5 projects under 5 MahaRERA registrations, registered 2017–2024. 80% have a completion date extended beyond the one promised.
Locality
5RERA projects
5Registrations
3Completion still due2 past their completion date
20 monthsMedian extension beyond promised date80% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 1 |
| 2023 | 0 |
| 2024 | 1 |
Projects in Ambadvet
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Urbanbrick Vista Ph-1Mohar Omkar Associates LLP | P52100056271 | 22 May 2024 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Pelican Phase CLaukik Construction Company | P52100033925 | 14 Mar 2022 | 28 Feb 2028 | 28 Jun 2028 | Extended 4 mo | 0 |
| Laukik IckonLaukik Infrastructure Company | P52100014820 | 2 Jan 2018 | 30 Jun 2021 | 31 Dec 2025 | Extended 54 mo | 0 |
| Apex AmbarApex Multicons Pvt. Ltd. | P52100002940 | 4 Aug 2017 | 30 Jun 2027 | 30 Jun 2027 | Not yet due | 0 |
| Pelican Phase BLaukik Construction Company | P52100000949 | 25 Jul 2017 | 31 Dec 2019 | 30 Dec 2022 | Extended 36 mo | 0 |
Other localities in Mulshi
Most active promoters
By projects registered here, as named on MahaRERA.
- Laukik Construction Company2 projects
- Apex Multicons Pvt. Ltd.1 project
- Laukik Infrastructure Company1 project
- Mohar Omkar Associates LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology