Delayed projects in Maharashtra
8,413 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 41 of 169.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Hallmark SquareYogesh Baban Jadhav proprietor of Hallmark properties | Vadgaon AnandPune | May 2022 | May 2023 | 4 yrs 6 mo late |
| Janavi Plaza, Janavi TowerJanavi Builders & Developers | Vasaivirar City (M Corp)Palghar | May 2022 | Dec 2024 | 4 yrs 6 mo late |
| Jp ResidencyJp Builders & Developers | Satara (M Cl)Satara | May 2022 | May 2022 | 4 yrs 6 mo late |
| Jaylaxmi ComplexMahalaxmi Builders & Developers | TandulwadiPune | May 2022 | May 2022 | 4 yrs 6 mo late |
| Kansara Mauli ApartmentGanesh Chintaman Chavan | Nashik (M Corp.)Nashik | May 2022 | May 2022 | 4 yrs 6 mo late |
| Magnums Zainab ResidencyNisar Hassan Wagle | Zadgaon CtRatnagiri | May 2022 | May 2022 | 4 yrs 6 mo late |
| Mahalaxmi ResidencyPrabhav Vijay Khawase | Nagpur (M Corp.)Nagpur | May 2022 | May 2022 | 4 yrs 6 mo late |
| Parshv Elite Phase IParshv Homes | BirwadiPalghar | May 2022 | May 2024 | 4 yrs 6 mo late |
| Radha ResidencyOm Developers | NagzariPalghar | May 2022 | May 2022 | 4 yrs 6 mo late |
| S R VillaS R Builders & Developers | Taloje PanchnadRaigarh | May 2022 | May 2022 | 4 yrs 6 mo late |
| Sai Leela ResidencyR K Builders And Developers | PanvelRaigarh | May 2022 | May 2022 | 4 yrs 6 mo late |
| SaidhamAnil Pandurang Mungaji | Vadghar (Ct)Raigarh | May 2022 | May 2022 | 4 yrs 6 mo late |
| Shree Neha ChslHari Om Sai Grihanrmiti Pvt Ltd | KurlaMumbai Suburban | May 2022 | Sep 2025 | 4 yrs 6 mo late |
| Shree Samarth NiwasPrachi Enterprises | Palghar | May 2022 | Dec 2023 | 4 yrs 6 mo late |
| Shree SrushtiShree Associates & Developers | Dhayari (Part)Pune | May 2022 | May 2022 | 4 yrs 6 mo late |
| Shrirang HeightsShivaji Shripati Pawar | Kodoli (Ct)Satara | May 2022 | May 2022 | 4 yrs 6 mo late |
| Silver SkiesVighnesh Developers | ChikhaliPune | May 2022 | May 2022 | 4 yrs 6 mo late |
| SkygoldShivsai Properties | KesnandPune | May 2022 | Dec 2024 | 4 yrs 6 mo late |
| Skyland ResidencyGaurav Kachhara | BopeleRaigarh | May 2022 | May 2022 | 4 yrs 6 mo late |
| SwashrayShanti Enterprise | BorivaliMumbai Suburban | May 2022 | Dec 2022 | 4 yrs 6 mo late |
| Swami Swarupanand ElitePravin Narayan Lad | KasopRatnagiri | May 2022 | May 2023 | 4 yrs 6 mo late |
| The CoralShantaram Damu Patil | UlaweRaigarh | May 2022 | May 2022 | 4 yrs 6 mo late |
| Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase IIVaishnavi Mahila Unnati Sanstha | Uruli DevachiPune | May 2022 | Nov 2023 | 4 yrs 6 mo late |
| Wisdom County Phase IArihant Edifice Private Ltd. | KurkumbhPune | May 2022 | May 2022 | 4 yrs 6 mo late |
| Nakshatra GreenSwami Capital | Pune (M Corp.)Pune | May 2022 | May 2022 | 4 yrs 6 mo late |
| Raut BuildingBhavna C Chheda | Thane (M Corp.)Thane | May 2022 | May 2022 | 4 yrs 6 mo late |
| Farmdean Prakash ResidencyFarmdean Builder Private Limited | Vadghar (Ct)Raigarh | Jun 2022 | Mar 2023 | 4 yrs 5 mo late |
| Friends CapitalAbdul Salim Qureshi | Jalna (M Cl)Jalna | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Moreshwar And Tamboli HeightsSumit Developers | Solapur (M Corp.)Solapur | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Park VisionVva Vision Realtors LLP | Ward GnorthMumbai City | Jun 2022 | Jun 2024 | 4 yrs 5 mo late |
| Shivraj 3 KedarnathNitin Dolke | Nagpur (M Corp.)Nagpur | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| 157 158 Guruwar PethPrathmesh Construction | Pune CityPune | Jun 2022 | Jun 2023 | 4 yrs 5 mo late |
| V N P Apartment C and D wingPranav Vasant Pawar | Nashik | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Uma ResidencyDipak Babanrao Kavitake | Daund (Ct)Pune | Jun 2022 | Jan 2026 | 4 yrs 5 mo late |
| Geras Misty WatersGera Developments Private Limited | KeshavnagarmundwaPune | Jun 2022 | Jun 2023 | 4 yrs 5 mo late |
| Vtp TownsquareNnp Buildcon Pvt. Ltd | MahalungePune | Jun 2022 | Mar 2025 | 4 yrs 5 mo late |
| Sp Residency Phase IIISupra Warehousing Private Limited | FursungiPune | Jun 2022 | Jun 2024 | 4 yrs 5 mo late |
| Square Park 1K K Buildcon Amenity And A Building | Talegaon DhamdherePune | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Parmar HeritageJitendra | AndheriMumbai Suburban | Jun 2022 | Mar 2026 | 4 yrs 5 mo late |
| Shree Sambhav Darshan CHSShree Sai Shraddha Associates | BorivaliMumbai Suburban | Jun 2022 | Dec 2025 | 4 yrs 5 mo late |
| Shree DarshanSanjay Dattatray Dandekar | Khed (M Cl)Ratnagiri | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Sairaj ApartmentJidnyasa Realtors | SaradwadiNashik | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| PraptiPrapti Enterprises | AmbarnathThane | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Aakruti Aashvi ApartmentAakruti Aashvi Developers | KurlaMumbai Suburban | Jun 2022 | Jun 2026 | 4 yrs 5 mo late |
| Aashraykalyani developers | Pune (M Corp.)Pune | Jun 2022 | Dec 2024 | 4 yrs 5 mo late |
| Abdul Aziz ApartmentSkyblue Homes Private Limited | Dapoli CampRatnagiri | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Akshara GardenNahar Reality | KatrajPune | Jun 2022 | Mar 2024 | 4 yrs 5 mo late |
| Apex DevelopersApex Developers | Vasai Virar City (M Corp)Palghar | Jun 2022 | Jan 2025 | 4 yrs 5 mo late |
| AranyaPrashant Mohan Barge | Satara (M Cl)Satara | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
| Archit ResidencyKiran Purushottam Bachhav | Malegaon (M Corp.)Nashik | Jun 2022 | Jun 2022 | 4 yrs 5 mo late |
Delayed projects by district
Pune · 2,214Thane · 1,157Raigarh · 1,041Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology