66 projects in Aurangabad were registered with MahaRERA in the last 12 months, newest first, each with its RERA number and promised completion date.

Newest registration first

Registered: the date of the project's MahaRERA registration certificate. Promised: the completion date the developer gave MahaRERA. Page 1 of 2.

ProjectLocalityRegisteredPromisedDelivery
Casagrand 28Sai Narayani BuildersItkhedaNov 2026Dec 2030Due Dec 2030
The 14 OaksVaradlaxmi DevelopersAurangabad (M Corp.)Nov 2026Dec 2030Due Dec 2030
Yashraj VrundavanYashraj DevelopersAurangabad (M Corp.)Nov 2026Mar 2031Due Mar 2031
Paritosh ComplexVedantbuilds Infradevelopers LLPAurangabad (M Corp.)Oct 2026Dec 2028Due Dec 2028
Royal Enclave Building 2Padmanabh Builders & Developers LLPAurangabad (M Corp.)Oct 2026Jun 2029Due Jun 2029
Shri Balaji EmpireShri Balaji InfraDevlaiOct 2026Feb 2028Due Feb 2028
Madhura MajestyMadhura Lifespaces LLPHarsoolOct 2026Dec 2033Due Dec 2033
Swapna srushti 2Nisha Amrut Sai BuildersNanakwadiOct 2026Mar 2030Due Mar 2030
Ganesha HeightsNamo RealtyAurangabad (M Corp.)Oct 2026Mar 2031Due Mar 2031
Ideas-2Ideas InfraItkhedaOct 2026Oct 2029Due Oct 2029
Shri Samarth ViharShri Samarth DevelopersNakshatrawadiOct 2026Mar 2031Due Mar 2031
Nabhraj Trilok Heights MHADANabhraj Builders And Developers Pvt LtdShahanur WadiOct 2026Dec 2030Due Dec 2030
Prassana High Class City Phase - IShri Krishna Nagar Sahakari Grah Nirman Sanstha MaryaditGandheliSep 2026Mar 2031Due Mar 2031
Urban NestMalkhare Builders And Developers Pvt LtdItkhedaSep 2026Dec 2032Due Dec 2032
VasundharaDizzi Land Farms Private LimitedItkhedaSep 2026Dec 2032Due Dec 2032
Arch Yz AtlantisJaz InfraOthersSep 2026Dec 2032Due Dec 2032
Ananda NilayamShreeja Builders And DevelopersChikalthanaSep 2026Dec 2032Due Dec 2032
Kasliwal AmaraSupushp EnterprisesAurangabad (M Corp.)Sep 2026Mar 2032Due Mar 2032
Mangala HomesNahata And Nirmal Ventures LLPTisgaonSep 2026Dec 2027Due Dec 2027
Kasliwal NiwaraKasliwal NiwaraChikalthanaAug 2026Dec 2032Due Dec 2032
Nabhraj SymphonyNabhraj Builders And Developers Pvt LtdItkhedaAug 2026Dec 2032Due Dec 2032
Sainath TowerSainath DevelopersAurangabad (M Corp.)Aug 2026Dec 2028Due Dec 2028
Fortune HomesArvind Raychand MuthaShahanur WadiJul 2026Sep 2030Due Jan 2031, extended 4 mo
Gangotri ResidencyShree Ganesha DevelopersPokhariJul 2026Dec 2030Due Apr 2031, extended 4 mo
Swapnil ApartmentSumeru RealitiesAurangabad (M Corp.)Jul 2026Mar 2028Due Jul 2028, extended 4 mo
Onkar Aakar Valley Phase 2Aakar ConstructionAurangabad (M Corp.)Jul 2026Dec 2032Due Apr 2033, extended 4 mo
Indrayani NandanwanIndrayani Builder and DevelopersHarsoolJul 2026Mar 2031Due Jul 2031, extended 4 mo
Shlok Tirupati Park Phase 1Shlok RealitiesSatara (Ct)Jul 2026Dec 2029Due Apr 2030, extended 4 mo
Venkatesh HaripriyaBhagyoday BuildersNakshatrawadiJul 2026Apr 2027Due Aug 2027, extended 4 mo
Waluj Trade TowerGovind EnterprisesRanjangaon (S) (Ct)Jul 2026Dec 2030Due Apr 2031, extended 4 mo
Oberoi Manali ComfortManali VenturesTisgaonJul 2026Oct 2029Due Feb 2030, extended 4 mo
Madhura Angan Phase 2Madhura Ventures LLPPisadeviJul 2026Dec 2032Due Apr 2033, extended 4 mo
Morya Residency 2Morya BuildersAshrafpurJul 2026Mar 2028Due Jul 2028, extended 4 mo
Aarav EnclaveRajendra Laxminarayan JaiswalGolwadiJun 2026Mar 2028Due Jul 2028, extended 4 mo
MORYA PARK Ph-IIIMh Builders And DevelopersKannadJun 2026Dec 2031Due Apr 2032, extended 4 mo
Sawangi City Phase-2Aryaman InfraSawangiJun 2026Mar 2031Due Jul 2031, extended 4 mo
Sai NakshatraEverest Bajaj CombinesAurangabad (M Corp.)Jun 2026Dec 2030Due Apr 2031, extended 4 mo
Leela-3Leela RealityAurangabad (M Corp.)Jun 2026Apr 2029Due Aug 2029, extended 4 mo
Prisha Square Phase-IINandkishor Bhimrao ChavanFattepurJun 2026Dec 2030Due Apr 2031, extended 4 mo
Tirupati HillsSSBD Builders and Developers LLPTisgaonJun 2026Jun 2028Due Oct 2028, extended 4 mo
Om Sai ResidencyDattatray Gangadhar RautBidkinMay 2026Dec 2030Due Apr 2031, extended 4 mo
Ssbd TowerSSBD Builders and Developers LLPGolwadiMay 2026Dec 2027Due Apr 2028, extended 4 mo
Shanta Apartment Swanand RealtiesSwanand RealtiesAurangabad (M Corp.)May 2026Nov 2028Due Mar 2029, extended 4 mo
T ThreeTayal Business Park LLPAurangabad (M Corp.)May 2026Dec 2029Due Apr 2030, extended 4 mo
Bhumija TejasBhumija Infra & DevelopersUsmanpuraApr 2026Dec 2029Due Apr 2030, extended 4 mo
Omkar ResidencyOmkar DevelopersItkhedaApr 2026Nov 2029Due Mar 2030, extended 4 mo
Radha Nagari BVision InfraKanchanwadiApr 2026Jan 2031Due May 2031, extended 4 mo
Palm Leaves Phase 2Shakti Lifespaces Pvt LtdShahanur WadiApr 2026Jun 2027Due Oct 2027, extended 4 mo
Khinvasara August HighStreet MarketChampalal Kanhaiyalal KhinvasaraGarkhedaApr 2026Dec 2031Due Apr 2032, extended 4 mo
Shubhlabh HeritageBhaishree Realtors LLPChikalthanaApr 2026Jan 2030Due May 2030, extended 4 mo

New projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsListed when the project's MahaRERA registration is at most 12 months old. A new registration can be a new phase or tower of an older project.Report a problemMethodology