Sadapur, Pune

Deedo IDDL-PUN-SADAPUR

5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due22 past their date
Median extension54 months25% of registrations extended
Regulatory cases0none on MahaRERA's lists

5 in 10 registrations run late here

4 MahaRERA registrations in Sadapur

2 not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 54 months.

Projects in Sadapur

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Bliss Estates Phase 2Benjamin Michael ManuelDue Dec 2029——
Doodle HomesDoodle Homes LLPDue Dec 2026—60%
IndusArcons Infrastructure1 yr 11 mo late—33%
Woodrock EstatePravin Vishwanath Khairnar5 yrs 5 mo late—69%
Sadapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Arcons Infrastructure1 project
  2. Benjamin Michael Manuel1 project
  3. Doodle Homes LLP1 project
  4. Pravin Vishwanath Khairnar1 project

Sadapur, in questions

How many projects in Sadapur run late?

5 in 10 MahaRERA registrations (2 of 4): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sadapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology