Sai Amar
Deedo IDDP-SAT-QNZDIts promised completion date, Aug 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Khed (Ct), Satara 415002 · by Dream World Constructions Llp
Buying a flat here?
See every deed registered on it.
Its promised completion date, Aug 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 23 Aug 2018, completion promised 28 Aug 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52700017489
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700017489 | 23 Aug 2018 | 28 Aug 2023 | 28 Aug 2023 | Dream World Constructions LLP | Project page |
Documents35
2 documents held by Deedo, 33 filings listed on MahaRERA's project page
Show all 35 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)p02.pdf · uploaded 13 Aug 2018Source
- 1 Building Plan Approval (IOD)PLAN.pdf · uploaded 13 Aug 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMICEMENT CERTIFICATE-ilovepdf-compressed-ilovepdf-compressed_compressed.pdf · uploaded 13 Aug 2018Source
- 1 Declaration in FORM BAFFIDAVATE.pdf · uploaded 13 Aug 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 13 Aug 2018Source
- 1 Certificates of CA (Form 3)RERA registration_CA CERTIFICATE.pdf · uploaded 13 Aug 2018Source
- 1 Proforma of Allotment lettersale agrrement-ilovepdf-compressed.pdf · uploaded 13 Aug 2018Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Completion Certificate Architech_compressed (1).pdf · uploaded 15 Jul 2020Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 18 Sep 2020Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 2 Aug 2022Source
- 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 2 Aug 2022View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1 New-com.pdf · uploaded 23 Feb 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200261204559_For_Asset_Based_Search_23_02_2023_19_06_14_753.pdf · uploaded 23 Feb 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other Real Estate Organisation-com.pdf · uploaded 23 Feb 2023Source
- 1 Proforma of Agreement for saleSale Deed Format.pdf · uploaded 23 Feb 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDisclosure of Seperate Bank Account-com.pdf · uploaded 23 Feb 2023Source
- 1 Deviation Report with respect to Allotment letterModel Form of Allotment Letter-com.pdf · uploaded 23 Feb 2023Source
- 1 Deviation Report with respect to model copy of AgreementModel Form of Allotment Letter-com.pdf · uploaded 23 Feb 2023Source
- 2 a Details of encumbrances concerned to FinanceSai Amar No Encumbrance of Partner.pdf · uploaded 24 Feb 2023Source
- 1 b Details of encumbrances concerned to LegalSai Amar No Encumbrance of Partner.pdf · uploaded 24 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A 2019-20.pdf · uploaded 24 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A 2020-21.pdf · uploaded 24 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A 2021-22.pdf · uploaded 24 Feb 2023Source
Technical (Architect)
- DocumentArchitect Certificate Form 1 New-com.pdf · uploaded 23 Feb 2023Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE.pdf · uploaded 13 Aug 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 76/6
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Office shop, Resi flat, Resiflat, Resi flats, Shop24 units in all
- Address
- 76/6, Khed Road, Vasant NagarPIN 415002
- Village
- Khed (CT), Satara taluka
- Location
- 17.70180, 74.03295
- Land area for this project
- 2,600 sq m (27,986 sq ft)
- Permissible built-up area
- 2,149 sq m (23,129 sq ft)
- Sanctioned built-up area
- 2,149 sq m (23,129 sq ft)
- Recreational open space
- 582 sq m (6,265 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
76/6
Boundaries
- North
- Khed Roed
- South
- Jadhav 76
- East
- Survey No 76
- West
- Shelar Apt
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking24 units
0 of 24 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office shop | 14.72 sq m · 158 sq ft | 2 | 0 |
| Resi flat | 62.32 sq m · 671 sq ft | 1 | 0 |
| Resi flat | 62.81 sq m · 676 sq ft | 1 | 0 |
| Resiflat | 65.09 sq m · 701 sq ft | 1 | 0 |
| Resi flats | 45.73 sq m · 492 sq ft | 3 | 0 |
| Resi flats | 46 sq m · 495 sq ft | 2 | 0 |
| Resi flats | 47.93 sq m · 516 sq ft | 2 | 0 |
| Resi flats | 48.64 sq m · 524 sq ft | 1 | 0 |
Show all 15 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Resi flats | 48.91 sq m · 526 sq ft | 1 | 0 |
| Resi flats | 48.93 sq m · 527 sq ft | 1 | 0 |
| Resi flats | 50.83 sq m · 547 sq ft | 3 | 0 |
| Resi flats | 59.23 sq m · 638 sq ft | 2 | 0 |
| Resi flats | 62.02 sq m · 668 sq ft | 2 | 0 |
| Shop | 19.27 sq m · 207 sq ft | 1 | 0 |
| Shop | 20.72 sq m · 223 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vijaykumar Patil | — |
| Chartered accountant | Sandip Anandrao Sutar | — |
| Engineer | Suraj Sanjay Jadhav | — |
Source: MahaRERA project page. Contact details are not shown.