Birwadi, Palghar
Deedo IDDL-PAL-BIRWADI10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects6
Registrations6
Completion still due33 past their date
Median extension36 months83% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
6 MahaRERA registrations in Birwadi
3 extended, not yet due3 past even the latest date
Extended registrations moved their completion date by a median of 36 months.
Projects in Birwadi
6 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Jivdani EnclaveVs Infra Builders And Developers | Due Apr 2030, extended 4 mo | — | — |
| Kamla EnclaveKapil Mani Tripathi | 2 yrs 11 mo late | — | — |
| Mahi RegencyMohammad Barik Shaukat Shaikh | Due Dec 2027, extended 3 yrs 4 mo | — | 43% |
| Parshv Elite Phase IParshv Homes | 4 yrs 6 mo late | — | 64% |
| Flower Valley ComplexSheru Shamsher Khan | 3 yrs 11 mo late | — | 36% |
Nearby: other villages in Palghar
Most active promoters
- Kapil Mani Tripathi1 project
- Mohammad Barik Shaukat Shaikh1 project
- Parshv Homes1 project
- Raj Mandir Reality1 project
- Sheru Shamsher Khan1 project
- Vs Infra Builders And Developers1 project
Birwadi, in questions
How many projects in Birwadi run late?
10 in 10 MahaRERA registrations (6 of 6): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Birwadi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology