Kbc Global Limited

Company or firm · 12 projects · 12 MahaRERA registrations

Also appears as Karda Constructions Limited

12Projects12 RERA registrations
0Completedas reported on MahaRERA project pages
58%Kept RERA date7 of 12 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 5 extended
5Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hari Sparsh IIP51600000119Bhagur Rural2017Certificate Signed31 Mar 201831 Mar 2018On date
Hari VatikaP51600000220Sansari2017Certificate Signed30 Jun 201830 Jun 2018On date
Hari Sparsh Phase IIIP51600000225Bhagur Rural2017Certificate Signed30 Jun 201930 Jun 2019On date
Hari Sanskruti Phase IIP51600000551Deolaligaon2017Certificate Signed28 Aug 202428 Aug 2024On date
Hari BhaktiP51600000585Deolali (Cb)2017Certificate Signed30 Jun 202131 Dec 2024+42 months
Hari Vishwa D BuildingP51600001205Nashik2017Certificate Signed31 Dec 201931 Aug 2023+44 months
Hari Laxmi Phase IIP51600005165Vihitgaon2017Certificate Signed30 Dec 202430 Dec 2024On date
Hari NamanP51600000228Deolaligaon2017Certificate Signed31 Dec 201710 Sep 2018+9 months
Hari AnandP51600001348Nashik2017Certificate Signed31 Dec 201731 Dec 2017On date
Hari VruddhiP51600018377Deolaligaon2018Certificate Signed30 Dec 202128 Dec 2025+48 months
Hari NisargP51600018648Nashik2018Certificate Signed30 Dec 202230 Dec 2022On date
Hari Krishna Phase IVP51600020324Deolali (Cb)2019Lapsed28 Nov 202331 Dec 2025+25 months
Show all 12 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hari Sparsh IIOn date
  • Hari VatikaOn date
  • Hari Sparsh Phase IIIOn date
  • Hari Sanskruti Phase IIOn date
  • Hari Bhakti+42 mo
  • Hari Vishwa D Building+44 mo
  • Hari Laxmi Phase IIOn date
  • Hari Naman+9 mo
  • Hari AnandOn date
  • Hari Vruddhi+48 mo
Show all 12 registrations
  • Hari NisargOn date
  • Hari Krishna Phase IV+25 mo

Track record notes

  • 7 of 12 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Hari Vruddhi (P51600018377).
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology