RERA projects in Holewadi

4 projects under 4 MahaRERA registrations, registered 2017–2021. 75% have a completion date extended beyond the one promised.

Locality
4RERA projects
4Registrations
1Completion still due3 past their completion date
24 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
10Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20180
20190
20200
20211

Projects in Holewadi

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shri Gurudev Samrajya E WingVaishanavi Builders and DevelopersP521000281154 Feb 202130 Dec 202230 Dec 2022Promised date passed0
Mahalaxmi HeightsMahalaxmi DevelopersP5210001055631 Aug 201730 Dec 202430 Dec 2026Extended 24 mo0
Vaishnavi Builders And DevelopersVaishnavi Builders & DevelopersP5210000853119 Aug 201729 Jul 201928 Jan 2021Extended 18 mo0
Alteza CityS Builders & DevelopersP5210000782518 Aug 201715 Dec 202230 Dec 2025Extended 36 mo0

Other localities in Khed

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Mahalaxmi Developers1 project
  2. S Builders & Developers1 project
  3. Vaishanavi Builders and Developers1 project
  4. Vaishnavi Builders & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology