Chikanghar, Thane
Deedo IDDL-THN-CHIKANGHAR6 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects108
Registrations113some projects hold several
Completion still due6053 past their date
Median extension4 months58% of registrations extended
Regulatory cases7on 4 projects
9 in 10 registrations run late here
113 MahaRERA registrations in Chikanghar
2 completed9 not yet due51 extended, not yet due51 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Chikanghar
108 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Om VardhastaZk Realty | Due Apr 2028, extended 4 mo | — | — |
| Empire TowerEkadanta Developers | Due Apr 2027, extended 4 mo | — | 0% |
| Shirish ResidencyRl Constructions | Due Apr 2027, extended 4 mo | — | — |
| Mauli PrideMauli Krupa Developers | Due Apr 2028, extended 4 mo | — | — |
| Om PushpanjaliR B Construction | Due Apr 2027, extended 4 mo | — | — |
| Swami Datta KrupaDinesh Laxman Sonawane | Completed | — | — |
| Ronak Solitaire /Wing AGayatri Associates | Due Jul 2029, extended 4 mo | — | — |
| Bhushan Anand Co Op Hsg SocDinesh Laxman Sonavane | 1 mo late | — | 37% |
| Ammu Co-Op Housing Society LtdStonecrafters | Due Jul 2027, extended 4 mo | — | 31% |
| Vishnu BlissLegacy Builders & Innovators | Completed | — | — |
| Seasons MayfairTiruma Sai Builders | Due Apr 2027, extended 4 mo | — | 35% |
| Harold Co-Op Housing SocietyStonecrafters | Due Apr 2027, extended 4 mo | — | 0% |
| Ambika Prassana ChsBuilt In Reality | 2 yrs 4 mo late | — | 79% |
| Ishanvi Ashapura TowerIshanvi Ashapura Developers | Due Jan 2027, extended 4 mo | — | — |
| Keshar Aagan Cooperative Housing SocietyGagan Homes | Due Jan 2029, extended 4 mo | — | — |
| Daffodil Co- Op Housing Society LtdStonecrafters | Due Apr 2027, extended 4 mo | — | 25% |
| The Pyramid OnePyramid Developers | 1 mo late | — | 19% |
| Shreesha HeightsVastunirman Developers | Due Dec 2028, extended 4 mo | — | — |
| Royal PlazaRoyal Realty | Due Apr 2028, extended 4 mo | — | — |
| Gayatri AnandGayatri Builders | Due Apr 2029, extended 4 mo | — | 0% |
| Heena AshishBuilt Charms Corporation | Due Apr 2029, extended 4 mo | — | 0% |
| Crown ParkGreenworld Developers | 1 yr 10 mo late | — | 8% |
| Sai ParkSai Satyam Realty LLP | Due Apr 2028, extended 4 mo | — | 43% |
| Shivneri Park Co Op Hsg Soc LtdShree Swastik Constructions | Due Mar 2027 | — | 23% |
| Proposed Residential,Commercial Bldgs on Plot bearing OLD 96 C 2-pt - Mayur MahalMayur Group (Rd) | Due Oct 2027, extended 4 mo | — | — |
Nearby: other localities in Kalyan
Most active promoters
- Mangesh Dashrath Gaikar5 projects
- Stonecrafters4 projects
- Tycoons Avanti Projects LLP4 projects
- Aarohi Development Corporation2 projects
- Dinesh Laxman Sonavane2 projects
- Gayatri Builders2 projects
- Mayur Group (Rd)2 projects
- Namdev Construction2 projects
- Shakti Realtors2 projects
- S.k. Homes Builder & Developers2 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology