RERA projects in Rakshewadi

2 projects under 2 MahaRERA registrations, registered 2017–2017. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date
54 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172

Projects in Rakshewadi

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Saiyog ResidencyYogita Jitendra RaksheP5210001464420 Dec 201730 Jun 202131 Dec 2025Extended 54 mo0
California HeightsSudhir Ashok MandaleP521000051039 Aug 201731 Dec 201931 Dec 2019Promised date passed0

Other localities in Khed

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sudhir Ashok Mandale1 project
  2. Yogita Jitendra Rakshe1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology