Gagan Developers

Deedo IDDD-Y0T8

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 76 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay76 mowhen late
Flats sold, all time109registered sale deeds
Regulatory cases0none on record

1 registration of 1 ran past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Gagan TishaP52100000351UndriCertificate Signed30 Jun 202031 Oct 2022+76 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology