Skip to content
Others · 8 buildings · 115 unitsRERA P51600000585

Hari Bhakti

Deedo IDDP-NSK-HMZ2

Completion was pushed back 3 years and 6 months to Dec 2024, and that date has passed too; no MahaRERA orders on record; 35% of its units are booked.

Deolali (Cb), Nashik 422101 · by Karda Constructions Limited, Kbc Global Limited

Delivery5 yrs 5 mo latePromised Jun 2021 · revised Dec 2024 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales35% booked40 of 115 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 3 years and 6 months to Dec 2024, and that date has passed too

  • This projectRegistered 18 Jul 2017, completion promised 30 Jun 2021, revised to 31 Dec 2024, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

8 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600000585
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160000058518 Jul 201730 Jun 202131 Dec 2024Kbc Global LimitedProject page
Documents121

56 documents held by Deedo, 65 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other (54)

Show all 121 documentsShow fewer documents

Other (54)

Legal

  • Legal Title report2_Supplementary Search report - Hari bhakti.pdf · uploaded 12 Jul 2017Source
  • Declaration Form B6_Form B Promoter.pdf · uploaded 12 Jul 2017Source

Migrated

  • 1 Copy of the legal title report2_Supplementary Search report - Hari bhakti.pdf · uploaded 12 Jul 2017Source
  • 1 Details of encumbrances3_Encumbrances Hari Bhakti-min.pdf · uploaded 12 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)4_LayoutApproval.pdf · uploaded 12 Jul 2017Source
  • 1 Building Plan Approval (IOD)4_LayoutApproval.pdf · uploaded 12 Jul 2017Source
  • 1 Declaration in FORM B6_Form B Promoter.pdf · uploaded 12 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)7_Bhakti Certificate-min.pdf · uploaded 12 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11_Eng Cert-Hari Bhakti.pdf · uploaded 12 Jul 2017Source
  • 1 Proforma of Allotment letter5_AllotmentAgreement-ilovepdf-compressed.pdf · uploaded 12 Jul 2017Source
  • 1 Certificates of CA (Form 3)9_Bhakti -ca certificate.pdf · uploaded 14 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 21 Apr 2018Source
  • 1 Certificates of CA (Form 5)Form 5 - Hari Bhakti-ilovepdf-compressed.pdf · uploaded 30 Sep 2018Source
  • 2 Certificates of CA (Form 5)Form 5 - Hari Bhakti_compressed.pdf · uploaded 30 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 - Hari Bhakti_compressed.pdf · uploaded 30 Sep 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 - Hari Bhakti-18-19.pdf · uploaded 1 Oct 2020Source
  • 1 Declaration about Commencement CertificateBHAKTI-DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 19 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Bhakti 19-20.pdf · uploaded 19 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Bhakti 20-21.pdf · uploaded 19 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 7 Oct 2021Source
  • 2 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 8 Oct 2021Source
  • 3 Disclosure of sold/ booked inventoryHARI BHAKTI (1).pdf · uploaded 12 Oct 2021View
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Bhakti.pdf · uploaded 13 Oct 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Bhakti.pdf · uploaded 13 Oct 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Bhakti.pdf · uploaded 14 Oct 2021Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)BHAKTI.pdf · uploaded 14 Oct 2021Source
  • 4 Disclosure of sold/ booked inventoryHARI BHAKTI.pdf · uploaded 15 Oct 2021Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)HARI BHAKTI.pdf · uploaded 22 Jan 2022Source
  • 5 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 12 Feb 2022Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Hari bhakti 2a.pdf · uploaded 25 Apr 2022Source
  • 6 Disclosure of sold/ booked inventoryHARI BHAKTI.pdf · uploaded 29 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Reco covering letter - 30062022 (1).pdf · uploaded 23 Jan 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)3009BHAKTI.pdf · uploaded 23 Jan 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)3112BHAKTI.pdf · uploaded 23 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) (1).pdf · uploaded 23 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) (1).pdf · uploaded 23 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)hari bhakti.pdf · uploaded 17 Feb 2024Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 7 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 8 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 9 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 10 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 11 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 12 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 13 Disclosure of sold/ booked inventoryHari Bhakti.pdf · uploaded 17 Feb 2024Source
  • 2 Details of encumbrancesEncumbrance certificate (1)_page-0001_page-0001.pdf · uploaded 23 Feb 2024Source
  • 3 a Details of encumbrances concerned to FinanceEncumbrance certificate finance_page-0001_page-0001.pdf · uploaded 23 Feb 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance certificate finance_page-0001_page-0001.pdf · uploaded 23 Feb 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank acc details (4)_page-0001.pdf · uploaded 23 Feb 2024Source
  • 1 Deviation Report with respect to Allotment letterEncumbrance certificate-model allotment letter_page-0001_page-0001.pdf · uploaded 23 Feb 2024Source
  • 1 Deviation Report with respect to model copy of AgreementEncumbrance certificate-model agreement_page-0001_page-0001.pdf · uploaded 23 Feb 2024Source
  • 8 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Hari Bhakti.pdf · uploaded 26 Apr 2024Source
  • 14 Disclosure of sold/ booked inventoryHARI BHAKTI.pdf · uploaded 29 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryHARI BHAKTI JUNE.pdf · uploaded 28 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryHARI BHAKTI SEPT.pdf · uploaded 28 Feb 2025Source
  • 3 Disclosure of sold/ booked inventoryHARI BHAKTI DEC.pdf · uploaded 28 Feb 2025View

Technical

  • Document4_LayoutApproval.pdf · uploaded 12 Jul 2017Source
  • Document4_LayoutApproval.pdf · uploaded 12 Jul 2017Source

Technical (Architect)

  • Document7_Bhakti Certificate-min.pdf · uploaded 12 Jul 2017Source

Technical (Engineer)

  • Document11_Eng Cert-Hari Bhakti.pdf · uploaded 12 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 37/1C, Survey No 37/1B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Hall, Office space, Shop, 2BHK, 3BHK115 units in all
Address
Survey No 37/1B and 37/1C, Datta Mandir road, Datta Mandir roadPIN 422101
Village
Deolali (CB), Nashik taluka
Land area for this project
5,066 sq m (54,532 sq ft)
Permissible built-up area
8,400 sq m (90,417 sq ft)
Sanctioned built-up area
5,408 sq m (58,213 sq ft)
Recreational open space
507 sq m (5,457 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

37/1CSurvey No 37/1B

Land as published on MahaRERA's project page

Survey No 37/1B and 37/1C

Boundaries

North
Adj Cts No 6889 And S No 37 1 C Cts No 6858
South
APP LAYOUT NO LND FINAL 13 AND 18 M Wide DP Rd
East
12 M Wide DP Road
West
CTS No 6857 Part and S No 30

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking115 units

40 of 115 units booked (35%), as the promoter reported to MahaRERA

Hall · 2 unitsOffice space · 11 unitsShop · 9 units2BHK · 45 units3BHK · 48 units
BuildingTypeCarpet areaUnitsBooked
AHall148.35 sq m · 1,597 sq ft10
AHall159.41 sq m · 1,716 sq ft11
AOffice space23.14 sq m · 249 sq ft30
AOffice space38.95 sq m · 419 sq ft10
AOffice space39.45 sq m · 425 sq ft10
AOffice space42.21 sq m · 454 sq ft11
AOffice space43.63 sq m · 470 sq ft50
AShop23.23 sq m · 250 sq ft31
Show all 18 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
AShop42.18 sq m · 454 sq ft11
AShop43.63 sq m · 470 sq ft52
B2BHK57.54 sq m · 619 sq ft208
B2BHK57.97 sq m · 624 sq ft227
B2BHK69.29 sq m · 746 sq ft11
B2BHK97.65 sq m · 1,051 sq ft10
B2BHK98.16 sq m · 1,057 sq ft10
C3BHK74.31 sq m · 800 sq ft2410
C3BHK75.86 sq m · 817 sq ft207
C3BHK75.98 sq m · 818 sq ft41

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRasik Bothara—
EngineerR G Birla—
OtherVasant Bhagat—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Deolali (Cb)

All 50 projects in Deolali (Cb) · Compare Hari Bhakti with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology