2,214 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 7 of 45.

ProjectLocalityPromisedRevisedDelivery
Sai AradhanaSai AgenciesMahalungeMar 2021Sep 20225 yrs 8 mo late
Signature TowerSaarrthi Realty and Infra Limited Liability PartnershipPune (M Corp.)Mar 2021Sep 20235 yrs 8 mo late
Anshulkosmas C And D BuildingAnshulbhosale RealtyHaveliMar 2021Mar 20215 yrs 8 mo late
Balkawade HeightsBalkawade AssociatesKatrajMar 2021Mar 20215 yrs 8 mo late
MeghrajDhanashree Devlopers And BuildersPimpri Chinchawad (M Corp.)Mar 2021Dec 20255 yrs 8 mo late
Sai VillaShivling Vasant JarePimpri Chinchawad (M Corp.)Mar 2021Jun 20245 yrs 8 mo late
Shree Madhavaashram ApartmentShree Gajanan DevelopersBanerMar 2021Mar 20215 yrs 8 mo late
Shree Ram ApartmentsShree Chaitanya DevelopersPimpri Chinchawad (M Corp.)Mar 2021Mar 20215 yrs 8 mo late
Vb CapitolKeystone RealtyPune (M Corp.)Apr 2021Jun 20225 yrs 7 mo late
Yogville Phase IRoyal Yogville VenturesDhayari (Part)Apr 2021Dec 20245 yrs 7 mo late
Anantmegh ATanish Promoters & DevelopersMoshiApr 2021Apr 20225 yrs 7 mo late
Anantmegh BSadguru DevelopersMoshiApr 2021Apr 20225 yrs 7 mo late
Maitreya ResidencyMaitreya Construction And DevelopersBhosariMay 2021Nov 20225 yrs 6 mo late
AmrutvelAmol Narayan BhoreMahalungeMay 2021Dec 20215 yrs 6 mo late
18 Longitude Phase 3G D Square Promoters LLPPunawaleJun 2021Jun 20255 yrs 5 mo late
Global CityDivine DevelopersWadagaon (Ct)Jun 2021Mar 20245 yrs 5 mo late
Anandita ApartmentPotear AssociatesBaramati (M Cl)Jun 2021Jun 20255 yrs 5 mo late
Aapla Ghar Chakan Phase I Amentiy A BldgMaple EstatesNanekarwadi (Ct)Jun 2021Dec 20225 yrs 5 mo late
Balaji Vishwa Building CIdeal PropertiesPune (M Corp.)Jun 2021Dec 20225 yrs 5 mo late
Chindhiwala ComplexChindhiwala DevelopersPune CityJun 2021Dec 20225 yrs 5 mo late
Ganga Bhagyoday D Bldg.Goel Ganga India Pvt LtdPune (M Corp.)Jun 2021Jun 20215 yrs 5 mo late
Goodwill Nirmiti C BuildingUnique Choice VenturesLohgaonJun 2021Dec 20225 yrs 5 mo late
Jai Ganesh 24Siddhivinayak KohinoorBhosariJun 2021Dec 20225 yrs 5 mo late
Laukik IckonLaukik Infrastructure CompanyAmbadvetJun 2021Dec 20255 yrs 5 mo late
MarvellaArush AssociatesPunawaleJun 2021Aug 20235 yrs 5 mo late
Mbm Developers The West Ford Phase 1M B M DevelopersPimpale SaudagarJun 2021Jun 20215 yrs 5 mo late
MtriumphKingsville Reality LLPPune (M Corp.)Jun 2021Mar 20245 yrs 5 mo late
Mohar PratimaMohar Housing LLPTalegaon Dabhade (M Cl)Jun 2021Jun 20255 yrs 5 mo late
Palm Nest Phase IINg Rathi Properties LLPWagholiJun 2021Dec 20225 yrs 5 mo late
Platinum BlissPlatinum RealtiesMarkalJun 2021Jun 20245 yrs 5 mo late
Platinum ParkSaffron Properties And SchemesManJun 2021Dec 20245 yrs 5 mo late
Prestige Commercial And ResidencialPrestige Promoters And BuildersPimpri Chinchawad (M Corp.)Jun 2021Jun 20245 yrs 5 mo late
Sai Samarth Construction The West Ford Phase 1Sai Samarth ConstructionPimpale SaudagarJun 2021Dec 20225 yrs 5 mo late
Saiyog ResidencyYogita Jitendra RaksheRakshewadiJun 2021Dec 20255 yrs 5 mo late
Shree Gajanan ShrustiPhoenix DevelopersDhayari (Part)Jun 2021Dec 20235 yrs 5 mo late
Silver ParkHakke And Kad DeveloeprsUruli DevachiJun 2021Dec 20225 yrs 5 mo late
Shree Sai Hills Phase IIShree Sai HillsKesnandJun 2021Dec 20255 yrs 5 mo late
Vaishnavi ViharVaishnavi ConstructionsAmbegaon BkJun 2021Dec 20225 yrs 5 mo late
Vardhaman GoldIntella HomesWadagaon (Ct)Jun 2021Dec 20225 yrs 5 mo late
VastushreeKalash Realities And DevelopersKatrajJun 2021Jul 20225 yrs 5 mo late
Woodrock EstatePravin Vishwanath KhairnarSadapurJun 2021Jan 20265 yrs 5 mo late
Aksha ElegenceCrystal PropertiesPimpri Chinchawad (M Corp.)Jul 2021Aug 20225 yrs 4 mo late
Chandrai OrchidManisha Ravindra LandgeBhosariJul 2021Jul 20225 yrs 4 mo late
Prabhu ResidencyP W DevelopersDighiAug 2021Mar 20255 yrs 3 mo late
Classic IconShamrao Sukhadeo PatilLohgaonSep 2021Sep 20215 yrs 2 mo late
Eminence Project 2NaiknavaredevelperspvtltdLohgaonSep 2021Mar 20255 yrs 2 mo late
Utsav Residency Phase IIRoyal DevelopersWagholiSep 2021Nov 20235 yrs 2 mo late
Shiv HeightsShiv Shakti DevelopersWakadOct 2021Oct 20215 yrs 1 mo late
Ambika SuvidhaTanuja KalokheTalegaon Dabhade (M Cl)Oct 2021Oct 20215 yrs 1 mo late
Shri ApartmentAscon DevelopersVaraleOct 2021Oct 20215 yrs 1 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology