Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Chikhali · Pune
Registration
RERA numbers
PromoterRama Spaces
Status on MahaRERACertificate Signed
Registered on1 Sep 2021
Delivery
Promised completion31 Dec 2027
Revised completion30 Apr 2028
Delay vs RERA date+3 monthsrevised completion date
Extension certificates2
Size
Project land area—
Buildings on record6
Units710
Units booked29141% of units
Regulatory
MahaRERA cases0
Documents on file6
Last checked on MahaRERA15 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology