Delayed projects in Pune
2,214 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 7 of 45.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Sai AradhanaSai Agencies | Mahalunge | Mar 2021 | Sep 2022 | 5 yrs 8 mo late |
| Signature TowerSaarrthi Realty and Infra Limited Liability Partnership | Pune (M Corp.) | Mar 2021 | Sep 2023 | 5 yrs 8 mo late |
| Anshulkosmas C And D BuildingAnshulbhosale Realty | Haveli | Mar 2021 | Mar 2021 | 5 yrs 8 mo late |
| Balkawade HeightsBalkawade Associates | Katraj | Mar 2021 | Mar 2021 | 5 yrs 8 mo late |
| MeghrajDhanashree Devlopers And Builders | Pimpri Chinchawad (M Corp.) | Mar 2021 | Dec 2025 | 5 yrs 8 mo late |
| Sai VillaShivling Vasant Jare | Pimpri Chinchawad (M Corp.) | Mar 2021 | Jun 2024 | 5 yrs 8 mo late |
| Shree Madhavaashram ApartmentShree Gajanan Developers | Baner | Mar 2021 | Mar 2021 | 5 yrs 8 mo late |
| Shree Ram ApartmentsShree Chaitanya Developers | Pimpri Chinchawad (M Corp.) | Mar 2021 | Mar 2021 | 5 yrs 8 mo late |
| Vb CapitolKeystone Realty | Pune (M Corp.) | Apr 2021 | Jun 2022 | 5 yrs 7 mo late |
| Yogville Phase IRoyal Yogville Ventures | Dhayari (Part) | Apr 2021 | Dec 2024 | 5 yrs 7 mo late |
| Anantmegh ATanish Promoters & Developers | Moshi | Apr 2021 | Apr 2022 | 5 yrs 7 mo late |
| Anantmegh BSadguru Developers | Moshi | Apr 2021 | Apr 2022 | 5 yrs 7 mo late |
| Maitreya ResidencyMaitreya Construction And Developers | Bhosari | May 2021 | Nov 2022 | 5 yrs 6 mo late |
| AmrutvelAmol Narayan Bhore | Mahalunge | May 2021 | Dec 2021 | 5 yrs 6 mo late |
| 18 Longitude Phase 3G D Square Promoters LLP | Punawale | Jun 2021 | Jun 2025 | 5 yrs 5 mo late |
| Global CityDivine Developers | Wadagaon (Ct) | Jun 2021 | Mar 2024 | 5 yrs 5 mo late |
| Anandita ApartmentPotear Associates | Baramati (M Cl) | Jun 2021 | Jun 2025 | 5 yrs 5 mo late |
| Aapla Ghar Chakan Phase I Amentiy A BldgMaple Estates | Nanekarwadi (Ct) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Balaji Vishwa Building CIdeal Properties | Pune (M Corp.) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Chindhiwala ComplexChindhiwala Developers | Pune City | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Ganga Bhagyoday D Bldg.Goel Ganga India Pvt Ltd | Pune (M Corp.) | Jun 2021 | Jun 2021 | 5 yrs 5 mo late |
| Goodwill Nirmiti C BuildingUnique Choice Ventures | Lohgaon | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Jai Ganesh 24Siddhivinayak Kohinoor | Bhosari | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Laukik IckonLaukik Infrastructure Company | Ambadvet | Jun 2021 | Dec 2025 | 5 yrs 5 mo late |
| MarvellaArush Associates | Punawale | Jun 2021 | Aug 2023 | 5 yrs 5 mo late |
| Mbm Developers The West Ford Phase 1M B M Developers | Pimpale Saudagar | Jun 2021 | Jun 2021 | 5 yrs 5 mo late |
| MtriumphKingsville Reality LLP | Pune (M Corp.) | Jun 2021 | Mar 2024 | 5 yrs 5 mo late |
| Mohar PratimaMohar Housing LLP | Talegaon Dabhade (M Cl) | Jun 2021 | Jun 2025 | 5 yrs 5 mo late |
| Palm Nest Phase IINg Rathi Properties LLP | Wagholi | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Platinum BlissPlatinum Realties | Markal | Jun 2021 | Jun 2024 | 5 yrs 5 mo late |
| Platinum ParkSaffron Properties And Schemes | Man | Jun 2021 | Dec 2024 | 5 yrs 5 mo late |
| Prestige Commercial And ResidencialPrestige Promoters And Builders | Pimpri Chinchawad (M Corp.) | Jun 2021 | Jun 2024 | 5 yrs 5 mo late |
| Sai Samarth Construction The West Ford Phase 1Sai Samarth Construction | Pimpale Saudagar | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Saiyog ResidencyYogita Jitendra Rakshe | Rakshewadi | Jun 2021 | Dec 2025 | 5 yrs 5 mo late |
| Shree Gajanan ShrustiPhoenix Developers | Dhayari (Part) | Jun 2021 | Dec 2023 | 5 yrs 5 mo late |
| Silver ParkHakke And Kad Develoeprs | Uruli Devachi | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Shree Sai Hills Phase IIShree Sai Hills | Kesnand | Jun 2021 | Dec 2025 | 5 yrs 5 mo late |
| Vaishnavi ViharVaishnavi Constructions | Ambegaon Bk | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| Vardhaman GoldIntella Homes | Wadagaon (Ct) | Jun 2021 | Dec 2022 | 5 yrs 5 mo late |
| VastushreeKalash Realities And Developers | Katraj | Jun 2021 | Jul 2022 | 5 yrs 5 mo late |
| Woodrock EstatePravin Vishwanath Khairnar | Sadapur | Jun 2021 | Jan 2026 | 5 yrs 5 mo late |
| Aksha ElegenceCrystal Properties | Pimpri Chinchawad (M Corp.) | Jul 2021 | Aug 2022 | 5 yrs 4 mo late |
| Chandrai OrchidManisha Ravindra Landge | Bhosari | Jul 2021 | Jul 2022 | 5 yrs 4 mo late |
| Prabhu ResidencyP W Developers | Dighi | Aug 2021 | Mar 2025 | 5 yrs 3 mo late |
| Classic IconShamrao Sukhadeo Patil | Lohgaon | Sep 2021 | Sep 2021 | 5 yrs 2 mo late |
| Eminence Project 2Naiknavaredevelperspvtltd | Lohgaon | Sep 2021 | Mar 2025 | 5 yrs 2 mo late |
| Utsav Residency Phase IIRoyal Developers | Wagholi | Sep 2021 | Nov 2023 | 5 yrs 2 mo late |
| Shiv HeightsShiv Shakti Developers | Wakad | Oct 2021 | Oct 2021 | 5 yrs 1 mo late |
| Ambika SuvidhaTanuja Kalokhe | Talegaon Dabhade (M Cl) | Oct 2021 | Oct 2021 | 5 yrs 1 mo late |
| Shri ApartmentAscon Developers | Varale | Oct 2021 | Oct 2021 | 5 yrs 1 mo late |
Delayed projects by district
All MaharashtraPune · 2,214Thane · 1,157Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology