Ready-to-move projects in Maharashtra
15,256 projects in 34 districts with a completion or occupancy certificate on MahaRERA still declare 6,61,149 unsold flats, as declared to MahaRERA.
Most unsold flats first
Unsold: flats declared to MahaRERA minus those declared booked, on the project's latest MahaRERA disclosure; a developer may not have updated it. Page 3 of 306.
| Project | Locality | Unsold flats | Delivery |
|---|---|---|---|
| Tharwani SolitaireAnil Hardasmal Tharwani | Mharal Kh. (N.V)Thane | 420 of 640 | Completed, extended 1 yr 6 mo |
| The LegendShree Sankalp Associates | Hinjavadi (Ct)Pune | 420 of 491 | Completed |
| Krystal OneRama Spaces | ChikhaliPune | 419 of 710 | Completed, extended 4 mo |
| BlossomNg Rathi Associates | WagholiPune | 408 of 573 | Completed |
| Ekta ParksvilleEkta Parksville Homes Pvt. Ltd. | VirarPalghar | 408 of 2,363 | Completed, extended 4 mo |
| Tharwani ArianaAnil Hardasmal Tharwani | Ambarnath(M Cl)Thane | 408 of 664 | Completed |
| PMAY Scheme Survey No 57 Hissa No 5part Plot No 1b Old Plot No 1 Kharadi Tal Haveli Dist PunePMAY Cell, Pune Municipal Corporation | KharadiPune | 405 of 405 | Completed |
| Plot No 01 Sector 11 DronagiriCity And Industrial Developement Corporation Of Maharashtra Ltd | NavgharRaigarh | 398 of 984 | Completed, extended 1 yr 6 mo |
| Mirai Phase-IAurigaa Realtors | PunawalePune | 392 of 589 | Completed |
| Constn of 219 Ts and 172 MIG Ts on CTS No 128 A 12 Pt at Mahaveer nagar Kandivali W MumbaiMaharashtra Housing And Area Development Authority | BorivaliMumbai Suburban | 391 of 391 | Completed, extended 2 yrs |
| Marina Enclave Wings Q and R with Kindergarten Phase - IVGurukrupa Developers D N Nagr Project | BorivaliMumbai Suburban | 390 of 390 | Completed |
| PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to TPalava Dwellers Private Limited | KhoniThane | 390 of 2,430 | Completed |
| Panama ParkThe Kallyaanee Fortune Properties | LohgaonPune | 388 of 388 | Completed |
| Pratik GreensShirvawala Estate Developers LLP | NeljeThane | 386 of 441 | Completed, extended 4 mo |
| Lodha Pune NIBM ProjectLodha Developers Limited | MohammadwadiPune | 382 of 1,135 | Completed, extended 4 mo |
| PMAY Scheme Survey No 57 Hissa No 5 Part Plot No 1a Old Plot No 1 KharadiPMAY Cell, Pune Municipal Corporation | KharadiPune | 382 of 382 | Completed |
| Euro VilleVastu Rachana JV | KharadeThane | 381 of 396 | Completed |
| Osians GardenOsian Dwellings Private Limited | Bhiwandi (M Corp.)Thane | 379 of 495 | Completed |
| Pradhan Mantri Awas Yojana- BorahdewadiPimpri Chinchwad Municipal Corporation | BorhadewadiPune | 378 of 1,299 | Completed |
| Rohan AnandRohan Builders & Developers Private Limited | SomatanePune | 377 of 609 | Completed |
| Tulsi AadvikRaj Group | Badlapur (M Cl)Thane | 377 of 377 | Completed |
| Upper Thane WoodlandsLodha Developers Limited | AnjurThane | 374 of 551 | Completed |
| AnantsrishtiLandscape Reality | JambhulPune | 367 of 723 | Completed |
| Plot No 68 Sector 12 DronagiriCity And Industrial Developement Corporation Of Maharashtra Ltd | PhundeRaigarh | 367 of 720 | Completed, extended 1 yr 6 mo |
| Tharwani Ariana Phase IVAnil Hardasmal Tharwani | ChikhloliThane | 366 of 426 | Completed |
| VNSVL Shubh NirvanaViman Nagar Shubh Ventures LLP | LohgaonPune | 366 of 462 | Completed |
| AriseVinod Premchand Chandwani | PunawalePune | 364 of 410 | Completed |
| Apna GharSeven Eleven Construction Private Limited | GhodbunderThane | 364 of 2,155 | Completed |
| Kashish ParkKashish Park Realtors | Thane (M Corp.)Thane | 356 of 441 | Completed, extended 4 mo |
| Piramal AranyaGlider Buildcon Realtors Private Limited | Mumbai City | 354 of 1,046 | Completed, extended 4 mo |
| The ExchangeViraj Estates Pvt. Ltd. & Others | DeolaligaonNashik | 353 of 514 | Completed |
| Joyville Hadapsar AnnexeJoyville Shapoorji Housing Private Limited | ShewalewadiPune | 352 of 2,010 | Completed, extended 4 mo |
| MicasaaGagan Global Developers | WagholiPune | 352 of 423 | Completed, extended 4 mo |
| Vasudev Sky HighShree Prathamesh Developer | Thane | 351 of 485 | Completed |
| Pranjee Garden City Phase -IIPranjee Properties Pvt. Ltd | KatrapThane | 346 of 456 | Completed, extended 1 yr |
| Life Republic Sector R10 10th Avenue UniverseKolte-Patil Planet Real Estate Private Limited | JambePune | 344 of 774 | Completed |
| The AddressSOL Developers | MoshiPune | 344 of 489 | Completed, extended 4 mo |
| Business SquareVastukrupa Construction (India) Pvt Ltd | Nashik | 343 of 535 | Completed |
| Iris Mira Road EJeetendra Alias Ravi Amarnath Kapoor | Mirabhayandar (M Corp.)Thane | 341 of 341 | Completed |
| Park InfiniaKumar Properties and Real Estate Pvt. Ltd. | FursungiPune | 341 of 446 | Completed |
| PMAY Scheme S No 106a 16a P Plus17 A P Plus17b P Plus18a P Plus18 B P Hadapsar Tal Haveli Dist PunePMAY Cell, Pune Municipal Corporation | HadapsarPune | 340 of 340 | Completed |
| Universal CubicalPagarani Universal Infrastructure Pvt. Ltd. | AndheriMumbai Suburban | 334 of 604 | Completed, extended 1 yr |
| Chembur Heights IIKukreja Construction Co | KurlaMumbai Suburban | 332 of 342 | Completed, extended 2 yrs 6 mo |
| Plot 1 Sector 10 GHANSOLICIDCO of Maharashtra Ltd. | GhansoliThane | 330 of 330 | Completed, extended 1 yr 3 mo |
| Plot No 63 Sector 12 DronagiriCity And Industrial Developement Corporation Of Maharashtra Ltd | NavgharRaigarh | 329 of 750 | Completed, extended 1 yr 6 mo |
| Vinay Unique GardensVinayunique Developers | DongrePalghar | 329 of 754 | Completed |
| Construction of 328 EWS t/s S.No. 392 pt village bolinj Tal - Vasai Dist - Palghar - PMAYArun Shankarrao Borgave | AndheriMumbai Suburban | 328 of 328 | Completed |
| Golden Vann - Phase 4A Plus Developers | ArdheRaigarh | 326 of 326 | Completed |
| PMAY Scheme At SurveyPMAY Cell, Pune Municipal Corporation | HadapsarPune | 324 of 324 | Completed |
| Tulsi AanandRaj Group | Badlapur (M Cl)Thane | 320 of 320 | Completed |
Ready-to-move projects by district
Pune · 4,088Thane · 2,041Raigarh · 1,960Mumbai Suburban · 1,827Nashik · 1,514Palghar · 768Nagpur · 384Ratnagiri · 362Sangli · 345Kolhapur · 331Mumbai City · 322Aurangabad · 302Satara · 295Ahmednagar · 189Sindhudurg · 171Solapur · 142Latur · 42Chandrapur · 34Amravati · 29Nanded · 17Jalna · 15Beed · 14Osmanabad · 14Wardha · 12Yavatmal · 8Bhandara · 7Parbhani · 6Washim · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsListed when MahaRERA shows completion (its status, or a completion or occupancy certificate in its documents) and the declared inventory still has unbooked flats. Bookings are as declared to MahaRERA.Report a problemMethodology