Skip to content

Delayed projects in Pune

2,214 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 5 of 45.

ProjectLocalityPromisedRevisedDelivery
Ratnadeep Wing BG P EnterprisesPimpale GuravDec 2019Dec 20216 yrs 11 mo late
SAMARPIT CITY - A1 and A2Sadguru ConstructionsShikrapurDec 2019Dec 20236 yrs 11 mo late
Shalini ShubharambhShalini DevelopersAmbegaon KhDec 2019Jun 20226 yrs 11 mo late
Shree Gurudatta DevelopersShree Gurudatta DevelopersWarwandDec 2019Dec 20196 yrs 11 mo late
Shri Ganesh ParkSanjay Parshuram KuteKolwadiDec 2019Dec 20216 yrs 11 mo late
ShubhkalashPurple GroupPimpri Chinchawad (M Corp.)Dec 2019Dec 20196 yrs 11 mo late
SonaidadaUdaykant Ranoji AndekarPune (M Corp.)Dec 2019Dec 20196 yrs 11 mo late
Subhadra HeightsC K DevelopersUravadeDec 2019Dec 20246 yrs 11 mo late
SwagatpsassociatesCharholi KhDec 2019Dec 20206 yrs 11 mo late
Sai BlessingsAbhijit Prakash BorasePimpri Chinchawad (M Corp.)Dec 2019Jun 20226 yrs 11 mo late
Sai BlossomVedant PropertiesDhanoriDec 2019May 20226 yrs 11 mo late
The Prestige AvenueSix Aces Realtors LLPPashanDec 2019Jun 20226 yrs 11 mo late
Trisha ResidencyNameeta Swapnil JoshiTalegaon Dabhade (M Cl)Dec 2019Dec 20196 yrs 11 mo late
Vishal Vishwa Phase 2 - Building Number 1 And 2Vishal ConstructionsTalegaon DhamdhereDec 2019Dec 20216 yrs 11 mo late
VedantShree Siddhivinayak Construction GroupSasvad (M Cl)Dec 2019Jul 20226 yrs 11 mo late
Vansh RealtyJ V DevelopersTalegaon Dabhade (M Cl)Jan 2020Jan 20206 yrs 10 mo late
Aqura ParadiseAqura Builder & Developer Private LimitedPune (M Corp.)Jan 2020Jun 20226 yrs 10 mo late
Mantri EmporioShore Dwellings Private LimitedKharadiJan 2020Mar 20266 yrs 10 mo late
SilvanaShreeji GroupSomataneFeb 2020Feb 20206 yrs 9 mo late
Alfa CornerAnand DevelopersBanerMar 2020Mar 20206 yrs 8 mo late
Krish LandmarkHemanshu Prataprai ShahKharadiMar 2020Mar 20246 yrs 8 mo late
Gayatri MantraIdeal ConstructionPimpri Chinchawad (M Corp.)Mar 2020Mar 20226 yrs 8 mo late
SaiplazaAgasti DevelopersRajgurunagar (Ct)Mar 2020Dec 20256 yrs 8 mo late
Urban Life Ventures Aapli SocietyUrban Life VenturesParvatiMar 2020Aug 20226 yrs 8 mo late
SwamipuramSandeep Janardhan LandgeAalandiApr 2020Mar 20226 yrs 7 mo late
Chakan AnnexSangam RealtyPimpalgaon Tarf KhedJun 2020Jun 20236 yrs 5 mo late
AyodhyapuramAbhaydev DevelopersTalegaon DhamdhereJun 2020Oct 20226 yrs 5 mo late
Bhagyasthan Phase1Tulip Inn Construwell Pvt. Ltd.Talegaon Dabhade (R)Jun 2020Jul 20246 yrs 5 mo late
Gagan TishaGagan DevelopersUndriJun 2020Oct 20226 yrs 5 mo late
Rudra PalaceSunil Gajaram KawareWagholiJul 2020Jul 20206 yrs 4 mo late
Swastik MadhurSwastik ConstructionMahalungeSep 2020Sep 20206 yrs 2 mo late
Aishwaryam NivaaraSai Essen PropertiesChikhaliSep 2020Jun 20226 yrs 2 mo late
CentropolisSkywards Ashtika LifestylePune (M Corp.)Sep 2020Oct 20266 yrs 2 mo late
Fortune ShilpFortune Vastushilpa Buildcon LLPManSep 2020Mar 20226 yrs 2 mo late
Kirad PrideDevachand Baburao KiradPune (M Corp.)Sep 2020Sep 20206 yrs 2 mo late
Madhurangan ApartmentShri Yogesh Prabhakar DholeMaladSep 2020Sep 20206 yrs 2 mo late
NatrajplazaVikram Vedprakash AgarwalPune (M Corp.)Sep 2020Mar 20226 yrs 2 mo late
Priya ApartmentMantri ConstructionDaund (M Cl)Sep 2020Sep 20206 yrs 2 mo late
S R K CornerS R K RealtyPimpale GuravSep 2020Sep 20206 yrs 2 mo late
Sadashiv Apartments B and C BuildingVasant Shriram KhedkarRajgurunagar (Ct)Sep 2020Sep 20206 yrs 2 mo late
Saipushp ResidencyRohit DevelopersPimpale GuravSep 2020Sep 20206 yrs 2 mo late
SarvadnyaMangesh Namdev KudaleHaveliSep 2020Jun 20226 yrs 2 mo late
Venkatesh HeightsVenkatesh AssociatesShirur GraminSep 2020Dec 20236 yrs 2 mo late
Xrbia Eiffel City Chakan Ph1Xrbia Chakan Developers Private LimitedChakan (Ct)Sep 2020Mar 20226 yrs 2 mo late
Dsk Gold LeafD S Kulkarni Developers LimitedBanerOct 2020Oct 20206 yrs 1 mo late
Dsk MayurbanD S Kulkarni Developers LimitedPirangutOct 2020Oct 20206 yrs 1 mo late
Dsk NandanvanD S Kulkarni Developers LimitedPirangutOct 2020Oct 20206 yrs 1 mo late
Mohan PetalsAkshay BhujbalBhosariOct 2020Oct 20216 yrs 1 mo late
Swastik Spira Phase IISwastik RealtyChikhaliOct 2020Oct 20206 yrs 1 mo late
prathamesh Residencyprathamesh builders & developersBaramati (M Cl)Oct 2020Oct 20206 yrs 1 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology