Gagan Tisha
Deedo IDDP-PUN-XBBSCompletion was pushed back 2 years and 4 months to Oct 2022, and that date has passed too; no MahaRERA orders on record; 56% of its units are booked.
Undri, Pune 411060 · Property rates in Undri · by Gagan Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 2 years and 4 months to Oct 2022, and that date has passed too
- This projectRegistered 15 Jul 2017, completion promised 30 Jun 2020, revised to 31 Oct 2022, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Nov 2026 | A · 609 | Rental | — | View Rental, Nov 2026 | |
| Aug 2026 | A · 1102 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | A · 308 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | A · 210 | Mortgage | — | View Mortgage, Aug 2026 | |
| Aug 2026 | A · 508 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | A · 210 | Resale | 368 sq ft | View Resale, Aug 2026 | |
| Jul 2026 | A · 1307 | Rental | — | View Rental, Jul 2026 | |
| Jul 2026 | A · 310 | Rental | — | View Rental, Jul 2026 | |
| Jul 2026 | A · 501 | Rental | — | View Rental, Jul 2026 | |
| Jul 2026 | A · 402 | Rental | — | View Rental, Jul 2026 |
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100000351
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100000351 | 15 Jul 2017 | 30 Jun 2020 | 31 Oct 2022 | Gagan Developers | Project page |
Documents147
2 documents held by Deedo, 145 filings listed on MahaRERA's project page
Finance
- PAN CardGagan Developers Pan Card.pdf · uploaded 8 Jul 2017Source
Legal
Migrated
- 1 PAN CardGagan Developers Pan Card.pdf · uploaded 8 Jul 2017Source
Show all 147 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportLegal Title Tisha.pdf · uploaded 8 Jul 2017Source
- 1 Details of encumbrancesENCUMBRANCE CERTIFICATE.pdf · uploaded 8 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)1-5.pdf · uploaded 8 Jul 2017Source
- 1 Building Plan Approval (IOD)2-5.pdf · uploaded 8 Jul 2017Source
- 2 Building Plan Approval (IOD)3-5.pdf · uploaded 8 Jul 2017Source
- 3 Building Plan Approval (IOD)4-5.pdf · uploaded 8 Jul 2017Source
- 4 Building Plan Approval (IOD)5-5.pdf · uploaded 8 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentTisha CC.pdf · uploaded 8 Jul 2017Source
- 1 Declaration in FORM BDEVELOPERS FORM B.pdf · uploaded 8 Jul 2017Source
- 1 Proforma of Allotment letterUNIT AGREEMENT.pdf · uploaded 8 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 11 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Tisha architect certificate.pdf · uploaded 13 Jul 2017Source
- 1 Certificates of CA (Form 3)CA Certificate-Tisha.pdf · uploaded 13 Jul 2017Source
- 2 Proforma of Allotment letterUNIT AGREEMENT.pdf · uploaded 4 Aug 2017Source
- 3 Proforma of Allotment letterUNIT AGREEMENT.pdf · uploaded 4 Aug 2017Source
- 4 Proforma of Allotment letterTISHA - UNIT AGREEMENT.pdf · uploaded 26 Oct 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Tisha Engineer Certificate.pdf · uploaded 31 Mar 2018Source
- 2 Certificates of CA (Form 3)CA Cert Gagan Developers.pdf · uploaded 31 Mar 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Dec Tisha.pdf · uploaded 9 Apr 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Mar'18 Tisha.pdf · uploaded 19 Jun 2018Source
- 3 Certificates of CA (Form 3)CA Certificate Mar'18 Tisha.pdf · uploaded 19 Jun 2018Source
- 1 Certificates of CA (Form 5)Form 5 Gagan Devlopers.pdf · uploaded 30 Sep 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Cubix.pdf · uploaded 4 Dec 2018Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate.pdf · uploaded 4 Dec 2018Source
- 4 Certificates of CA (Form 3)Form 3.pdf · uploaded 4 Dec 2018Source
- 5 Certificates of CA (Form 3)Form 3.pdf · uploaded 29 Dec 2018Source
- 2 Copy of Layout Approval (in case of layout)1-1.pdf · uploaded 22 Jan 2019Source
- 5 Building Plan Approval (IOD)1-8.pdf · uploaded 22 Jan 2019Source
- 6 Building Plan Approval (IOD)2-8.pdf · uploaded 22 Jan 2019Source
- 7 Building Plan Approval (IOD)3-8.pdf · uploaded 22 Jan 2019Source
- 8 Building Plan Approval (IOD)4-8.pdf · uploaded 22 Jan 2019Source
- 9 Building Plan Approval (IOD)5-8.pdf · uploaded 22 Jan 2019Source
- 10 Building Plan Approval (IOD)6-8.pdf · uploaded 22 Jan 2019Source
- 11 Building Plan Approval (IOD)7-8.pdf · uploaded 22 Jan 2019Source
- 12 Building Plan Approval (IOD)8-8.pdf · uploaded 22 Jan 2019Source
- 2 Commencement Certificates / NA Order for plotted developmentBuilding CC.pdf · uploaded 22 Jan 2019Source
- 3 Commencement Certificates / NA Order for plotted developmentLayout CC.pdf · uploaded 22 Jan 2019Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate .pdf · uploaded 6 Apr 2019Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 6 Apr 2019Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 6 Apr 2019Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 6 Apr 2019Source
- 6 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 6 Apr 2019Source
- 7 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 6 Apr 2019Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 15 Jun 2019Source
- 2 Certificates of CA (Form 5)Form 5.pdf · uploaded 28 Sep 2019Source
- 2 Details of encumbrancesNOC Edelweiss.Pdf · uploaded 22 Feb 2020Source
- 3 Details of encumbrancesEncumbrance Certificate 24-02-2020.pdf · uploaded 24 Feb 2020Source
- 1 OtherIndex II.pdf · uploaded 24 Feb 2020Source
- 2 Declaration in FORM BAffidavit Cum Declaration.pdf · uploaded 25 Feb 2020Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 25 Feb 2020Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Tisha Architect.pdf · uploaded 25 Feb 2020Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 25 Feb 2020Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 25 Feb 2020Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 25 Feb 2020Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 25 Feb 2020Source
- 8 Certificates of CA (Form 3)Form 3.pdf · uploaded 25 Feb 2020Source
- 9 Certificates of CA (Form 3)Form 3.pdf · uploaded 25 Feb 2020Source
- 10 Certificates of CA (Form 3)Form 3.pdf · uploaded 25 Feb 2020Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Aug 2020Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 14 Aug 2020Source
- 11 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Aug 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5.pdf · uploaded 30 Sep 2020Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)From 5 Gagan Tisha.pdf · uploaded 6 Feb 2021Source
- 3 Copy of Layout Approval (in case of layout)1-1.pdf · uploaded 24 Jul 2021Source
- 4 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 24 Jul 2021Source
- 13 Building Plan Approval (IOD)Building Plan 1.pdf · uploaded 24 Jul 2021Source
- 14 Building Plan Approval (IOD)Building Plan 2.pdf · uploaded 24 Jul 2021Source
- 15 Building Plan Approval (IOD)Building Plan 3.pdf · uploaded 24 Jul 2021Source
- 16 Building Plan Approval (IOD)Building Plan 3.pdf · uploaded 24 Jul 2021Source
- 17 Building Plan Approval (IOD)Building Plan 4.pdf · uploaded 24 Jul 2021Source
- 18 Building Plan Approval (IOD)Building Plan 5.pdf · uploaded 24 Jul 2021Source
- 19 Building Plan Approval (IOD)Building Plan 6.pdf · uploaded 24 Jul 2021Source
- 20 Building Plan Approval (IOD)Building Plan 7.pdf · uploaded 24 Jul 2021Source
- 21 Building Plan Approval (IOD)Building Plan 8.pdf · uploaded 24 Jul 2021Source
- 22 Building Plan Approval (IOD)Building Plan 9.pdf · uploaded 24 Jul 2021Source
- 23 Building Plan Approval (IOD)Building Plan 10.pdf · uploaded 24 Jul 2021Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 24 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance.pdf · uploaded 24 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance.pdf · uploaded 24 Jul 2021Source
- 1 Disclosure of sold/ booked inventorySold booked inventory.pdf · uploaded 24 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5.pdf · uploaded 24 Jul 2021Source
- 12 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 6 Aug 2021Source
- 13 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 6 Aug 2021Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Tisha Architect Certificate.pdf · uploaded 7 Sep 2021Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Tisha Engineer Certificate.pdf · uploaded 7 Sep 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)From 5.pdf · uploaded 30 Sep 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Gagan Tisha.pdf · uploaded 6 Dec 2022Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Dec 2022Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Dec 2022Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Dec 2022Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Dec 2022Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Dec 2022Source
- 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Dec 2022Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Dec 2022Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Dec 2022Source
- 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Dec 2022Source
- 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Dec 2022Source
- 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Dec 2022Source
- 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Dec 2022Source
- 14 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Dec 2022Source
- 15 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Dec 2022Source
- 16 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Dec 2022Source
- 17 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Dec 2022Source
- 18 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Dec 2022Source
- 19 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Dec 2022Source
- 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 16 Feb 2023Source
- 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 16 Feb 2023Source
- 20 Certificates of CA (Form 3)Form 3.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Gagan Tisha.pdf · uploaded 22 Oct 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)GAGAN TISHA.pdf · uploaded 9 Aug 2024Source
Technical
- Document1-5.pdf · uploaded 8 Jul 2017Source
- Document2-5.pdf · uploaded 8 Jul 2017Source
- Document3-5.pdf · uploaded 8 Jul 2017Source
- Document4-5.pdf · uploaded 8 Jul 2017Source
- Document5-5.pdf · uploaded 8 Jul 2017Source
- Document1-1.pdf · uploaded 22 Jan 2019Source
- Document1-8.pdf · uploaded 22 Jan 2019Source
- Document2-8.pdf · uploaded 22 Jan 2019Source
- Document3-8.pdf · uploaded 22 Jan 2019Source
- Document4-8.pdf · uploaded 22 Jan 2019Source
- Document5-8.pdf · uploaded 22 Jan 2019Source
- Document6-8.pdf · uploaded 22 Jan 2019Source
- Document7-8.pdf · uploaded 22 Jan 2019Source
- Document8-8.pdf · uploaded 22 Jan 2019Source
- Document1-1.pdf · uploaded 24 Jul 2021Source
- DocumentLayout.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 1.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 2.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 3.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 3.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 4.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 5.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 6.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 7.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 8.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 9.pdf · uploaded 24 Jul 2021Source
- DocumentBuilding Plan 10.pdf · uploaded 24 Jul 2021Source
Technical (Architect)
- DocumentArchitect Certificate.pdf · uploaded 16 Feb 2023Source
Technical (Engineer)
- DocumentEngineers Certificate.pdf · uploaded 16 Feb 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 18/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK128 units in all
- Address
- 18/1, Undri, UndriPIN 411060
- Village
- Undri, Haveli taluka
- Location
- 18.46020, 73.91254
- Land area for this project
- 4,525 sq m (48,707 sq ft)
- Permissible built-up area
- 7,306 sq m (78,641 sq ft)
- Sanctioned built-up area
- 7,306 sq m (78,641 sq ft)
- Recreational open space
- 453 sq m (4,871 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
18/1
Boundaries
- North
- S No 19
- South
- S No 18
- East
- S No 18
- West
- Road and S No 18
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking128 units
72 of 128 units booked (56%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.17 sq m · 368 sq ft | 50 | 21 |
| 2BHK | 46.06 sq m · 496 sq ft | 50 | 32 |
| 2BHK | 46.93 sq m · 505 sq ft | 13 | 9 |
| 2BHK | 49.43 sq m · 532 sq ft | 13 | 10 |
| 3BHK | 61.39 sq m · 661 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals37
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Arc Imran Shaikh | — |
| Chartered accountant | Kunal Jhamvar | — |
| Engineer | Mr.Rajesh Mankani | — |
| Other | Mr.Ajay | — |
| Other | Mr.Bandal | — |
| Other | Mr.Ghule | — |
| Other | Mr.Gurudatta | — |
| Other | Mr.Manojkumar Bhagat | — |
Show all 37 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Other | Mr.Rahul Harphale | — |
| Other | Mr. Rajesh | — |
| Other | Mr.Rao | — |
| Other | Mr.Sameer Kad | — |
| Other | Mr. Vishal Kardile | — |
| Registered real estate agent | Abhay Motilal Bhurat | — |
| Registered real estate agent | Addressofchoice Realty Pvt Ltd | — |
| Registered real estate agent | Akash Amolokchand Khater | — |
| Registered real estate agent | Amit Arvind Sodani | — |
| Registered real estate agent | ANAROCK Property Consultants Pvt. Ltd. | — |
| Registered real estate agent | Bhisham Suresh Parwani | — |
| Registered real estate agent | Bluenest Properties LLP | — |
| Registered real estate agent | Dhruba Prasad Gupta | — |
| Registered real estate agent | Hasan Khujema Nadir | — |
| Registered real estate agent | Investadvise Wealth Management Private Limited | — |
| Registered real estate agent | Jiten Ashok Gore | — |
| Registered real estate agent | Kirankumar Tarachand Chopda | — |
| Registered real estate agent | Mint Lifespaces | — |
| Registered real estate agent | Murtaza Husaini Hathaiwala | — |
| Registered real estate agent | Optimus Realtors | — |
| Registered real estate agent | Pravin Deochandra Jha | — |
| Registered real estate agent | Premlata Estate Solutions Pvt. Ltd. | — |
| Registered real estate agent | Raviraj Gangaprasad Thanvi | — |
| Registered real estate agent | Sanjay Haribhau Gargate | — |
| Registered real estate agent | Saroj Vinod Jain | — |
| Registered real estate agent | sayed Ali Arabian | — |
| Registered real estate agent | Signet Space Realty Private Limited | — |
| Registered real estate agent | Thomas C Abraham | — |
| Registered real estate agent | Vikas Satish Gupta | — |
Source: MahaRERA project page. Contact details are not shown.
Gagan Tisha in numbers
Registered deals, summarised
Deedo has 361 registered documents at Gagan Tisha, from Mar 2017 to Nov 2026: 134 sales, 145 leave and licence agreements, 69 mortgages. The median registered sale since Mar 2017 works out to about ₹5,200 per sq ft, at a median of ₹32 L a deal; 10% of sales were resales.
- What is the price per sq ft at Gagan Tisha?
- The median registered sale since Mar 2017 works out to about ₹5,200 per sq ft, at a median of ₹32 L a deal; 10% of sales were resales.
- How many properties have been sold at Gagan Tisha?
- 134 sales are registered at Gagan Tisha, 13 of them resales.
- Are properties at Gagan Tisha rented out?
- Yes: 145 leave and licence agreements are registered at Gagan Tisha, at a median rent since Mar 2017 of about ₹13,000 a month with a deposit of about ₹30,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Gagan Tisha by Deedo, last updated with deals registered in Nov 2026.
Latest deal · Rental · Nov 2026
₹10–20k / month