VNSVL Shubh Nirvana
Completion due Oct 2027Lohgaon, Pune 411047 |Promoter: Viman Nagar Shubh Ventures LLP
Project summary
As registered with MahaRERA
- RERA registrations
- 4
- Phases
- 4
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2025
P52100031263The latest completion date on record passed 10 months ago.
- Registered
- 15 Oct 2021
- Promised
- 31 Dec 2025
Completion promised for 30 Jun 2026
P52100050937The latest completion date on record passed 4 months ago.
- Registered
- 15 May 2023
- Promised
- 30 Jun 2026
Completion promised for 31 Dec 2026
P52100055241- Registered
- 14 Mar 2024
- Promised
- 31 Dec 2026
Completion promised for 30 Oct 2027
P52100055359- Registered
- 22 Mar 2024
- Promised
- 30 Oct 2027
4 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031263 | 15 Oct 2021 | 31 Dec 2025 | — | Viman Nagar Shubh Ventures LLP | Project page |
| P52100050937 | 15 May 2023 | 30 Jun 2026 | — | Viman Nagar Shubh Ventures LLP | Project page |
| P52100055241 | 14 Mar 2024 | 31 Dec 2026 | — | Viman Nagar Shubh Ventures LLP | Project page |
| P52100055359 | 22 Mar 2024 | 30 Oct 2027 | — | Viman Nagar Shubh Ventures LLP | Project page |
Documents
5 documents held by Deedo
Registration certificate (5)
- Registration certificateP52100050937 · 15 May 2023ViewSource
- Registration certificateP52100031263 · 17 Jan 2024ViewSource
- Registration certificateP52100055241 · 14 Mar 2024ViewSource
- Registration certificateP52100055359 · 21 Aug 2026ViewSource
- Registration certificateP52100055359 · 8 Oct 2026ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Lohgaon
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.