Residential / Group Housing · 2 buildings · 17 unitsRERA P51600020682

Krishnai Apartment

Deedo IDDP-NSK-PYX4

Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 59% of its units are booked.

Deolali (Cb), Nashik 422401 · by Padmavati Developers

Delivery3 yrs 8 mo past duePromised Mar 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales59% booked10 of 17 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 3 May 2019, completion promised 30 Mar 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600020682
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000206823 May 201930 Mar 2023—Padmavati DevelopersProject page
Documents44

21 documents held by Deedo, 23 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Registration certificate

Form 5 (4)

Show all 44 documentsShow fewer documents

Form 5 (4)

Other (7)

Layout plan

Building plan (3)

Allotment letter

Document library

  • Declaration in FORM BformB.pdf · uploaded 29 Mar 2019View
  • Details of encumbrancesno emcumbrances.pdf · uploaded 29 Mar 2019View
  • Commencement Certificates / NA Order for plotted developmentcommesment certificte.pdf · uploaded 29 Mar 2019View
  • Copy of the legal title reportsearch report-compressed.pdf · uploaded 29 Mar 2019View
  • Building Plan Approval (IOD)iod 1.pdf · uploaded 29 Mar 2019View
  • Building Plan Approval (IOD)iod 2.pdf · uploaded 29 Mar 2019View
  • Building Plan Approval (IOD)plan explanation.pdf · uploaded 29 Mar 2019View
  • Copy of Layout Approval (in case of layout)layout.pdf · uploaded 29 Mar 2019View
  • Proforma of Allotment letterdraft-agreement-padmavati_developers.PDF · uploaded 29 Mar 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA FORM 5 19-20.pdf · uploaded 14 Mar 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA FORM 5 20-21.pdf · uploaded 14 Mar 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Rera FORM 5 21-22.pdf · uploaded 14 Mar 2023View
  • Disclosure of sold/ booked inventoryInventory status P Developers.pdf · uploaded 7 Aug 2024View
  • Other – LegalShigwe completion.pdf · uploaded 7 Aug 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Padmavati FORM 5 22-23.pdf · uploaded 1 Dec 2024View

Promoter documents

  • Declaration Form BformB.pdf · uploaded 29 Mar 2019View
  • Legal Title reportsearch report-compressed.pdf · uploaded 29 Mar 2019View

Technical documents

  • Building Plan Approvaliod 1.pdfView
  • Building Plan Approvaliod 2.pdfView
  • Building Plan Approvalplan explanation.pdfView
  • Layout Approvallayout.pdfView

Other legal documents

  • Other – LegalShigwe completion.pdfView

Proforma allotment letter

  • Proforma allotment letterdraft-agreement-padmavati_developers.PDFView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 157/3 shigwebahula

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Address
157/3 shigwebahula, off Dhondi Road, ShigwebahulaPIN 422401
Village
Deolali (CB), Nashik taluka
Land area for this project
1,900 sq m (20,451 sq ft)
Permissible built-up area
950 sq m (10,226 sq ft)
Sanctioned built-up area
945 sq m (10,176 sq ft)
Recreational open space
190 sq m (2,045 sq ft)
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

157/3 shigwebahula

Land as published on MahaRERA's project page

157/3 shigwebahula

Boundaries

North
S No 157-2
South
Road
East
Nalla
West
S No 3

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking20 parking spaces

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space000020

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Krishnai

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsConcrete or Block road0%
  • Water Supplybore water and cantonment water supply0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Chamber line and septic tank0%
  • Storm Water Drainsalong internal road0%
  • Landscaping & Tree PlantingBorder Planting0%
  • Street Lightingalong internal road0%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingOpen Parking0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNitin K Salve—

Source: MahaRERA project page. Contact details are not shown.