Pashane, Raigarh
Deedo IDDL-RAI-PASHANE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects34
Registrations39some projects hold several
Completion still due1326 past their date
Median extension12 months62% of registrations extended
Regulatory cases3on 3 projects
10 in 10 registrations run late here
39 MahaRERA registrations in Pashane
2 not yet due11 extended, not yet due26 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Pashane
34 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Gagangiri ParkGagangiri Group | Due Aug 2029, extended 4 mo | — | — |
| Virat Greenwoods Wing B & DVraj Realty | Due Apr 2030, extended 4 mo | — | — |
| Ashtavinayak ComplexAshtavinayak Enterprises | Due Apr 2030, extended 4 mo | — | — |
| Galaxy VrundavanShree Krishna Enterprises | Due Apr 2033, extended 4 mo | — | — |
| Tulsi VedantShubh Developers | Due Apr 2029, extended 4 mo | — | — |
| Nikhil ParkGurudev Developers | Due Apr 2027, extended 4 mo | — | — |
| Dhruv Residency PlatinumKamlesh Devidas Dhruv | Due Apr 2027, extended 4 mo | — | 17% |
| Gagangiri ComplexGagangiri Developers | 1 yr 11 mo late | — | 77% |
| Virat Greenwoods Wing EVraj Realty | 2 yrs 11 mo late | — | 3% |
| Vaastu SankalpVaastu Enteprises | Due Dec 2026 | — | — |
| Sai Enrich HillsSai Infra Builders And Developers | 11 mo late | — | — |
| Vande Mataram DivineSadguru Shelter | 2 yrs 11 mo late | — | 66% |
| Wellwisher TulipAbhijeet Chandrakant Bhansali | Due Sep 2027, extended 3 yrs 1 mo | — | 11% |
| Wellwisher CosmosWellwisher Developer | 2 yrs 3 mo late | — | — |
| Wellwisher IrisHimgiri Dealcom LLP | Due Oct 2030, extended 4 mo | — | — |
| Wellwisher RoseHimgiri Dealcom LLP | 2 yrs 5 mo late | — | — |
| Wellwisher SunflowerAbhijeet Chandrakant Bhansali | 2 yrs 5 mo late | — | — |
| Galaxygarden Plot No 2 And Plot No 4S K Developers | Completed | — | 83% |
| Virat GreenwoodsVraj Realty | Completed | — | 32% |
| Tulsi V City - Tulsi VivaanRAJ REALTORS (A project by Raj Group) | Completed, extended 3 yrs 6 mo | — | 72% |
| Shree Samarth ResidencyShree Samarth Infra Developers | 6 yrs late | — | 15% |
| Dhruv Residency-NxKpz Enterprise | Completed | — | 84% |
| Himalaya GardensHimalaya Builders And Developers LLP | Completed | — | 84% |
| Gurudev ParkGurudev Enterprises | Completed, extended 1 yr 6 mo | — | — |
| Vardhaman ResidencyGeetadevi Bimleshkumar Jain | 5 yrs 5 mo late | — | 99% |
Nearby: other villages in Karjat
Most active promoters
- Vraj Realty3 projects
- Abhijeet Chandrakant Bhansali2 projects
- Himalaya Builders And Developers Llp2 projects
- Himgiri Dealcom LLP2 projects
- S K Developers2 projects
- Ashtavinayak Enterprises1 project
- DeepJyoti Infra1 project
- Dhruv Associates1 project
- Gagangiri Developers1 project
- Gagangiri Group1 project
Pashane, in questions
How many projects in Pashane run late?
10 in 10 MahaRERA registrations (37 of 39): their completion date was extended or has passed, data through 14 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pashane by Deedo. Medians on fewer than 3 deeds are not shown.
Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology