RERA projects in Malkapur (M Cl)
2 projects under 2 MahaRERA registrations, registered 2018–2021. None has an extended completion date on record.
2RERA projects
2Registrations
0Completion still due2 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 1 |
Projects in Malkapur (M Cl)
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| DS PlazaDSS Group | P53000031255 | 15 Oct 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Om PrestigeM/s Om Associates | P53000018450 | 1 Nov 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
Other localities in Kolhapur
- Bambavade1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- DSS Group1 project
- M/s Om Associates1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology