Park Infinia
Completion date passedFursungi, Pune 412308 |Promoter: Kumar Properties and Real Estate Pvt. Ltd.
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 May 2019
P52100000084The latest completion date on record passed 7 years and 5 months ago.
- Registered
- 28 Jun 2017
- Promised
- 31 May 2019
Completion promised for 21 Aug 2022
P52100014939The latest completion date on record passed 4 years and 2 months ago.
- Registered
- 15 Jan 2018
- Promised
- 21 Aug 2022
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100000084 | 28 Jun 2017 | 31 May 2019 | — | Kumar Properties and Real Estate Pvt. Ltd. | Project page |
| P52100014939 | 15 Jan 2018 | 21 Aug 2022 | — | Kumar Properties and Real Estate Pvt. Ltd. | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.