New projects in Pune
1,076 projects in Pune were registered with MahaRERA in the last 12 months, newest first, each with its RERA number and promised completion date.
Newest registration first
Registered: the date of the project's MahaRERA registration certificate. Promised: the completion date the developer gave MahaRERA. Page 11 of 22.
| Project | Locality | Registered | Promised | Delivery |
|---|---|---|---|---|
| IconEvita Krisala Township LLP | Darumbare | Jun 2026 | May 2031 | Due Sep 2031, extended 4 mo |
| ManodeepGokhale Constructions | Kothrud-Ext | Jun 2026 | May 2029 | Due Sep 2029, extended 4 mo |
| SubhadrarjunEcorb Realty | Dhankawadi | Jun 2026 | Apr 2029 | Due Aug 2029, extended 4 mo |
| The Vantage EKuber Properties | Wakad | Jun 2026 | Mar 2031 | Due Jul 2031, extended 4 mo |
| Vansh VastuRajvansh Infra | Kiwale | Jun 2026 | May 2027 | Due Sep 2027, extended 4 mo |
| Mantra Mistara Phase IA Plus Design House LLP | Sus | Jun 2026 | Dec 2030 | Due Apr 2031, extended 4 mo |
| Advait AvenueShree Nand Group | Balewadi | Jun 2026 | Dec 2026 | Due Apr 2027, extended 4 mo |
| ChaitanyaramChaitanyaram Sahakari Gruhrachana Sanstha Maryadit | Karve Nagar | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| Park Imperial Tower AIqoniq shelters llp | Hadapsar | Jun 2026 | Dec 2034 | Due Apr 2035, extended 4 mo |
| Real EnclaveRealspace Construction | Bibwewadi-Munjeri | Jun 2026 | Dec 2029 | Due Apr 2030, extended 4 mo |
| Silverise Radiant TowerSilverise Radiant Tower LLP | Dudulgaon | Jun 2026 | Sep 2030 | Due Sep 2030 |
| Shreeyog Co-operative Housing SocietyTrinity Spaces | Pashan | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| Trimurti Saroj HeightsNageshwar Properties | Dehu | Jun 2026 | Mar 2029 | Due Jul 2029, extended 4 mo |
| Chordiya SamruddhiA.n.k. Buildcon | Kondhwa Budruk | Jun 2026 | Mar 2029 | Due Jul 2029, extended 4 mo |
| EkaantaPrasun Associates | Lohgaon | Jun 2026 | Mar 2029 | Due Jul 2029, extended 4 mo |
| K K MaplesShah And Associates | Chovisawadi | Jun 2026 | May 2031 | Due Sep 2031, extended 4 mo |
| Lotus SevaLotus Landmarks | Kothrud | Jun 2026 | Mar 2029 | Due Jul 2029, extended 4 mo |
| Nutan Shaiva Bramhan Sanstha Gurav BhavanSapkal Construction | Narayan Peth | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| One Place-Bund Garden RoadTopspace Landmarks LLP | Ghorpadi | Jun 2026 | Dec 2032 | Due Apr 2033, extended 4 mo |
| Samarth Paradise Phase 5Vaibhav Hanumant Kawade | Jalochi | Jun 2026 | Dec 2029 | Due Apr 2030, extended 4 mo |
| V-Uptown, A-wingTatvam Constructions Private Limited | Kiwale | Jun 2026 | Dec 2030 | Due Apr 2031, extended 4 mo |
| Vyana Phase-I-T5, T6, T7 at The ReserveKolte-Patil Developers Limited | Vadgaon-Khurd | Jun 2026 | Dec 2031 | Due Apr 2032, extended 4 mo |
| Deshpande Somani SquareSomani Landmarks LLP | Baramati (M Cl) | Jun 2026 | Dec 2030 | Due Apr 2031, extended 4 mo |
| Dream VelmoreVertex Developers | Balewadi | Jun 2026 | Dec 2032 | Due Apr 2033, extended 4 mo |
| Neel-PrakashVakratunda Realtors | Talegaon Dabhade (R) | Jun 2026 | Dec 2029 | Due Apr 2030, extended 4 mo |
| Shankeshwar Kingsland Phase 1Shankeshwar Homes Pvt Ltd | Hinjavadi (Ct) | Jun 2026 | Dec 2032 | Due Apr 2033, extended 4 mo |
| Siddhivinayak VishwaSai Ganesh Ventures | Wagholi | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| The HamptonnsBhansali Luxury Homes LLP | Balewadi | Jun 2026 | Dec 2030 | Due Apr 2031, extended 4 mo |
| Gandharv GokulamGandharv Corp | Hadapsar | Jun 2026 | Dec 2029 | Due Apr 2030, extended 4 mo |
| Aakar Heights B WingRiya Rahul Katkamwar | Bavadhan Bk | Jun 2026 | Dec 2027 | Due Apr 2028, extended 4 mo |
| Magnar OneRyse Landmarks LLP | Ghorpadi | Jun 2026 | Dec 2030 | Due Apr 2031, extended 4 mo |
| Nakshatra NandanvanSkyworks Developers | Narhe | Jun 2026 | Dec 2032 | Due Apr 2033, extended 4 mo |
| New Prasanna Park Co-op Housing Society Ltd.Rahul Lifespaces LLP | Gultekadi | Jun 2026 | Jun 2031 | Due Oct 2031, extended 4 mo |
| Taksh Villas Ph IITaksh Properties | Uruli Devachi | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| 9 DhanlaxmiAjit Construction & Builders LLP | Erandwana North | Jun 2026 | Feb 2028 | Due Jun 2028, extended 4 mo |
| Darade Chavan ComplexDarade Chavan Associates | Jalochi | Jun 2026 | Dec 2029 | Due Apr 2030, extended 4 mo |
| Jalvan Homes Phase - IMompaasons LLP | Marunji | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| Madhuban Phase IING Rathi Estate | Pirangut | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| OrianaFortune Realtors | Dudulgaon | Jun 2026 | Dec 2028 | Due Apr 2029, extended 4 mo |
| Pristine AmorePristine Landmark Spaces LLP | Vadgaon Sheri | Jun 2026 | Apr 2032 | Due Apr 2032 |
| Swanand ResidencyShreekrupa Associates | Dhankawadi | Jun 2026 | Dec 2029 | Due Apr 2030, extended 4 mo |
| VrundavanTrinity Developers | Ambegaon Bk | Jun 2026 | Aug 2029 | Due Dec 2029, extended 4 mo |
| Babar Classic VistaClassic Properties | Kondhwa Khurd | Jun 2026 | Mar 2031 | Due Jul 2031, extended 4 mo |
| Mangalmurti ParadiseMangalmurti And Rushabh Developers | Talegaon Dabhade (M Cl) | Jun 2026 | Sep 2028 | Due Jan 2029, extended 4 mo |
| Muktangan KimayaMuktangan Kimaya Realities LLP | Pimpale Saudagar | Jun 2026 | Mar 2030 | Due Jul 2030, extended 4 mo |
| Phule Mansion Co-Operative Housing Society LimitedShreesha Landmark LLP | Parvati | Jun 2026 | Dec 2030 | Due Apr 2031, extended 4 mo |
| Ganga GenesiaVardaan Lifestyle Limited | Mohammadwadi | Jun 2026 | Mar 2030 | Due Jul 2030, extended 4 mo |
| Om Building Chs LtdDhanlaxmi Associates | Erandwane South | Jun 2026 | Mar 2029 | Due Jul 2029, extended 4 mo |
| Shankeshwar TatvaMunisuvrat Properties | Moshi | Jun 2026 | Mar 2029 | Due Jul 2029, extended 4 mo |
| Ajmera UptownAjmera Bora Associates | Kalas | Jun 2026 | Jan 2031 | Due May 2031, extended 4 mo |
New projects by district
All MaharashtraPune · 1,076Mumbai Suburban · 645Thane · 633Raigarh · 392Nagpur · 254Palghar · 234Nashik · 226Mumbai City · 102Satara · 80Kolhapur · 68Aurangabad · 66Ratnagiri · 53Ahmednagar · 29Sangli · 29Sindhudurg · 29Amravati · 24Solapur · 21Latur · 12Akola · 10Chandrapur · 7Nanded · 7Yavatmal · 5
SourcesMahaRERA registrations, extension certificates, project pages and document listsListed when the project's MahaRERA registration is at most 12 months old. A new registration can be a new phase or tower of an older project.Report a problemMethodology