2,214 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 25 of 45.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Gokhale Business HubGokhale Heights LLP | Kothrud | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| GovindaR J Brothers | Kondhwa Bk | Jun 2024 | Dec 2025 | 2 yrs 5 mo late |
| Green City Phase II K BuildingAjit Girdharilal Nahar | Shivne (Part) | Jun 2024 | Jun 2025 | 2 yrs 5 mo late |
| Gulmohar SquareRajkumar Chamanlal Behr | Mundhawa | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Hatimi Hills Phase II Building FPyramid Infrastructure | Yawalewadi | Jun 2024 | Dec 2025 | 2 yrs 5 mo late |
| JD GaathaShree Jagadguru Developers | Lohgaon | Jun 2024 | Mar 2026 | 2 yrs 5 mo late |
| Jewel SquareVardhaman Buildcons | Pune (Cb) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| KojagiriGokhale Realty LLP | Kothrud | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Lake VistaLake Vista Propertis LLP | Bhugaon | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Madhura ApartmentSathe Shah Developers | Parvati | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Manik VillaSamarth Associates | Sinhgad Road | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Manohar ParadiseBhagyashree Bharat Shastri | Baner | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Manohar ResidencyManohar Civil Services | Baner | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| N V Business CenterN V Construction Company | Somatane | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| North East Business CapitalShiv Properties | Chikhali | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| North East Business CornerShiv Properties | Chikhali | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| NayanaGokhale Promoters LLP | Kothrud | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Nexus WestprideNexus Buildtech | Punawale | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Nyati Enthral INyati Landmark Projects LLP | Kharadi | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Om Ganesh CornerJai Ganesh Developers | Sasvad (M Cl) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Onnyyx AurrumOnnyyx Realtors | Pune (M Corp.) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| ParadiseAmarnath Buildcon | Charholi | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Purvanchal F BuildingVTP Corpartion LLP | Kesnand | Jun 2024 | Jun 2025 | 2 yrs 5 mo late |
| Ramanand ComplexDisha Constructions | Talegaon Dabhade (M Cl) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Royal ResidencyAbdul Rehman Durrani | Vadgaonsheri | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Rivers Edge Wing BKokane Builders | Pimpri Chinchawad (M Corp.) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sai Anirudha DhamSmw Builders And Developers | Wadagaon (Ct) | Jun 2024 | Jun 2025 | 2 yrs 5 mo late |
| Sai KrupaAditya Associates | Talegaon Dabhade (R) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sai SadanAbhishek Enterprises | Kondhwa Bk | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sai VatsalyaShree Sai Associates | Hadapsar | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Samarth ResidencyShree Swami Developers | Pune City | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Shanti KunjAditya Associates | Talegaon Dabhade (R) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Shiv Hills Phase 2Trimurti Developers | Wagholi | Jun 2024 | Jun 2025 | 2 yrs 5 mo late |
| Shradha ApartmentTrisha Developers | Kothrud | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Shubh Global StreetShubh Capital | Vadgaonsheri | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sidheshwar ComplexManisha Balkrishna Jadhav | Korhale Bk | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| SpectrumJoshi Buildcon Landmarks | Pune (M Corp.) | Jun 2024 | May 2025 | 2 yrs 5 mo late |
| Suraj ResidencySanghavi Constructions | Ravet | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Swanand ApartmentArsya Creations LLP | Pune (M Corp.) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sahyadri HeightsV. K. Developers | Dhankawadi | Jun 2024 | May 2025 | 2 yrs 5 mo late |
| Siddhi IrisJai Ganesh Construction | Pimpale Gurav | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Sun VistaMittal Vastushilp LLP | Wadgaon Bk | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Trimurti ParkSiddhanath Developers | Pune (M Corp.) | Jun 2024 | Dec 2025 | 2 yrs 5 mo late |
| The Greater GoodSai Infra | Mohammadwadi | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Up-Life-Phase-1-VeronicaAvior Shelters LLP | Uravade | Jun 2024 | Jun 2025 | 2 yrs 5 mo late |
| VasundharaGreystone Venture | Dudulgaon | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Vidyanjani ApartmentsPradeep Gopal Sabane | Pune (M Corp.) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Villagio ToscanaDasscon Realty Private Limited | Pune (M Corp.) | Jun 2024 | Dec 2024 | 2 yrs 5 mo late |
| VivantaShree Sonigara Punamiya Associates | Pimpri Chinchawad (M Corp.) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
| Vande MataramShree Sai Samarth Developers | Pimpri Chinchawad (M Corp.) | Jun 2024 | Jun 2024 | 2 yrs 5 mo late |
Delayed projects by district
All MaharashtraPune · 2,214Thane · 1,157Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology