Delayed projects in Pune
2,215 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 42 of 45.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Godavari Apartment CondominiumRevive Homes LLP | Pune (M Corp.) | May 2026 | Sep 2026 | 6 mo late |
| Harshad ApartmentArchway Properties | Parvati | May 2026 | Sep 2026 | 6 mo late |
| Mahadeo DreamsShree Ganesh Associates | Bhosari | May 2026 | May 2026 | 6 mo late |
| Sadanand CondominiumRajendra Balkrushna Chaphalkar | Erandwana | May 2026 | Sep 2026 | 6 mo late |
| Vaishnavi City Phase 2 Sector 2Vaishnavi Mahila Unnati Sanstha | Uruli Devachi | May 2026 | Sep 2026 | 6 mo late |
| WESTWINDS Wing AShreeram Sankalp Associates | Warje | May 2026 | May 2026 | 6 mo late |
| Hari Vitthal ApartmentsNiwas Enterprises | Pune (M Corp.) | Jun 2026 | Oct 2026 | 5 mo late |
| Abhishek Co Operative Housing Society LimitedFortune Developers | Shivajinagar Bhamburda | Jun 2026 | Jun 2026 | 5 mo late |
| LaxmiviharLaxmi Gulab Murgunde | Pune (M Corp.) | Jun 2026 | Jun 2026 | 5 mo late |
| Navkar SuchitFour Pillars | Pimpri Chinchawad (M Corp.) | Jun 2026 | Jun 2026 | 5 mo late |
| Splendour County WagholiPs Developers | Wagholi | Jun 2026 | Jun 2026 | 5 mo late |
| Prisma Homesprisma realty pvt ltd | Chikhali | Jun 2026 | Oct 2026 | 5 mo late |
| Prime AvenuePrasad Developers | Dehu | Jun 2026 | Oct 2026 | 5 mo late |
| Ram Kanta ApartmentsPhadtare Buildcon | Bhosari | Jun 2026 | Oct 2026 | 5 mo late |
| Sara SwapnodayJagrutsara Structures LLP | Kharabwadi (Ct) | Jun 2026 | Jun 2026 | 5 mo late |
| Vtp AltairIntegrated Business Ecosystem Private Limited | Wagholi | Jun 2026 | Jun 2026 | 5 mo late |
| Angad ParkAavani Developers | Kothrud | Jun 2026 | Jun 2026 | 5 mo late |
| Apex Retail MarketOne Apex Infra LLP | Yawalewadi | Jun 2026 | Jun 2026 | 5 mo late |
| ArcadiaAcme Sawant Ventures | Bhilarewadi | Jun 2026 | Oct 2026 | 5 mo late |
| Austin OneDivya Associates | Pimpale Saudagar | Jun 2026 | Oct 2026 | 5 mo late |
| AarambhSeven Star Properties | Pirangut | Jun 2026 | Oct 2026 | 5 mo late |
| Aarti ApartmentChaphalkar Karandikar Developers | Pune (M Corp.) | Jun 2026 | Jun 2026 | 5 mo late |
| Arihant SakshiDharmesh Vasantrai Shah | Wanwadi | Jun 2026 | Jun 2026 | 5 mo late |
| Ashapuri VrundavanAshapuri Developers | Pirangut | Jun 2026 | Oct 2026 | 5 mo late |
| AvantiAmbar Developers | Pune (M Corp.) | Jun 2026 | Oct 2026 | 5 mo late |
| Bhakti RudvedBhakti Builders | Pimpri Chinchawad (M Corp.) | Jun 2026 | Jun 2026 | 5 mo late |
| ChandrahasGANGOTREE HOMES (Formerly known as Gangotree Greenbuild) | Pune (M Corp.) | Jun 2026 | Jun 2026 | 5 mo late |
| Dolphin SerenoDolphin Sereno LLP | Pimpri Chinchawad (M Corp.) | Jun 2026 | Jun 2026 | 5 mo late |
| Durga ViharSatkar Reality | Dhankawadi | Jun 2026 | Oct 2026 | 5 mo late |
| Dwarka Project3Naiknavarehousingdevelopementspvtltd | Mahalunge | Jun 2026 | Jun 2026 | 5 mo late |
| Dinkar ApartmentSiddhhidata Realtors | Chinchwad | Jun 2026 | Jun 2026 | 5 mo late |
| Ecopolitan Phase IIIftekhar Peerpashahusseni Inamdar | Punawale | Jun 2026 | Oct 2026 | 5 mo late |
| Forestia Wing AShakuntal Developers | Dudulgaon | Jun 2026 | Oct 2026 | 5 mo late |
| Fortune PrideFortune Pride | Yawalewadi | Jun 2026 | Jun 2026 | 5 mo late |
| GatewayRaichandani Constructions Private Limited | Kharadi | Jun 2026 | Jun 2026 | 5 mo late |
| Grace PlazaNeelawati Developers and Promoters | Gopalwadi | Jun 2026 | Jun 2026 | 5 mo late |
| Gulmohar ApartmentSai Builders And Developers | Chakan (Ct) | Jun 2026 | Jun 2026 | 5 mo late |
| Godrej Green CoveMahalunge Township Developers Private Limited | Mahalunge | Jun 2026 | Oct 2026 | 5 mo late |
| Hare Krishna KunjB G Promoters And Builders | Kondhwa Bk | Jun 2026 | Oct 2026 | 5 mo late |
| Imperial Atria Tower 2Meridian | Baner | Jun 2026 | Oct 2026 | 5 mo late |
| Indrayani Riverview ResidencyShreenath Developers | Dudulgaon | Jun 2026 | Oct 2026 | 5 mo late |
| Jito NagarJain Ashapuri Developer Unit II | Kondhwa Khurd | Jun 2026 | Oct 2026 | 5 mo late |
| Kj TowerKalyan Jagannath Jadhav | Warje | Jun 2026 | Oct 2026 | 5 mo late |
| Krishiv VistaVed Associates | Kiwale | Jun 2026 | Oct 2026 | 5 mo late |
| Kutumb Prime Project 6Naiknavare Buildcon Private Limited | Mawal | Jun 2026 | Jun 2026 | 5 mo late |
| KomalSrkd Landmark LLP | Karve Nagar | Jun 2026 | Jun 2026 | 5 mo late |
| Kshitij ApartmentSiddhhidata Developer | Chinchwad | Jun 2026 | Oct 2026 | 5 mo late |
| Lambodar ResidenceVighnaharta Landmarks | Pimpale Gurav | Jun 2026 | Oct 2026 | 5 mo late |
| Leela HillsDasscon Realty Private Limited | Kondhwa Khurd | Jun 2026 | Oct 2026 | 5 mo late |
| Love SpringApex Associates | Chikhali | Jun 2026 | Jun 2026 | 5 mo late |
Delayed projects by district
All MaharashtraPune · 2,215Thane · 1,158Raigarh · 1,042Mumbai Suburban · 994Nashik · 483Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 156Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology