Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 21% of its units are booked.

Chikanghar, Thane 421301 · by Jayawant Balaram Bhoir Patil

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales21% booked11 of 53 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 13 Jan 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700048716
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004871613 Jan 202331 Dec 202630 Apr 2027Jayawant Balaram Bhoir PatilProject page
Documents113

2 documents held by Deedo, 111 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN Cardpan self attested jaywant bhoir.pdf · uploaded 11 Sep 2022Source
  • Other – Financedev rep letter of allot.pdf · uploaded 2 Nov 2022Source

Legal

  • Legal Title reporttitle dt 04-1-23.pdf · uploaded 27 Oct 2022Source
  • Legal Title reportsearch report final.pdf · uploaded 27 Oct 2022Source
  • Declaration Form Bform B landowner.pdf · uploaded 27 Oct 2022Source
  • Declaration Form BForm B developer_compressed.pdf · uploaded 27 Oct 2022Source
Show all 113 documentsShow fewer documents

Legal

  • Other – Legalcompletion abc wing.pdf · uploaded 2 Nov 2022Source
  • Other – Legalmitali patil dev agreement_compressed (1).pdf · uploaded 2 Nov 2022Source
  • Other – Legaldev rep letter of allot.pdf · uploaded 2 Nov 2022Source
  • Other – Legalmitali shivsai dev agr.pdf · uploaded 2 Nov 2022Source
  • Other – Legalreply submitted.pdf · uploaded 13 Dec 2022Source
  • Other – Legalsociety letter1.pdf · uploaded 13 Dec 2022Source
  • Other – Legalform b original owners COMPRESS.pdf · uploaded 22 Dec 2022Source

Migrated

  • 1 PAN Cardpan self attested jaywant bhoir.pdf · uploaded 11 Sep 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 11 Sep 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers Certificate.pdf · uploaded 11 Sep 2022Source
  • 1 Disclosure of sold/ booked inventorydisclosure of inventory pdf.pdf · uploaded 11 Sep 2022Source
  • 1 CERSAI detailscersai undertaking signed pdf.pdf · uploaded 11 Sep 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORM A signed.pdf · uploaded 11 Sep 2022Source
  • 1 a Details of encumbrances concerned to Financeundertaking of no financial encumbrances.pdf · uploaded 14 Sep 2022Source
  • 1 b Details of encumbrances concerned to Legalencumbrances concerned to legal.pdf · uploaded 14 Sep 2022Source
  • 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 14 Sep 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentconstruction permission.pdf · uploaded 14 Sep 2022Source
  • 1 Proforma of Allotment letterAmmended Letter of Allotment (1).pdf · uploaded 14 Sep 2022Source
  • 1 Deviation Report with respect to Allotment letterletter to rera authorities-allottment letter.pdf · uploaded 14 Sep 2022Source
  • 2 a Details of encumbrances concerned to FinanceCERSAI_Search_Report_200247161705_For_Asset_Based_Search_15_09_2022_11_00_10_650.pdf · uploaded 15 Sep 2022Source
  • 2 CERSAI detailsCERSAI_Search_Report_200247161705_For_Asset_Based_Search_15_09_2022_11_00_10_650.pdf · uploaded 15 Sep 2022Source
  • 2 Proforma of Allotment letterallotment letter nw_compressed.pdf · uploaded 15 Sep 2022Source
  • 1 Copy of the legal title reporttitle dt 04-1-23.pdf · uploaded 27 Oct 2022Source
  • 2 Copy of the legal title reportsearch report final.pdf · uploaded 27 Oct 2022Source
  • 1 Declaration about Commencement Certificatekalyan rera form D.pdf · uploaded 27 Oct 2022Source
  • 1 Declaration in FORM Bform B landowner.pdf · uploaded 27 Oct 2022Source
  • 2 Declaration in FORM BForm B developer_compressed.pdf · uploaded 27 Oct 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentplan scanned_compresseD.pdf · uploaded 30 Oct 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)jaya patil new.pdf · uploaded 2 Nov 2022Source
  • 1 Proforma of Agreement for salesamarpan heights flat sale agreement.pdf · uploaded 2 Nov 2022Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation report flat sell comp.pdf · uploaded 2 Nov 2022Source
  • 1 Other – Legalcompletion abc wing.pdf · uploaded 2 Nov 2022Source
  • 2 Other – Legalmitali patil dev agreement_compressed (1).pdf · uploaded 2 Nov 2022Source
  • 3 Other – Legaldev rep letter of allot.pdf · uploaded 2 Nov 2022Source
  • 4 Other – Legalmitali shivsai dev agr.pdf · uploaded 2 Nov 2022Source
  • 1 Other – Financedev rep letter of allot.pdf · uploaded 2 Nov 2022Source
  • 5 Other – Legalreply submitted.pdf · uploaded 13 Dec 2022Source
  • 6 Other – Legalsociety letter1.pdf · uploaded 13 Dec 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCONSTRUCTION PERMISSION.pdf · uploaded 22 Dec 2022Source
  • 7 Other – Legalform b original owners COMPRESS.pdf · uploaded 22 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 7 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31032023.pdf · uploaded 11 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31062023.pdf · uploaded 11 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30092023.pdf · uploaded 11 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 310320230001.pdf · uploaded 11 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 300620230001.pdf · uploaded 11 Oct 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 300920230001.pdf · uploaded 11 Oct 2023Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 11 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 June 0001 compressed.pdf · uploaded 18 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 September compressed.pdf · uploaded 18 Oct 2023Source
  • 3 Disclosure of sold/ booked inventorysold mar_0001.pdf · uploaded 19 Oct 2023Source
  • 4 Disclosure of sold/ booked inventorysold june_0001.pdf · uploaded 19 Oct 2023Source
  • 5 Disclosure of sold/ booked inventorysold sep_0001.pdf · uploaded 19 Oct 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 mar_0001_compressed.pdf · uploaded 19 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5_0001.pdf · uploaded 19 Oct 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31122023.pdf · uploaded 14 Feb 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Shiv Sai_0002.pdf · uploaded 14 Feb 2024Source
  • 6 Disclosure of sold/ booked inventoryShiv Sai Construction_0001.pdf · uploaded 27 Feb 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec2023.pdf · uploaded 27 Feb 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 31-03-2024.pdf · uploaded 16 Apr 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 31-03-2024.pdf · uploaded 16 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A FY 2023-24.pdf · uploaded 25 May 2024Source
  • 7 Disclosure of sold/ booked inventorySold Unsold List March 2024.pdf · uploaded 25 May 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 31-03-2024.pdf · uploaded 25 May 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 30-06-2024.pdf · uploaded 9 Aug 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 30-06-2024.pdf · uploaded 16 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 FY 2023-24 Sign.pdf · uploaded 8 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 30-09-2024.pdf · uploaded 29 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 31-12-2024.pdf · uploaded 29 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 30-06-2024.pdf · uploaded 29 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 30-09-2024.pdf · uploaded 15 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 31-12-2024.pdf · uploaded 15 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final 30062024_compressed.pdf · uploaded 7 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHIV SAI DEC 2024_0001_compressed.pdf · uploaded 7 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3 Jaywant Bhoir Pail 300924_0001_compressed.pdf · uploaded 7 Mar 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHIV SAI DEC 2024_0001_compressed.pdf · uploaded 7 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Shiv Sai 30-06-24.pdf · uploaded 7 Mar 2025Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Shiv Sai 30-09-24.pdf · uploaded 7 Mar 2025Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Shiv Sai 31-12-24.pdf · uploaded 7 Mar 2025Source
  • Withdrawal Update Form 1Form-1 30-06-2025.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 2Form-2 30-06-2025.pdf · uploaded 17 Sep 2025Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 17 Sep 2025Source
  • Form 2A (FY 2024-2025)Form-2A FY 2024-25.pdf · uploaded 20 Sep 2025Source
  • Form 5 (FY 2024-2025)Form-5 FY 2024-25.pdf · uploaded 20 Sep 2025Source
  • Withdrawal Update Form 1form-1 30-09-2025.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1form-1 30-09-2025.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2Form 2 Q2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2Form 2 Q2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Final Q2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1form-1 31-12-2025.pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 2Form-2 31-12-2025.pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 3Form-3 31-12-2025.pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 1Form 1 31-03-2026 Shiv Sai Construction.pdf · uploaded 22 May 2026Source
  • Withdrawal Update Form 2Form 2 31-03-2026 Shiv Sai Construction.pdf · uploaded 22 May 2026Source
  • Withdrawal Update Form 3Final Form 3 31-03-2026 Shiv Sai Construction.pdf · uploaded 22 May 2026Source

Technical

  • Documentlayout.pdf · uploaded 14 Sep 2022Source
  • Documentconstruction permission.pdf · uploaded 14 Sep 2022Source
  • Documentplan scanned_compresseD.pdf · uploaded 30 Oct 2022Source

Technical (Architect)

  • DocumentForm-1 30-09-2024.pdf · uploaded 29 Jan 2025Source
  • DocumentForm-1 31-12-2024.pdf · uploaded 29 Jan 2025Source
  • DocumentForm 1 31-03-2026 Shiv Sai Construction.pdf · uploaded 22 May 2026Source

Technical (Engineer)

  • DocumentForm-2 30-09-2024.pdf · uploaded 15 Feb 2025Source
  • DocumentForm-2 31-12-2024.pdf · uploaded 15 Feb 2025Source
  • DocumentForm 2 31-03-2026 Shiv Sai Construction.pdf · uploaded 22 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 19

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Alloted to Landowner, AllotedtoLandowner53 units in all
Address
19, ChikangharPIN 421301
Village
Chikanghar, Kalyan taluka
Land area for this project
995 sq m (10,707 sq ft)
Permissible built-up area
7,637 sq m (82,206 sq ft)
Sanctioned built-up area
3,820 sq m (41,116 sq ft)
Designated bank account
89
Developed in phases
No

Survey, CTS, gat or plot numbers

19

Land as published on MahaRERA's project page

19

Boundaries

North
Survey no 19 HM2
South
chikanghar
East
Survey no 19 4
West
Survey no 16

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking53 units

11 of 53 units booked (21%), as the promoter reported to MahaRERA

1BHK · 10 units2BHK · 24 unitsAlloted to Landowner · 18 unitsAllotedtoLandowner · 1 unit
TypeCarpet areaUnitsBooked
1BHK33.65 sq m · 362 sq ft10
1BHK35.93 sq m · 387 sq ft92
2BHK53.39 sq m · 575 sq ft248
Alloted to Landowner33.65 sq m · 362 sq ft100
Alloted to Landowner53.39 sq m · 575 sq ft80
AllotedtoLandowner53.69 sq m · 578 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSatish Kanade—
Chartered accountantAnkit Paras Jain—
Chartered accountantG V Pabhu Company—
EngineerAniket Bhoir—
EngineerArun khasnis—
OtherAniket Jaywant Bhoir—
OtherSarvesh Shivnarayan Shukla—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology