Delayed projects in Nashik
481 MahaRERA projects in Nashik are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 10.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Shakuntala ApartmentGreen Globe Infra | Nandadgaon | Dec 2022 | Jan 2026 | 3 yrs 11 mo late |
| Shree Sakshi ApartmentKalpataru Enterprises | Sinnar | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| Tarangan ApartmentRoger Rajkumar Mundada | Nashik | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Hill WoodsS.v.enterprises | Deolali (Cb) | Jan 2023 | Jan 2023 | 3 yrs 10 mo late |
| Panchvati PrideShri Uma Construction | Nashik (M Corp.) | Jan 2023 | — | 3 yrs 10 mo late |
| Sai City CenterSai Ganesh Buildcon | Manmad (M Cl) | Jan 2023 | Jun 2024 | 3 yrs 10 mo late |
| Sai Vinayak ApartmentYogisai Construction | Nashik (M Corp.) | Jan 2023 | Jan 2023 | 3 yrs 10 mo late |
| Kashiba Business ComplexJayesh Dilipkumar Majithia | Nashik (M Corp.) | Jan 2023 | Jan 2023 | 3 yrs 10 mo late |
| Shivam HeightsOmbuilders and develpers | Nashik (M Corp.) | Jan 2023 | Jan 2023 | 3 yrs 10 mo late |
| Mangal Murti ApartmentPrafull Shankarrao Ahire | Nashik | Mar 2023 | Dec 2023 | 3 yrs 8 mo late |
| Pushpanjali ResidencyArjun Karbhari Kedar | Sinnar(M Cl) | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Akruti Heights Wing AAkruti Buildcon | Nashik (M Corp.) | Mar 2023 | Mar 2026 | 3 yrs 8 mo late |
| Destination OneShree Sainath Land & Development (India) Private Limited | Deolaligaon | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Krishnai ApartmentPadmavati Developers | Deolali (Cb) | Mar 2023 | — | 3 yrs 8 mo late |
| Nisarga Sham Co. Op Hsg. SocietySwaraj Infrastructure | Nashik Road | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Shri Balaji Heights ApartmentLalit Sanjay Agrawal | Nashik (M Corp.) | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Siddhi PridePritish Ramesh Chopda | Nashik (M Corp.) | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Trinity ParkTrinity Constructions | Nashik | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Balaji HeightsAditya Dilip Bhandari | Lasalgaon | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Datta ResidencyDhruved Construction | Nashik | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Dream TowerAjaz Janamuddin Siddiqui | Nashik | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Shweta PrideShweta Constructions | Nashik (M Corp.) | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Suyojit Viridian Vallis Sector C And ISun Infrastructures Pvt Ltd | Nashik | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Balaji ResidencyBalaji Developers | Nashik (M Corp.) | Apr 2023 | Apr 2023 | 3 yrs 7 mo late |
| Sai Vishwa ApartmentMakani Infra Proprietor Nilesh Ishwarbhai Patel | Nashik Road | Apr 2023 | Apr 2023 | 3 yrs 7 mo late |
| Kankariyas AvenueOm Sandeepkumar Kankariya | Nashik | Apr 2023 | Dec 2023 | 3 yrs 7 mo late |
| Nirmal PremM K Group Of Developers | Pimpalgaon Baswant | Apr 2023 | Apr 2023 | 3 yrs 7 mo late |
| Shiv Darshan AppartmentOmbuilders and develpers | Nashik (M Corp.) | Apr 2023 | Apr 2023 | 3 yrs 7 mo late |
| Amrut Vihar ApartmentJayant Ashok Nagmoti | Nashik (M Corp.) | May 2023 | May 2023 | 3 yrs 6 mo late |
| Techsai Industrial ParkTechsai Ites Pvt Ltd | Nashik | May 2023 | May 2023 | 3 yrs 6 mo late |
| Sai NisargDevraj Builders & Land Developers | Sansari | Jun 2023 | — | 3 yrs 5 mo late |
| Shree Sai Krupa ApartmentTulsi Developers | Satpur | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Bagmar PlazaBagmar Pradeep Kantilal HUF | Niphad | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Balaji Heights ApartmentRahul Popatrao Kakulte | Nashik (M Corp.) | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Chaitra SwarChaitra Santosh Hudlikar | Nashik | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Divya Swapna ApartmentKalpana Raju Jagtap | Sinnar(M Cl) | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Sahyadri ParkRakesh Baburao Palde | Sansari | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Sai Srushti Phase-IHarak Patil Developers | Deolali (Cb) | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Sailaxmi ParkJ P Construction | Nashik | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Yashlaxmi TowerStruct-Est Designs Private Limited | Nashik | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Nandanvan ResidencySushil Developers | Nashik (M Corp.) | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Recon Inspire ApartmentRecon Constructions | Nashik (M Corp.) | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| T Galaxy ApartmentTayades Buildcon | Nashik (M Corp.) | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Vedant Pushpa ApartmentManda Vasant Benake | Sinnar(M Cl) | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Shyam OrnateShyam Buildcon | Nashik (M Corp.) | Aug 2023 | Aug 2023 | 3 yrs 3 mo late |
| Vedant Pooja ApartmentPravin Balasaheb Kedar | Sinnar(M Cl) | Aug 2023 | Aug 2023 | 3 yrs 3 mo late |
| Matoshri TowerShri Builders And Developers | Indiranagar | Aug 2023 | Aug 2023 | 3 yrs 3 mo late |
| Saroj Vihar ApartmentRajashree Developers | Nashik | Sep 2023 | Sep 2023 | 3 yrs 2 mo late |
| Vedant Bhakti ApartmentVaijayanta V Nagare and Kamal E Shelke partner of BHAKTI CONSTRUCTION | Sinnar(M Cl) | Sep 2023 | Sep 2023 | 3 yrs 2 mo late |
| Hari Nakshatra Phase IIShree Sainath Land & Development (India) Private Limited | Deolaligaon | Sep 2023 | Sep 2023 | 3 yrs 2 mo late |
Delayed projects by district
All MaharashtraPune · 2,214Thane · 1,157Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology