Ghodbunder, Thane
Deedo IDDL-THN-GHODBUNDER7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects13
Registrations15some projects hold several
Completion still due114 past their date
Median extension4 months47% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
15 MahaRERA registrations in Ghodbunder
4 not yet due7 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Ghodbunder
13 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Casa Supremo RetailLodha Developers Limited | Due Mar 2027 | — | — |
| OctaveRajdeep Realtors And Developers Pvt Ltd, Ravi Developments | Due Dec 2031 | — | — |
| Shree Nidhi HeavenShree Nidhi Heaven | Due Aug 2031 | — | — |
| RD RoyaltonRavi Developments | Due Dec 2028 | — | — |
| Codename EndgameJP Infra Realty Private Limited | Due Apr 2035, extended 4 mo | — | — |
Nearby: other villages in Thane
Thane (M Corp.) · 896 projectsNavi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsBhayandar · 118 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 61 projectsNerul · 58 projectsGhansoli · 56 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projects
Most active promoters
- Reyanshp Realty LLP2 projects
- Godrej Greenview Housing Private Limited1 project
- Jp Infra Realty Private Limited1 project
- Lodha Developers Limited1 project
- North South Estate Builders1 project
- Rajdeep Realtors And Developers Pvt Ltd, Ravi Developments1 project
- Ravi Developments1 project
- Seven Eleven Construction Private Limited1 project
- Shree Nidhi Heaven1 project
- Shree Ramdev Ritu Developers1 project
Ghodbunder, in questions
How many projects in Ghodbunder run late?
7 in 10 MahaRERA registrations (11 of 15): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ghodbunder by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology