Kbc Global Limited
Company or firm · 12 projects · 12 MahaRERA registrations
Also appears as Karda Constructions Limited
12Projects12 RERA registrations
0Completedas reported on MahaRERA project pages
58%Kept RERA date7 of 12 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 5 extended
5Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Hari Sparsh IIP51600000119 | Bhagur Rural | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Hari VatikaP51600000220 | Sansari | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Hari Sparsh Phase IIIP51600000225 | Bhagur Rural | 2017 | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Hari Sanskruti Phase IIP51600000551 | Deolaligaon | 2017 | Certificate Signed | 28 Aug 2024 | 28 Aug 2024 | On date |
| Hari BhaktiP51600000585 | Deolali (Cb) | 2017 | Certificate Signed | 30 Jun 2021 | 31 Dec 2024 | +42 months |
| Hari Vishwa D BuildingP51600001205 | Nashik | 2017 | Certificate Signed | 31 Dec 2019 | 31 Aug 2023 | +44 months |
| Hari Laxmi Phase IIP51600005165 | Vihitgaon | 2017 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Hari NamanP51600000228 | Deolaligaon | 2017 | Certificate Signed | 31 Dec 2017 | 10 Sep 2018 | +9 months |
| Hari AnandP51600001348 | Nashik | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Hari VruddhiP51600018377 | Deolaligaon | 2018 | Certificate Signed | 30 Dec 2021 | 28 Dec 2025 | +48 months |
| Hari NisargP51600018648 | Nashik | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Hari Krishna Phase IVP51600020324 | Deolali (Cb) | 2019 | Lapsed | 28 Nov 2023 | 31 Dec 2025 | +25 months |
Show all 12 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 12 registrations
Track record notes
- 7 of 12 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 48 months, for Hari Vruddhi (P51600018377).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- complaintComplaint CC001000000080400 · Hari Krishna Phase IV · P51600020324
- complaintComplaint CC001000000080402 · Hari Krishna Phase IV · P51600020324
- complaintComplaint CC001000000080406 · Hari Krishna Phase IV · P51600020324
- complaintComplaint CC001000000080407 · Hari Krishna Phase IV · P51600020324
- complaintComplaint CC001000000090412 · Hari Krishna Phase IV · P51600020324
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology