RERA projects in Loni Kand

4 projects under 4 MahaRERA registrations, registered 2018–2025. 50% have a completion date extended beyond the one promised.

Locality
4RERA projects
4Registrations
3Completion still due1 past their completion date
12 monthsMedian extension beyond promised date50% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181
20190
20200
20210
20220
20231
20241
20251

Projects in Loni Kand

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Green CityGreen CityPP126000250057114 Aug 202531 Dec 2026—Not yet due0
Guruvista Phase 3Arham RealtyP5210005589829 Apr 202431 Dec 2031—Not yet due0
Oxy Flora Phase 3Yogesh DevelopersP5210005170027 Jun 202331 Dec 202531 Dec 2026Extended 12 mo0
Oxy Flora Phase 2Oxy Flora Phase 2P521000159409 Apr 201830 Dec 202131 Dec 2022Extended 12 mo1

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Arham Realty1 project
  2. Green City1 project
  3. Oxy Flora Phase 21 project
  4. Yogesh Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology