Hari Krishna Phase IV

Lapsed

Deolali (Cb), Nashik 422101 |Promoter: Kbc Global Limited

5 Apr 2019Registered with MahaRERA
28 Nov 2023Promised completion
31 Dec 2025Revised completionPushed back 2 years and 1 month
2Buildings
5MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
2
Land area for this project
2,600 sq m (27,986 sq ft)
Permissible built-up area
4,162 sq m (44,802 sq ft)
Sanctioned built-up area
2,465 sq m (26,533 sq ft)
Recreational open space
250 sq m (2,690 sq ft)
Planning authority
Nashik Municipal Corporation
Address
S NO 44/1 AND CTS NO 6825, Deolali, DeolaliPIN 422101
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Hari Krishna Phase IV is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years and 1 month

The latest completion date on record passed 10 months ago.

Registered
5 Apr 2019
Promised
28 Nov 2023
Revised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000203245 Apr 201928 Nov 202331 Dec 2025Kbc Global LimitedProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building A9—
Building (P51600020324)——

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000019
Open Space000023

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building A

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsAS PER APPROVED BUILDING PLAN0%
  • Internal Roads & FootpathsAS PER APPROVED BUILDING PLAN10%
  • Water SupplyTo be obtained from NMC0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)As per approved building plan0%
Show all 28 activitiesShow fewer activities
  • Sewerage (Chamber, Lines, Septic Tank , STP)As per approved building plan15%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Septic Tank With Soak PIT0%
  • Storm Water DrainsAs per approved building plan0%
  • Storm Water DrainsAs per approved plan0%
  • Landscaping & Tree PlantingAs per approved plan0%
  • Landscaping & Tree PlantingAs per approved building plan0%
  • Street LightingSeptic tank with soak pit0%
  • Street LightingAs per approved plan0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterAs per approved building plan0%
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalAs per approved plan0%
  • Solid Waste Management And DisposalAs per approved building plan0%
  • Water conservation /Rain water harvestingRecharge pit with borewell0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsAs per approved building plan0%
  • Fire protection and fire safety requirementsAs per approved plan0%
  • Electrical meter room, sub-station, receiving stationAs per approved plan0%
  • Electrical meter room, sub-station, receiving stationAs per approved building plan0%
  • Aggregate area of recreational Open SpaceAs per approved building plan0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingAs per approved building plan0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

98 documents held by Deedo, 108 filings listed on MahaRERA's project page

Title report

Encumbrance details (5)

Commencement certificate (3)

Show all 206 documentsShow fewer documents

Commencement certificate (3)

Form B (4)

Form 1 (6)

Form 2A (9)

Form 5 (5)

Other (49)

Form 2 (9)

Registration certificate

Allotment letter (2)

Extension certificate

Layout plan

Building plan (2)

Document library

  • Details of encumbrancesEncumbrances Certificate.pdf · uploaded 26 Mar 2019View
  • Copy of the legal title reportTitle Report (6).pdf · uploaded 26 Mar 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement (8).pdf · uploaded 26 Mar 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate (8).pdf · uploaded 26 Mar 2019View
  • Copy of Layout Approval (in case of layout)layout.pdf · uploaded 26 Mar 2019View
  • Declaration in FORM BForm B.pdf · uploaded 26 Mar 2019View
  • Building Plan Approval (IOD)BOI-1.pdf · uploaded 1 Apr 2019View
  • Building Plan Approval (IOD)BOI-2.pdf · uploaded 1 Apr 2019View
  • Proforma of Allotment letterAgreement.pdf · uploaded 1 Apr 2019View
  • Form 2AKrishna IV-Form 2A.pdf · uploaded 15 May 2019View
  • Form 2AForm 2A K4.pdf · uploaded 24 Dec 2019View
  • Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 16 May 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 - Hari Krishna Phase IV_compressed.pdf · uploaded 30 Sep 2020View
  • Details of encumbrancesENC CERTIFICATE-KRISHNA IV.pdf · uploaded 25 May 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)KRISHNA IV20-21.pdf · uploaded 16 Aug 2021View
  • Disclosure of sold/ booked inventoryHari Krishna Phase IV.pdf · uploaded 7 Oct 2021View
  • Disclosure of sold/ booked inventoryHari Krishna Phase 4.pdf · uploaded 8 Oct 2021View
  • Disclosure of sold/ booked inventoryKrishna Phase 4.pdf · uploaded 9 Oct 2021View
  • Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE- Krishna IV (4).pdf · uploaded 12 Oct 2021View
  • Disclosure of sold/ booked inventoryHARI KRISHNA PHASE IV.pdf · uploaded 12 Oct 2021View
  • Form 2AKrishna IV.pdf · uploaded 13 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Krishna IV.pdf · uploaded 13 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Krishna IV.pdf · uploaded 13 Oct 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)KRISHNA 4.pdf · uploaded 22 Jan 2022View
  • Disclosure of sold/ booked inventoryHARI KRISHNA PHASE IV final.pdf · uploaded 11 Mar 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Krishna 4 2a.pdf · uploaded 25 Apr 2022View
  • Disclosure of sold/ booked inventoryHARI KRISHNA IV.pdf · uploaded 29 Apr 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)H Krishna IV.pdf · uploaded 16 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Krishna IV.pdf · uploaded 20 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Krishna IV.pdf · uploaded 20 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Krishna IV.pdf · uploaded 9 Nov 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Krishna IV.pdf · uploaded 9 Nov 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Krishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryHari Krishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryHari Krishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryHari Krishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryKrishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryKrishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryKrishna IV.pdf · uploaded 9 Nov 2023View
  • Disclosure of sold/ booked inventoryKrishna IV.pdf · uploaded 9 Nov 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Hari Krishna IV FY 20-21.pdf · uploaded 14 Dec 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Hari Krishna IV FY 21-22.pdf · uploaded 14 Dec 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Hari Krishna IV FY 22-23.pdf · uploaded 14 Dec 2023View
  • Declaration in FORM BScannerGo_1703077689485_page-0001.pdf · uploaded 20 Dec 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Hari Krishna IV FY 20-21.pdf · uploaded 2 Jan 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Hari Krishna IV FY 21-22.pdf · uploaded 2 Jan 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Hari Krishna IV FY 22-23.pdf · uploaded 2 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)krishna iv.pdf · uploaded 11 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 11 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 11 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)krishna IV.pdf · uploaded 11 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Krishna IV.pdf · uploaded 11 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Krishna IV.pdf · uploaded 11 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Hari Krishna -IV.pdf · uploaded 11 Jan 2024View
  • Declaration in FORM BKrishna iv affidavit cum declaration.pdf · uploaded 12 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 15 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Krishna 4.pdf · uploaded 15 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Hari Krishna IV.pdf · uploaded 15 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Krishna 4.pdf · uploaded 16 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Hari Krishana 4.pdf · uploaded 16 Jan 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Krishan IV.pdf · uploaded 20 Jan 2024View
  • Disclosure of sold/ booked inventoryKrishna IV.pdf · uploaded 23 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna 4.pdf · uploaded 25 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 25 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 25 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 25 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Krishna IV.pdf · uploaded 25 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Krishna 4.pdf · uploaded 25 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Krishna IV.pdf · uploaded 25 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Hari Krishana 4.pdf · uploaded 25 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Hari Krishna -IV.pdf · uploaded 25 Jan 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Krishna IV.pdf · uploaded 27 Jan 2024View
  • CERSAI detailsCERSAI_Search_Report_200295349342_For_Asset_Based_Search_01_02_2024_02_31_34_083.pdf · uploaded 1 Feb 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANKDECLARATION-KRISHNA_page-0001.pdf · uploaded 1 Feb 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsAnnexure 1 (1) (2)_page-0001.pdf · uploaded 1 Feb 2024View
  • Deviation Report with respect to Allotment letterEncumbrance certificate-model allotment letter_page-0001.pdf · uploaded 1 Feb 2024View
  • Deviation Report with respect to model copy of AgreementEncumbrance certificate-model agreement_page-0001.pdf · uploaded 1 Feb 2024View
  • a Details of encumbrances concerned to FinanceEncumbrance certificate finance_page-0001.pdf · uploaded 1 Feb 2024View
  • a Details of encumbrances concerned to FinanceEncumbrance certificate (1)_page-0001.pdf · uploaded 1 Feb 2024View
  • b Details of encumbrances concerned to LegalEncumbrance certificate finance_page-0001.pdf · uploaded 1 Feb 2024View
  • b Details of encumbrances concerned to LegalEncumbrance certificate (1)_page-0001.pdf · uploaded 1 Feb 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Hari Krishna IV.pdf · uploaded 2 Jun 2024View
  • Disclosure of sold/ booked inventoryHARI KRISHNA PHASE IV.pdf · uploaded 2 Jun 2024View
  • Disclosure of sold/ booked inventoryHARI KRISHNA PHASE IV JUNE.pdf · uploaded 6 Feb 2025View
  • Disclosure of sold/ booked inventoryHARI KRISHNA PHASE IV SEPT.pdf · uploaded 6 Feb 2025View
  • Disclosure of sold/ booked inventoryHARI KRISHNA PHASE IV DEC.pdf · uploaded 6 Feb 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June24.pdf · uploaded 19 Feb 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 sept24.pdf · uploaded 19 Feb 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 300924.pdf · uploaded 19 Feb 2025View
  • Declaration in FORM Bform b -krishna.pdf · uploaded 26 Mar 2025View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 march.pdf · uploaded 26 Mar 2025View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 June.pdf · uploaded 26 Mar 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A June.pdf · uploaded 26 Mar 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Dec.pdf · uploaded 26 Mar 2025View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Sept.pdf · uploaded 26 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March.pdf · uploaded 26 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec.pdf · uploaded 26 Mar 2025View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Dec.pdf · uploaded 26 Mar 2025View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)KBC Global Rera Form 5.pdf · uploaded 27 Mar 2025View

Promoter documents

  • Legal Title reportTitle Report (6).pdf · uploaded 26 Mar 2019View
  • Declaration Form BForm B.pdf · uploaded 26 Mar 2019View
  • Declaration Form BScannerGo_1703077689485_page-0001.pdf · uploaded 20 Dec 2023View
  • Declaration Form BKrishna iv affidavit cum declaration.pdf · uploaded 12 Jan 2024View
  • Declaration Form Bform b -krishna.pdf · uploaded 26 Mar 2025View

Technical documents

  • Layout Approvallayout.pdfView
  • Building Plan ApprovalBOI-1.pdfView
  • Building Plan ApprovalBOI-2.pdfView

Proforma allotment letter

  • Proforma allotment letterAgreement.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Deolali (CB), Nashik taluka

Survey, CTS, gat or plot numbers

44/16825CTS NO 6825S NO 44/1

As published on MahaRERA's project page

S NO 44/1 AND CTS NO 6825

Boundaries

North
Sr No 45 And Cts No 6823 And 6820
South
Sr No 8 And Cts 6826
East
Sr No 2 And Cts No 6827
West
Sr No 4 And D P Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant Themaskar—
Chartered accountantHSB & Go.—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology