Company or firm · first RERA registration 2017
Gagan Developers
Deedo IDDD-Y0T8Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 76 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay76 mowhen late
Flats sold, all time109registered sale deeds
Regulatory cases0none on record
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gagan TishaP52100000351 | Undri | Certificate Signed | 30 Jun 2020 | 31 Oct 2022 | +76 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology