Delayed projects in Satara
228 MahaRERA projects in Satara are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 5.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Sai GagangiriLahu Balwant Sawant | Wai (Rural) | Aug 2023 | Aug 2023 | 3 yrs 3 mo late |
| Sai AmarDream World Constructions LLP | Khed (Ct) | Aug 2023 | Aug 2023 | 3 yrs 3 mo late |
| Krishnadham ResidencyDhiraj Tanaji Dudhe | Songirwadi (Rural) (Ct) | Sep 2023 | Sep 2023 | 3 yrs 2 mo late |
| Kasa VillageKasa Builders & Contractor | Satara | Oct 2023 | Oct 2024 | 3 yrs 1 mo late |
| Mahagaon HillsVinod Chhaganmal Jain | Mahagaon | Oct 2023 | Oct 2023 | 3 yrs 1 mo late |
| Sai AanganMatoshree Landmark Private limited | Nagthane | Oct 2023 | Oct 2024 | 3 yrs 1 mo late |
| Sai DarshanAmol Nanaso Ghadage | Khindwadi | Oct 2023 | Oct 2023 | 3 yrs 1 mo late |
| Go PadamaPrashant Shantaram Palkar | Satara | Nov 2023 | Nov 2023 | 3 yrs late |
| Gandharva ResidencyVaibhav Madhavrao Yewale | Wai (Rural) | Nov 2023 | Nov 2023 | 3 yrs late |
| Vrundavan Vandanshree rudra developers | Satara | Nov 2023 | Nov 2023 | 3 yrs late |
| Anvi PrideAnay Developers | Satara (M Cl) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Icon ResidencyIcon Infra | Aundh | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Mauli ResidencyMauli Builders And Developers | Karad (M Cl) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Sai Varad ResidencyVarad Builders And Developers | Khed (Ct) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shivaraj ResidencyRanjit Dinkar Shinde | Vanvaswadi | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Shrisai HeightsVishwashri Developers | Kodoli (Ct) | Dec 2023 | Aug 2025 | 2 yrs 11 mo late |
| Silver SpringsVision Developers | Sidhanathwadi (Rural) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| SwapnapurtiSwapnapurti Housing | Karanje Tarf Satara (Ct) | Dec 2023 | Dec 2024 | 2 yrs 11 mo late |
| Star ResidencyBramhachaitanya Developers through Proprietor Guruprasad Madhukar Vaidya | Satara | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Windsor ParkKumar Builders | Bhose | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Ajinkya HeightsSangita Dattatray Bobade | Phaltan (M Cl) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Chandrabhaga PrimeR K Developers | Phaltan (M Cl) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Rudra HeightsPrerana Sachin Rajage | Khed (Ct) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Surekha CornerAditya Developers through Proprietor Kumar Balasaheb Chavan | Kodoli (Ct) | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| YashodhanShreebanshankari Developers through Proprietor Prashant Madhukar Vaidya | Satara | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| Laxmi ResidencyHrd Builders & Developers | Malkapur (Np) | Feb 2024 | Oct 2025 | 2 yrs 9 mo late |
| Shri Swami Samartha ParkDeepak Kantilal Shah & other 2 | Khandala | Feb 2024 | Feb 2024 | 2 yrs 9 mo late |
| Vrundavan City - 2Kalyani Associates | Malkapur (Np) | Mar 2024 | Mar 2024 | 2 yrs 8 mo late |
| Bhandari ClassicAbhishek Radheshyam Bhandari | Karanje Tarf Satara (Ct) | Mar 2024 | Mar 2024 | 2 yrs 8 mo late |
| Ganesh Darshan ResidencySarda Builders And Developers | Karad (M Cl) | Mar 2024 | Mar 2024 | 2 yrs 8 mo late |
| Kriti ShilpKriti Properties | Phaltan (M Cl) | Mar 2024 | Mar 2024 | 2 yrs 8 mo late |
| OberonSaj Buildcon | Saidapur (Ct) | Mar 2024 | Mar 2024 | 2 yrs 8 mo late |
| SakshishilpSakshi Samuh Developers | Songirwadi (Rural) (Ct) | Mar 2024 | Mar 2024 | 2 yrs 8 mo late |
| Rajkamal ComplexSanjay Vinayak Jadhav | Koregaon | Apr 2024 | Dec 2025 | 2 yrs 7 mo late |
| Shahu ParkDream Home Developers | Satara | Apr 2024 | Apr 2024 | 2 yrs 7 mo late |
| Varad Viharvaradvinayak Developers | Godoli (Ct) | Apr 2024 | Apr 2024 | 2 yrs 7 mo late |
| Dharmakalp VillaBhumi Developers Satara | Karanje Tarf Satara (Ct) | May 2024 | May 2024 | 2 yrs 6 mo late |
| Amruta HeightsTirupati Developers | Phaltan (M Cl) | May 2024 | May 2024 | 2 yrs 6 mo late |
| Krupasindhu HightKrupasindu Builder And Construction | Songirwadi (Rural) (Ct) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Mangalam ApartmentMangalam Construction | Thakurki | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Nirman SankulNirman Associates | Mandrulkole | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Prajakta PushpShree Chaitanya Developers | Kodoli (Ct) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Radha KrushanVikram Construction | Saidapur | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Radiant HomesJawad Developers | Kondhave | Jun 2024 | Jun 2026 | 2 yrs 5 mo late |
| Shri Sai ApartmentShri Venkatesh Developers Through Proprietor Suhas Vyankat Saste | Phaltan | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sai Prasad ParkVarad Builders and Promoters | Godoli (Ct) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Hira Greensjaymala Dnyaneshwar shedge | Mahagaon | Jul 2024 | Jul 2024 | 2 yrs 4 mo late |
| Shree Sanjay Sankul Wing AShri Siddhivinayak Builders | Satara | Jul 2024 | Jul 2024 | 2 yrs 4 mo late |
| Krishnakunj Vihar Phase-2Pooja Shridhar Kangralkar | Karanje Tarf Satara (Ct) | Aug 2024 | Aug 2024 | 2 yrs 3 mo late |
| Woodwinds Phase IIAlliance Vanashree Ventures | Dhawadwadi | Aug 2024 | Aug 2024 | 2 yrs 3 mo late |
Delayed projects by district
All MaharashtraPune · 2,214Thane · 1,157Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology