Chikanghar, Thane
Deedo IDDL-THN-CHIKANGHAR9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects113
Registrations118some projects hold several
Completion still due6355 past their date
Median extension4 months56% of registrations extended
Regulatory cases7on 4 projects
9 in 10 registrations run late here
118 MahaRERA registrations in Chikanghar
2 completed12 not yet due51 extended, not yet due53 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Chikanghar
113 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shivneri Park Co Op Hsg Soc LtdShree Swastik Constructions | Due Mar 2027 | — | 23% |
| Nav Ashokvan Cooperative Housing Society LtdGagan Developers And Engineers | Completed | — | — |
| Proposed Residential, Commercial Bldgs on Plot bearing OLD 96 C 2-pt - Mayur MahalMayur Group (Rd) | Due Oct 2027, extended 4 mo | — | — |
| Vaishnavi HeightsVaishnavi Construction | Due Apr 2027, extended 4 mo | — | — |
| Atharva HeightsJai Shreegurutatvam Engineers And Developers | Due Dec 2026 | — | 62% |
| Sunder DarshanDinesh Laxman Sonavane | Completed | — | 58% |
| Vijaya EliteElite Associates | 1 yr 11 mo late | — | 39% |
| Vedant ConnectMohan Hardasmal Tharwani | Due Apr 2027, extended 4 mo | — | 34% |
| Anand EleganzaV N Constructions | 8 mo late | — | 36% |
| TanishqPhoenix Realty | Due Apr 2027 | — | 18% |
| Samarpan HeightsJayawant Balaram Bhoir Patil | Due Apr 2027, extended 4 mo | — | 21% |
| Patel MountPatel Group & Co | Due Apr 2027, extended 4 mo | — | 17% |
| AvdhutS.k. Homes Builder & Developers | Due Apr 2027, extended 4 mo | — | — |
| Meghana Co. Op. Hsg. Soc.A. V. Gajare | 1 yr 7 mo late | — | 42% |
| Chavan AdvaitamSaideep Constructions | Due Apr 2027, extended 4 mo | — | 47% |
| Mangeshi RoyaleMangesh Dashrath Gaikar | Completed | — | 28% |
| Seasons OneUnique Enterprises | Due Apr 2029, extended 4 mo | — | 40% |
| Mangeshi MarvelMangesh Dashrath Gaikar | Completed | — | 3% |
| Mangeshi WoodsMangesh Dashrath Gaikar | Completed | — | 45% |
| Mangeshi ImperialMangesh Dashrath Gaikar | 6 mo late | — | — |
| Corner StoneSarvodaya Amrut LLP | Due Apr 2027, extended 4 mo | — | 60% |
| Omkar Matruchaya ApartmentOmkar Properties | 1 yr 2 mo late | — | 69% |
| Tycoons Square Avenue I Tower ATycoons Avanti Projects LLP | 1 yr 4 mo late | — | 92% |
| Kisan HeightsPravin Kisan Bhoir | Due Jan 2028, extended 4 mo | — | 32% |
| Gayatri NiwasGayatri Builders | Completed | — | 100% |
Nearby: other villages in Kalyan
Most active promoters
- Mangesh Dashrath Gaikar5 projects
- Stonecrafters4 projects
- Tycoons Avanti Projects Llp4 projects
- Aarohi Development Corporation2 projects
- Dinesh Laxman Sonavane2 projects
- Gayatri Builders2 projects
- Mayur Group (Rd)2 projects
- Mayur Group (Rd)2 projects
- Namdev Construction2 projects
- Shakti Realtors2 projects
Chikanghar, in questions
How many projects in Chikanghar run late?
9 in 10 MahaRERA registrations (104 of 118): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chikanghar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology