Rama Spaces
Deedo IDDD-8RQGOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Paradise OneP52100018033 | Chikhali | Certificate Signed | 30 Sep 2021 | 30 Mar 2023 | +18 mo |
| Krystal OneP52100030567 | Chikhali | Certificate Signed | 31 Oct 2024 | 30 Oct 2025 | +12 mo |
| Krystal OneP52100047325 | Chikhali | Certificate Signed | 31 Aug 2026 | 31 Aug 2026 | +3 mo* |
| Krystal OneP52100049781 | Chikhali | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Krystal OneP52100055473 | Chikhali | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Rama Spaces, in questions
Does Rama Spaces finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rama Spaces registered with MahaRERA?
2 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.
Does Rama Spaces have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.