Delayed projects in Maharashtra

8,426 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 13 of 169.

ProjectLocalityPromisedRevisedDelivery
Anand BlossomAnand AssociatesNashik (M Corp.)NashikAug 2019Aug 20197 yrs 3 mo late
Laxmi Nagar Phase IIVijayalaxmi DevelopersShendrabanAurangabadAug 2019Aug 20197 yrs 3 mo late
Shree Swami Samarth DarshanAshish Mangesh ChikhaleKhed (M Cl)RatnagiriAug 2019Jun 20237 yrs 3 mo late
Narsinh ResidencyNarsinh DevelopersPune (M Corp.)PuneAug 2019Aug 20197 yrs 3 mo late
Kedari LandmarkShree Ganesha EnterprisesPune (M Corp.)PuneAug 2019Mar 20267 yrs 3 mo late
Kini TowerShubh Shwet DevelopersVasaivirar City (M Corp)PalgharAug 2019Mar 20267 yrs 3 mo late
Vidhya DarshanAditya EnterprisesKurlaMumbai SuburbanAug 2019Feb 20217 yrs 3 mo late
A and O BELLEVUEAshapura Homes Private LimitedAndheriMumbai SuburbanAug 2019Dec 20217 yrs 3 mo late
Nirmal Lifestyle-Blu Diamond-One EditionNirmal Lifestyle LtdKurlaMumbai SuburbanAug 2019Dec 20247 yrs 3 mo late
Rohit PinnacleRohit InfraPimpri Chinchawad (M Corp.)PuneAug 2019Feb 20217 yrs 3 mo late
Sai Siddhi ResidencyPandurang Laxman YadavKodoli (Ct)SataraAug 2019Nov 20227 yrs 3 mo late
Siddhachal ResidencyHitech DevelopersMirabhayandar (M Corp.)ThaneAug 2019Jun 20227 yrs 3 mo late
Swami SankulPrarambh AssociatesPen (M Cl)RaigarhAug 2019Aug 20197 yrs 3 mo late
Grand OrchidShree Siddhivinayak Construction GroupSasvad (M Cl)PuneSep 2019Feb 20217 yrs 2 mo late
Parisparsh SwapnotsavParisparshShahapur (Ct)ThaneSep 2019Sep 20197 yrs 2 mo late
The CosmopolisVishal Sanjay GalandeHadapsarPuneSep 2019Oct 20207 yrs 2 mo late
Simran HeightsVikas Narayan RaikarKurlaMumbai SuburbanSep 2019Mar 20257 yrs 2 mo late
Arihant ResidencyArihant Infrastructure CompanyKurlaMumbai SuburbanSep 2019Mar 20267 yrs 2 mo late
Chaitanya High PointChaitanya DevelopersBanerPuneSep 2019Mar 20217 yrs 2 mo late
Chintamani VillaChintamani VillaManjari BkPuneSep 2019Sep 20197 yrs 2 mo late
Hdil Paradise CityHousing Development And Infrastructure LtdMahimPalgharSep 2019Sep 20197 yrs 2 mo late
Mangalmurti GalaxyShree Mangalmurti EnterprisesDombivliThaneSep 2019Sep 20227 yrs 2 mo late
N G Grand Plaza Phase IIOm Namah Shivay Developers Private LimitedGhansoliThaneSep 2019Sep 20197 yrs 2 mo late
NandanvanSaikrupa Builders And DevelopersManeriSindhudurgSep 2019Mar 20217 yrs 2 mo late
New Murli Malhar ChsGuinea Global Builders And DevelopersKurlaMumbai SuburbanSep 2019Mar 20217 yrs 2 mo late
Safal OnerioSanjay Dattatray DapodikarWakadPuneSep 2019Mar 20217 yrs 2 mo late
Sakshat NavkarNavkar Infra ProjectsBorivaliMumbai SuburbanSep 2019May 20257 yrs 2 mo late
SerreneNirmaann Encon DevelopersUndriPuneSep 2019Jun 20237 yrs 2 mo late
Shrushti ApartmentRenuka ConstructionsTalegaon Dabhade (M Cl)PuneSep 2019Sep 20197 yrs 2 mo late
Savitri ViewSavitri GroupNavi Mumbai (M Corp.)ThaneSep 2019Sep 20197 yrs 2 mo late
Shalom RegencyJacob GeorgeUranRaigarhSep 2019Jun 20237 yrs 2 mo late
Raleraskar HeightsNitin Sadanand KulkarniSolapur (M Corp.)SolapurOct 2019Oct 20197 yrs 1 mo late
MuktanganShraddha RealityDighiPuneOct 2019Apr 20217 yrs 1 mo late
New Simit ApartmentReliable Buildhights LLPBorivaliMumbai SuburbanOct 2019Dec 20247 yrs 1 mo late
Royal PalaceSunil Mahadev PusalkarGoregaonRaigarhOct 2019Oct 20197 yrs 1 mo late
OrchidSiroyaFM Constructions Pvt LtdAndheriMumbai SuburbanOct 2019Oct 20197 yrs 1 mo late
Hiralaxmi ApartmentShree Sadguru DevelopersThane (M Corp.)ThaneOct 2019Oct 20237 yrs 1 mo late
VatsalyabhumiVedbhumi Builders And Developers Pvt. LtdNagpur (M Corp.)NagpurOct 2019Dec 20257 yrs 1 mo late
759Sahaj DevelopersWard FnorthMumbai CityOct 2019Sep 20257 yrs 1 mo late
Building on Sub plot - D, CTS No 101/B of village GoregaonSkyline Construction Co.BorivaliMumbai SuburbanOct 2019Oct 20217 yrs 1 mo late
Cd Plot No 7SD SVP Nagar Redevelopment Private LimitedAndheriMumbai SuburbanOct 2019Oct 20217 yrs 1 mo late
Citrus ParkFiltrum Infrastructure Pvt LtdShirwalSataraOct 2019Dec 20237 yrs 1 mo late
Divine PathDivine EnterprisesNeralRaigarhOct 2019Oct 20217 yrs 1 mo late
Highland Springs B4- E WingSiddhi Real Estate DevelopersThane (M Corp.)ThaneOct 2019Oct 20197 yrs 1 mo late
Mulund Ravi KailashM Patankar Build Cons Private LimitedKurlaMumbai SuburbanOct 2019Apr 20227 yrs 1 mo late
Navkala BharatiLakshmiconstructionAndheriMumbai SuburbanOct 2019Sep 20257 yrs 1 mo late
Rachana SukrutRachana ProjectsDombivliThaneOct 2019Oct 20197 yrs 1 mo late
Shree Township Building - 5, Type-A, Being No.11Shree ConstructionKambalgaonPalgharOct 2019Oct 20217 yrs 1 mo late
Shukratara ChslHariom DevelopersAndheriMumbai SuburbanOct 2019Oct 20247 yrs 1 mo late
Eden ParkProminent Builders And DevelopersTaloje PanchnadRaigarhNov 2019Nov 20217 yrs late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology