Skip to content
Deedo home
Menu

Krystal One

Completion due Dec 2027

Chikhali, Pune 412114 |Promoter: Rama Spaces

1 Sep 2021Registered with MahaRERAFirst of 4 registrations
31 Dec 2027Promised completionLatest across registrations
30 Oct 2025Revised completion1 of 4 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
4
Phases
4

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.68420, 73.83459
Krystal One is at latitude 18.68420, longitude 73.83459.

Also registered as

Krystal One Phase IKrystal One Phase IIKrystal One Phase IIIKrystal One Phase IV
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P52100030567

The latest completion date on record passed 1 year ago.

Registered
1 Sep 2021
Promised
31 Oct 2024
Revised
30 Oct 2025

Completion promised for 31 Aug 2026

P52100047325

The latest completion date on record passed 2 months ago.

Registered
19 Oct 2022
Promised
31 Aug 2026

Completion promised for 31 Dec 2026

P52100049781
Registered
24 Feb 2023
Promised
31 Dec 2026

Completion promised for 31 Dec 2027

P52100055473
Registered
2 Apr 2024
Promised
31 Dec 2027

4 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000305671 Sep 202131 Oct 202430 Oct 2025Rama SpacesProject page
P5210004732519 Oct 202231 Aug 2026—Rama SpacesProject page
P5210004978124 Feb 202331 Dec 2026—Rama SpacesProject page
P521000554732 Apr 202431 Dec 2027—Rama SpacesProject page

Documents

6 documents held by Deedo

Registration certificates

  • Registration certificateP52100030567 · 1 Sep 2021ViewSource
  • Registration certificateP52100055473 · 19 Dec 2024ViewSource
  • Registration certificateP52100047325 · 18 Aug 2026ViewSource
  • Registration certificateP52100049781 · 23 Sep 2026ViewSource

Extension certificates

  • Extension certificateP52100030567 · 25 Oct 2024ViewSource
  • Extension certificateP52100049781 · 20 Aug 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Chikhali

Survey, CTS, gat or plot numbers

9797 (P)Gat No 96Gat No. 96 (P)Gat No.97 (P)

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology