RERA projects in Uruli Devachi
17 projects under 17 MahaRERA registrations, registered 2017–2026. 65% have a completion date extended beyond the one promised.
Locality
17RERA projects
17Registrations
7Completion still due10 past their completion date
12 monthsMedian extension beyond promised date65% of registrations extended
0Regulatory casesnone on MahaRERA's lists
32Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 5 |
| 2018 | 3 |
| 2019 | 1 |
| 2020 | 2 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 1 |
| 2025 | 2 |
| 2026 | 3 |
Projects in Uruli Devachi
17 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree ParkShri Dattakrupa Infra | PC1260002601812 | 7 Sep 2026 | 30 Jun 2029 | 30 Jun 2029 | Not yet due | 0 |
| Savali PrideSaptsiddhi Associates | PM1260002601707 | 31 Aug 2026 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Taksh Villas Ph IITaksh Properties | PR1260002600693 | 8 Jun 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Ganraj SukhadaGanraj Realty | P52100080386 | 29 May 2025 | 31 May 2030 | 30 Sep 2030 | Extended 4 mo | 0 |
| Taksh VillasTaksh Developers | P52100079934 | 3 Apr 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Vaishnavi City Phase 2 Sector 2Vaishnavi Mahila Unnati Sanstha | P52100076657 | 20 Jun 2024 | 31 May 2026 | 30 Sep 2026 | Extended 4 mo | 0 |
| NisargWaje & Harpale Patil Builders | P52100026279 | 4 Sep 2020 | 7 Aug 2024 | 31 Dec 2027 | Extended 40 mo | 0 |
| Silver Park - B WingHakke And Kad Developers | P52100025181 | 20 Mar 2020 | 30 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Kingston Serene Phase 2 A1, A2, B1 and B2 WingVedant Realtors | P52100019558 | 8 Feb 2019 | 29 Aug 2024 | 29 Aug 2024 | Promised date passed | 0 |
| Tarangana SquareTarangana Square | P52100015822 | 27 Mar 2018 | 6 Jun 2024 | 6 Jun 2024 | Promised date passed | 0 |
| Dev Residency Phase 1Shraddha Construction | P52100015506 | 7 Mar 2018 | 30 Nov 2018 | 30 Nov 2019 | Extended 12 mo | 0 |
| Silver ParkHakke And Kad Develoeprs | P52100014784 | 2 Jan 2018 | 30 Jun 2021 | 29 Dec 2022 | Extended 18 mo | 0 |
| Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase IIVaishnavi Mahila Unnati Sanstha | P52100013110 | 14 Sep 2017 | 30 May 2022 | 30 Nov 2023 | Extended 18 mo | 0 |
| VaradvinayakPandhari Construction | P52100010384 | 24 Aug 2017 | 30 Sep 2020 | 30 Sep 2020 | Promised date passed | 0 |
| Kingston Serene B1 Building Phase 1Vedant Realtors | P52100006952 | 16 Aug 2017 | 31 Dec 2018 | 31 Dec 2018 | Promised date passed | 0 |
| Ganraj HeightsBhudhan Construction | P52100004465 | 9 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Mountain RagaAlacrity Developers Promoters And Builders | P52100002239 | 31 Jul 2017 | 31 Jul 2018 | 31 Jul 2019 | Extended 12 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Vaishnavi Mahila Unnati Sanstha2 projects
- Vedant Realtors2 projects
- Alacrity Developers Promoters And Builders1 project
- Bhudhan Construction1 project
- Ganraj Realty1 project
- Hakke And Kad Develoeprs1 project
- Hakke And Kad Developers1 project
- Pandhari Construction1 project
- Saptsiddhi Associates1 project
- Shraddha Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology