 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| HorizonDeshpande Infra | PM1150002501261 | 16 Oct 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Padalkar ResidencyShirke More Builders and Developers | PM1150002501222 | 13 Oct 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Shakuntala HeightsGaikwad Infrastructure Private Limited | PR1150002501128 | 9 Oct 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Guru Vedas ResidencyGM Infrastructure | PR1150002501087 | 1 Oct 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Ishwar KrupaChavan Builders and Developers | PM1150002500934 | 24 Sep 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Nanda Bal ParadiseUnity Pramoters And Builders | PR1150002500882 | 22 Sep 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Galaxy HeightsAditya Bhimrao Kolawale | PM1150002500795 | 15 Sep 2025 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
Localities in Kolhapur
By number of registered projects, as MahaRERA names them.
- Kolhapur (M Corp.)454 projects
- Karvir59 projects
- Ichalkaranji (M Cl)58 projects
- Gadhinglaj (M Cl)33 projects
- Gadhinglaj27 projects
- Ujalaiwadi (Ct)26 projects
- Jaysingpur (M Cl)24 projects
- Karvir19 projects
- Hatkanangle17 projects
- Gadhinglaj16 projects
All 51 localities
- Kolhapur (M Corp.)454
- Karvir59
- Ichalkaranji (M Cl)58
- Gadhinglaj (M Cl)33
- Gadhinglaj27
- Ujalaiwadi (Ct)26
- Jaysingpur (M Cl)24
- Karvir19
- Hatkanangle17
- Gadhinglaj16
- Kagal (M Cl)16
- Jaysingpur12
- Vadgaon Kasba (M Cl)11
- Uchgaon (Ct)7
- Balinge6
- Gijavane4
- Kagal4
- Morewadi (Ct)4
- Ajara (Ct)3
- Vadgaon Kasaba3
- Gargoti2
- Hupari (Ct)2
- Kabnur (Ct)2
- Malkapur (M Cl)2
- Pachgaon (Ct)2
- Panhala2
- Sarnobatwadi2
- Wadipir2
- Yadrav2
- Ajra1
- Bambavade1
- Bhudargad1
- Chandgad1
- Danewadi1
- Gagan Bavda1
- Hatkanangale1
- Japhale1
- Kalambe T. Thane (Ct)1
- Kandalgaon1
- Kodoli1
- Madale1
- Majale1
- Nagdevwadi1
- Nrusinhawadi1
- Panhala (M Cl)1
- Radhanagari1
- Radhanagari1
- Shirol1
- Shiroli1
- Shiye1
- Vathar Tarf Vadgaon1
Other districts
Most active promoters
By projects registered here, as named on MahaRERA.
- Deshpande Infra7 projects
- Pune Housing and Area Development Board Pune7 projects
- Bhaskar Ramgonda Patil6 projects
- M/S SD Associates6 projects
- Shendre and Associates5 projects
- The Ideal Construction5 projects
- Bedekar Lifespaces LLP4 projects
- Fortune Developers4 projects
- Mahabharat Construction Corporation4 projects
- Patki-Joshi Engineers and Contractors Pvt. Ltd.4 projects
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology