RERA projects in Ardhe

3 projects under 3 MahaRERA registrations, registered 2017–2019. 33% have a completion date extended beyond the one promised.

3RERA projects
3Registrations
0Completion still due3 past their completion date
11 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20192

Projects in Ardhe

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shrusti VanA Plus DevelopersP5200002132521 Jun 201930 Mar 2025—Promised date passed0
Golden VanA Plus DevelopersP520000207548 May 201930 Mar 202528 Feb 2026Extended 11 mo0
Golden Vann - Phase 4A Plus DevelopersP520000032055 Aug 201724 Sep 2022—Promised date passed0

Other localities in Karjat

Most active promoters

By projects registered here, as named on MahaRERA.

  1. A Plus Developers3 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology