RERA projects in Rajgurunagar (Ct)
39 projects under 39 MahaRERA registrations, registered 2017–2026. 15% have a completion date extended beyond the one promised.
39RERA projects
39Registrations
21Completion still due18 past their completion date
51 monthsMedian extension beyond promised date15% of registrations extended
0Regulatory casesnone on MahaRERA's lists
18Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 7 |
| 2018 | 7 |
| 2019 | 4 |
| 2020 | 1 |
| 2021 | 3 |
| 2022 | 1 |
| 2023 | 8 |
| 2024 | 2 |
| 2025 | 5 |
| 2026 | 1 |
Projects in Rajgurunagar (Ct)
39 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shiv Sonai ResidencyShankara Realty | PM1260002502628 | 6 Mar 2026 | 31 Oct 2028 | — | Not yet due | 0 |
| Shree Jay Ganesh SamrthamShree Jay Ganesh Construction And Developers | PR1260002501747 | 11 Dec 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Shankeshwar WorldNitin Chhaganlal Jain | PM1260002500768 | 15 Sep 2025 | 30 Jun 2030 | — | Not yet due | 0 |
| Rajashri ApartmentsOmkar Sanjay Thigale | P52100080594 | 16 Jun 2025 | 22 Oct 2026 | — | Not yet due | 0 |
| Suraj EkyumSuraj Infra | P52100079997 | 17 Apr 2025 | 1 Jan 2030 | — | Not yet due | 0 |
| Shree Gurudev PlazaVaishnavi Developers | P52100079866 | 28 Mar 2025 | 14 May 2028 | — | Not yet due | 0 |
| Sai Trade CenterDnyaneshwar Tukaram Karande | P52100077682 | 21 Oct 2024 | 7 Mar 2029 | — | Not yet due | 0 |
| Kohinoor HeightsAbbas Ayub Ansari | P52100054625 | 2 Feb 2024 | 1 Oct 2026 | — | Promised date passed | 0 |
| Classic AmrutClassic Infra | P52100054029 | 19 Dec 2023 | 24 Oct 2026 | — | Not yet due | 0 |
| Br 24Anil Ramchandra Rakshe | P52100053879 | 8 Dec 2023 | 22 Aug 2027 | — | Not yet due | 0 |
| Shiv Shakti HeightsSahyadri Buildcon | P52100052070 | 19 Jul 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shree Jay Ganesh AishwaryamMahendra Sayaji Pacharane | P52100052027 | 19 Jul 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Sky View Residencymangesh vasant gundal | P52100051864 | 7 Jul 2023 | 21 Feb 2028 | — | Not yet due | 0 |
| Aarambha VastuSai Shagun Builders And Developers | P52100051037 | 22 May 2023 | 28 Feb 2027 | — | Not yet due | 0 |
| 7 Sagar PlazaSagar Kaluram Patole | P52100050536 | 21 Apr 2023 | 31 Aug 2026 | — | Promised date passed | 0 |
| Sadanand ResidencySeema Pradeep More | P52100048932 | 24 Jan 2023 | 31 Oct 2024 | — | Promised date passed | 0 |
| Shree Gurudev ParkShivaji Namdev Hole | P52100046412 | 22 Jun 2022 | 13 May 2025 | — | Promised date passed | 0 |
| Shiv Ekviramangesh vasant gundal | P52100031026 | 1 Oct 2021 | 21 Aug 2024 | — | Promised date passed | 0 |
| Malhar Srushti HomesSagar Kaluram Patole | P52100030222 | 5 Aug 2021 | 15 Jul 2025 | — | Promised date passed | 0 |
| Shiv ClassicShri Kulswamini Promoters | P52100028449 | 2 Mar 2021 | 30 Jun 2023 | 31 Dec 2026 | Extended 42 mo | 0 |
| Ashanand residency Building D and EAnand Deoram Tambe | P52100026295 | 7 Sep 2020 | 30 Jun 2028 | — | Not yet due | 0 |
| Sai Samrajyasp developers pramotors and builders | P52100023399 | 12 Dec 2019 | 28 Nov 2023 | — | Promised date passed | 0 |
| Ashanand Residency F BuidlingAnand Deoram Tambe | P52100019921 | 13 Mar 2019 | 30 Dec 2024 | — | Promised date passed | 0 |
| Ashanand Residency G BuildingAnand Deoram Tambe | P52100019866 | 7 Mar 2019 | 30 Dec 2024 | — | Promised date passed | 0 |
| Shivraiemangesh vasant gundal | P52100019824 | 5 Mar 2019 | 11 Feb 2024 | — | Promised date passed | 0 |
| SaiplazaAgasti Developers | P52100018259 | 22 Oct 2018 | 31 Mar 2020 | 31 Dec 2025 | Extended 69 mo | 0 |
| Saivyankatesh ResidencySaivyankatesh Residency | P52100018239 | 16 Oct 2018 | 31 Dec 2026 | — | Not yet due | 0 |
| Shivsai ResidancyShivsai Residancy | P52100018000 | 3 Oct 2018 | 30 Apr 2022 | 30 Jan 2027 | Extended 57 mo | 0 |
| Varadh Residency - Phase 2Radiants Properties | P52100016872 | 20 Jun 2018 | 30 Mar 2023 | 31 Dec 2026 | Extended 45 mo | 0 |
| AlankapuriPralhad Laxman Arude | P52100016224 | 24 Apr 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Sadashiv Apartments B and C BuildingVasant Shriram Khedkar | P52100015314 | 15 Feb 2018 | 30 Sep 2020 | — | Promised date passed | 0 |
| Padma VillaGururaj Developers | P52100015039 | 22 Jan 2018 | 26 Jan 2020 | — | Promised date passed | 0 |
| Anand Sagar ResidencyShripad Builders & Developers | P52100014456 | 4 Dec 2017 | 30 Mar 2028 | — | Not yet due | 0 |
| Jigisha GardenKalashri Construction Group | P52100013769 | 25 Oct 2017 | 30 Mar 2022 | 30 Jun 2029 | Extended 87 mo | 0 |
| Star City B WingAmar Builder and Promoters | P52100013488 | 7 Oct 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Sahadu Construction Co.Sahadu Construction Co | P52100012673 | 7 Sep 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Shree Jayganesh DarpanMahendra Sayaji Pacharane | P52100010521 | 31 Aug 2017 | 31 Jul 2019 | — | Promised date passed | 0 |
| Yesai ParkSiddhivinayak Developers | P52100009994 | 23 Aug 2017 | 31 Oct 2027 | 31 Oct 2027 | Not yet due | 0 |
| Playtor Rajgurunagar- Phase 2Playtor Rajgurunagar Developers Private Limited | P52100006327 | 14 Aug 2017 | 30 Sep 2019 | 30 Mar 2023 | Extended 42 mo | 0 |
Other localities in Khed
- Chakan (Ct)61 projects
- Kharabwadi (Ct)23 projects
- Charholi Kh21 projects
- Mahalunge20 projects
- Alandi (M Cl)19 projects
- Medankarwadi12 projects
- Nanekarwadi (Ct)12 projects
- Alandi Rural11 projects
- Holewadi4 projects
- Nighoje4 projects
- Satkarsthal4 projects
- Chimbali3 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Anand Deoram Tambe3 projects
- mangesh vasant gundal3 projects
- Mahendra Sayaji Pacharane2 projects
- Sagar Kaluram Patole2 projects
- Abbas Ayub Ansari1 project
- Agasti Developers1 project
- Amar Builder and Promoters1 project
- Anil Ramchandra Rakshe1 project
- Classic Infra1 project
- Dnyaneshwar Tukaram Karande1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology