ProjectLocalityRegisteredPromisedDelivery
Madhaswad Realty Phase-1Madhaswad Realty LLPNandedOct 2026Dec 2033Due Dec 2033
Padmavati Empire B1Padmavati DevelopersWadi Bk.Jul 2026Apr 2029Due Aug 2029, extended 4 mo
Lotus HeightsM. M. DevelopersKouthaMay 2026Mar 2029Due Jul 2029, extended 4 mo
Jinen SquareJinen InfraNandedApr 2026Dec 2030Due Apr 2031, extended 4 mo
Kuber ResidencyNeev EnterprisesVasarniApr 2026Mar 2030Due Jul 2030, extended 4 mo
Shri Swami Samarth Heights-KauthaShri Swami Samarth EstatesKouthaMar 2026Mar 2028Due Jul 2028, extended 4 mo
Visawa ResidencySbg GroupWajirabadDec 2025Jun 2028Due Oct 2028, extended 4 mo

New projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsListed when the project's MahaRERA registration is at most 12 months old. A new registration can be a new phase or tower of an older project.Report a problemMethodology