ProjectLocalityPromisedRevisedDelivery
Lotus Pride ApartmentKalash Developers AssociatesNashikSep 2023Sep 20233 yrs 2 mo late
Shivalik SadguruMadhubhai Babubhai KothiyaNashikSep 2023Sep 20233 yrs 2 mo late
Shree Padmalaya ParkShree Padmalaya ConstructionNashikSep 2023Sep 20233 yrs 2 mo late
Ariba ApartmentMohammad Anjar Inamullah KhanChunchaleOct 2023Oct 20233 yrs 1 mo late
Sai Shivam ApartmentKunal ConstrctionNashik (M Corp.)Oct 2023Oct 20233 yrs 1 mo late
Nirmal VishwaNirmal ConstructionPimpalgaon BaswantNov 2023Nov 20233 yrs late
Hari Krishna Phase IVKbc Global LimitedDeolali (Cb)Nov 2023Dec 20253 yrs late
Gangahari ApartmentApex BuildconNashik (M Corp.)Nov 2023Nov 20233 yrs late
Guru Om ApartmentVimal Builtech Prop Raj Laxman SonawaneNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Godavari Park BShree Sai Shraddha BuildconNashik (M Corp.)Dec 2023—2 yrs 11 mo late
Royal ResidencyMangalam DevelopersNashikDec 2023Dec 20232 yrs 11 mo late
Saakar PlazaBuildsworth EnterprisesNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Samrin ManzilJamil Annoddin Khatik And Ayyub Hanif MalikNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Suyojit Viridian VallisSun Infrastructures Pvt LtdNashikDec 2023—2 yrs 11 mo late
AanganAbh Developers Private LimitedAanandwaliDec 2023Dec 20232 yrs 11 mo late
Abhiraj BlossomAbhijeet Ashok HembadeAanandwaliDec 2023Dec 20232 yrs 11 mo late
Ashtvinayak VillasConcrete SolutionsNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Balaji Pride ApartmentShree Builders And DevelopersNashikDec 2023Dec 20232 yrs 11 mo late
Bhabad ResidencyChabubai Chandrakant SangaleNashikDec 2023Dec 20232 yrs 11 mo late
Dropada HeightsSagar Kedu NatheNashik RoadDec 2023Dec 20232 yrs 11 mo late
G S PrideShree Shivchandra ConstructionNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
GazalShree Yashashree Constructions Private LimitedNashikDec 2023Dec 20232 yrs 11 mo late
Girijatmaj HeightsMangalmurti EstateChehedi BkDec 2023Dec 20232 yrs 11 mo late
Kashi Dham Phase IShivdas Nimba ThankarNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Laxmi HeightsPramod Dudhnath GuptaNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Lambodar AnnexLaxmi BuildersNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Pavan Park A WingGodse CorporationVilholiDec 2023Jun 20242 yrs 11 mo late
Shree Ganesh ApartmentSachin Ashok DhatrakOzar (Ct)Dec 2023Dec 20232 yrs 11 mo late
Shreeja HeightsPalde ConstructionVihitgaonDec 2023Dec 20232 yrs 11 mo late
Shri Datta ParkBalaji DevelopersIgatpuri (M Cl)Dec 2023Dec 20232 yrs 11 mo late
Shubham Shopping CenterShree Ganesh Builders And DevelopersNashikDec 2023Dec 20242 yrs 11 mo late
Skyland HeightsRajlaxmi BuildconNashikDec 2023Dec 20232 yrs 11 mo late
Tanishaka ApartmentR D ConstructionSatpurDec 2023Dec 20232 yrs 11 mo late
Vishwas SkyVishwas RealityNashik (M Corp.)Dec 2023Dec 20232 yrs 11 mo late
Durvankur ViharKanhaiya InfratechNashikFeb 2024Feb 20242 yrs 9 mo late
Samarth Vijay GalaxyAtul Tukaram WaghMakhmalabadFeb 2024Feb 20242 yrs 9 mo late
Mangalmurti ApartmentPranjal Nalin ChandakAanandwaliFeb 2024Feb 20242 yrs 9 mo late
Pushkar Co-Op. Hsg. Soc. Ltd.Raviraj BuildtechIndiranagarFeb 2024Feb 20242 yrs 9 mo late
Tirumal Co-Op. Hsg. Soc.ltdJ And B BuildersNashik (M Corp.)Feb 2024Jan 20252 yrs 9 mo late
GargashrayRadheraman ConstructionNashik (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Sai AshaJay DevelopersNashikMar 2024Dec 20252 yrs 8 mo late
Durvankur GardenNarendra A Jadhav & Jaywant B YeolaNashik (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Shree Madhulaxmi ApartmentPankaj Dinkar ShilwateNashik (M Corp.)Mar 2024Mar 20242 yrs 8 mo late
Samartha ParkMadhukar Bhagirath JadhavSatpurMar 2024Mar 20242 yrs 8 mo late
Samarth ParkMadhukar Bhagirath JadhavNashik (M Corp.)Mar 2024—2 yrs 8 mo late
Shri Ganesh Castle Ph-2Viva Highways LimitedNashik RoadMar 2024—2 yrs 8 mo late
TathagatPavan Vijay PagareIgatpuriMar 2024Mar 20242 yrs 8 mo late
Venus ParkVenus and Astavinayak DevelopersNashikMar 2024Mar 20242 yrs 8 mo late
Anandmay Co-Op Hsg SoceitySai Vaishnavi BuildconNashikMar 2024Mar 20242 yrs 8 mo late
Krishna VillaKrishna ConstructionsTrimbakeshwarMar 2024Mar 20242 yrs 8 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology