Delayed projects in Pune
2,214 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 8 of 45.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Bhosale PrideGanesh Nathu Bhosale | Moshi | Nov 2021 | Jul 2025 | 5 yrs late |
| Silver ParadiseAv Group | Talegaon Dabhade (R) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| ashwamedh residencyCsm Construction | Baramati (M Cl) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| 32nd AvenueSMP Prime Developers | Hinjavadi (Ct) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Alcon RitazzaAlcon | Kharadi | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Annapurna ComplexAara Infraprojects | Talegaon Dabhade (R) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Aapla Ghar KirkatwadiMaple Kuober Realtors | Kirkatwadi | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Aapla Ghar Talegaon Dhamdhere Phase IMaple City Developers | Talegaon Dhamdhere | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Bhagyashree ApartmentOm Associates | Chinchwad | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Baliraj residencySairaj Construction | Rahatani | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Brookview 1,2,3,4,5 LCL 0001Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Chintamani ResidencyArihant Construction | Boripardhi | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Crystal TowerOm Sai Developers | Lonikalbhor | Dec 2021 | Aug 2023 | 4 yrs 11 mo late |
| Centrino LCL0002Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Club View 1,2,3,9,10,11 LCL 0003Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Club View 12, 13 - LCL0005Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Club View 4,5,6Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Creative OrchidCreative Infra Tech | Punawale | Dec 2021 | Jun 2024 | 4 yrs 11 mo late |
| Devanshi TerraceAvenue Developers | Hadapsar | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Devraj Residency Plot No-01Devraj Housing Development Pvt Ltd | Baramati | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Durva HeritageTrimurti Construction | Chinchwad | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Dasve Rd 136,138 LCl 0026Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Delfino 1, 2 - LCL 0006Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Dreams Aryan A B wingsDreams Aryan Faltholders Association A & B | Hadapsar | Dec 2021 | Jun 2023 | 4 yrs 11 mo late |
| Dwarka Sai Paramount New PhaseHaresh Premchand Chandwani | Pimpale Saudagar | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| First Court 1,3 Valley View Court 1, Hilltop Street 126 LCL 0020Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Ganga Fernhill Phase IMeenamani Ganga Builders LLP | Undri | Dec 2021 | Jun 2023 | 4 yrs 11 mo late |
| Ganga Trueno Tower BKappa Realtors LLP | Lohgaon | Dec 2021 | Dec 2022 | 4 yrs 11 mo late |
| Gurukrupa AsterGurukrup Developers | Pune (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Gururatna HeritageThe Creations | Baner | Dec 2021 | Mar 2023 | 4 yrs 11 mo late |
| Hill StreetLavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Hill Street 131, 133, 55, 57, 59, 61 LCL 0024Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Hill View Street 7, 127 ,129, 137 LCL 0015Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Hilltop Street 123 LCL 0029Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Hilltop Street 124, Valley View Ct 3, 11 LCL 0030Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Hilltop Street 93,95,99,105,107,109,111 LCL 0023Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| IndrayaniMangalmurti Construction And Developers | Dehu | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Ishita ResidencyGanesh Machchhindra Sawant | Narhe | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| JaswandRahul Bhagwan Nikam | Pimple Nilakh | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Kulkarni SadanJitendra Motilal Bora | Pimpri Chinchawad (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Kushal Swarnali C1Kushal Adiraj Associates | Kharabwadi (Ct) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Krishna ResidencyJayant Vithoba Mahadik | Balewadi | Dec 2021 | Dec 2025 | 4 yrs 11 mo late |
| Krishna-Kamal SerenityOm Developers | Wagholi | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Lake HouseShaila Bhalchandra Gaikwad | Talegaon Dabhade (M Cl) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Lake View 6,7,8,9 - LCL0007Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Mandke Business CentreVyankatesh Vasudeo Mandke | Pune (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Midas RegencyMidas Constructions | Dehu | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Mlcp Lcl 0011Lavasa Corporation Ltd | Dasave | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Marvel Kyra A AND B BuildingMarvel Sigma Homes Private Limited | Hadapsar | Dec 2021 | Dec 2021 | 4 yrs 11 mo late |
| Oxy Flora Phase 2Oxy Flora Phase 2 | Loni Kand | Dec 2021 | Dec 2022 | 4 yrs 11 mo late |
Delayed projects by district
All MaharashtraPune · 2,214Thane · 1,157Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology