Skip to content
Residential / Group Housing · 1 building · 20 unitsRERA P52700024573

Varad Vihar

Deedo IDDP-SAT-SDBE

Its promised completion date, Apr 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Godoli (Ct), Satara 415001 · by Varadvinayak Developers

Delivery2 yrs 7 mo past duePromised Apr 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 20 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Apr 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 24 Feb 2020, completion promised 30 Apr 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52700024573
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5270002457324 Feb 202030 Apr 202430 Apr 2024varadvinayak DevelopersProject page
Documents29

1 document held by Deedo, 28 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportscan_20200212_0001.pdf · uploaded 12 Feb 2020Source
  • Declaration Form Bscan_20200212_0002.pdf · uploaded 12 Feb 2020Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)Godoli 1-compressed.pdf · uploaded 8 Feb 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentGodoli 2-compressed.pdf · uploaded 8 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentsanction permission 1.pdf · uploaded 8 Feb 2020Source
  • 1 Details of encumbrancesnon encumbarance.pdf · uploaded 10 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 10 Feb 2020Source
Show all 29 documentsShow fewer documents

Migrated

  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca certificate (1).pdf · uploaded 10 Feb 2020Source
  • 1 Copy of the legal title reportscan_20200212_0001.pdf · uploaded 12 Feb 2020Source
  • 1 Declaration in FORM Bscan_20200212_0002.pdf · uploaded 12 Feb 2020Source
  • 1 Proforma of Allotment letterAgreement of formant Rera .pdf · uploaded 12 Feb 2020Source
  • 1 Status of ConveyanceF 103.pdf · uploaded 4 Aug 2021Source
  • 2 Status of ConveyanceF 104.pdf · uploaded 4 Aug 2021Source
  • 3 Status of ConveyanceF 105.pdf · uploaded 4 Aug 2021Source
  • 4 Status of ConveyanceF 202.pdf · uploaded 4 Aug 2021Source
  • 5 Status of ConveyanceF 205.pdf · uploaded 4 Aug 2021Source
  • 6 Status of ConveyanceF 301.pdf · uploaded 4 Aug 2021Source
  • 7 Status of ConveyanceF 302.pdf · uploaded 4 Aug 2021Source
  • 8 Status of ConveyanceF 304.pdf · uploaded 4 Aug 2021Source
  • 9 Status of ConveyanceF 305.pdf · uploaded 4 Aug 2021Source
  • 10 Status of ConveyanceF 404.pdf · uploaded 4 Aug 2021Source
  • 11 Status of ConveyanceF 405.pdf · uploaded 4 Aug 2021Source
  • 12 Status of ConveyanceF 102 (2).pdf · uploaded 27 Sep 2021Source
  • 13 Status of ConveyanceF 204 raviraj kadam.pdf · uploaded 27 Sep 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)society certificate.pdf · uploaded 14 Apr 2022Source

Technical

  • DocumentGodoli 1-compressed.pdf · uploaded 8 Feb 2020Source
  • DocumentGodoli 2-compressed.pdf · uploaded 8 Feb 2020Source

Technical (Architect)

  • Documentarchitect certificate.pdf · uploaded 10 Feb 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel survey no 154/D/3/4/1/1 plot no 15/1A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK20 units in all
Address
survey no 154/D/3/4/1/1 plot no 15/1A, shahunagar, opp telephone exchangePIN 415001
Village
Godoli (CT), Satara taluka
Land area for this project
965 sq m (10,387 sq ft)
Permissible built-up area
1,157 sq m (12,455 sq ft)
Sanctioned built-up area
1,157 sq m (12,455 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

survey no 154/D/3/4/1/1 plot no 15/1A

Land as published on MahaRERA's project page

survey no 154/D/3/4/1/1 plot no 15/1A

Boundaries

North
adjusent plot number 14
South
Road and plot number 15 - 1B
East
plot no 15-2
West
survey no 155

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking20 units

0 of 20 units booked (0%), as the promoter reported to MahaRERA

1BHK · 8 units2BHK · 12 units
TypeCarpet areaUnitsBooked
1BHK45.68 sq m · 492 sq ft20
1BHK46.2 sq m · 497 sq ft20
1BHK46.35 sq m · 499 sq ft40
2BHK62.27 sq m · 670 sq ft20
2BHK62.41 sq m · 672 sq ft20
2BHK62.84 sq m · 676 sq ft20
2BHK62.98 sq m · 678 sq ft20
2BHK63.7 sq m · 686 sq ft20
2BHK63.97 sq m · 689 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrasad D Kasture—
Chartered accountantDhiraj R Kasat—
EngineerShriram A kulkarni—
OtherVishal Babasaheb Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology