ProjectLocalityPromisedRevisedDelivery
Gokhale Business HubGokhale Heights LLPKothrudJun 2024Jun 20242 yrs 5 mo late
GovindaR J BrothersKondhwa BkJun 2024Dec 20252 yrs 5 mo late
Green City Phase II K BuildingAjit Girdharilal NaharShivne (Part)Jun 2024Jun 20252 yrs 5 mo late
Gulmohar SquareRajkumar Chamanlal BehrMundhawaJun 2024Jun 20242 yrs 5 mo late
Hatimi Hills Phase II Building FPyramid InfrastructureYawalewadiJun 2024Dec 20252 yrs 5 mo late
JD GaathaShree Jagadguru DevelopersLohgaonJun 2024Mar 20262 yrs 5 mo late
Jewel SquareVardhaman BuildconsPune (Cb)Jun 2024Jun 20242 yrs 5 mo late
KojagiriGokhale Realty LLPKothrudJun 2024Jun 20242 yrs 5 mo late
Lake VistaLake Vista Propertis LLPBhugaonJun 2024Jun 20242 yrs 5 mo late
Madhura ApartmentSathe Shah DevelopersParvatiJun 2024Jun 20242 yrs 5 mo late
Manik VillaSamarth AssociatesSinhgad RoadJun 2024Jun 20242 yrs 5 mo late
Manohar ParadiseBhagyashree Bharat ShastriBanerJun 2024Jun 20242 yrs 5 mo late
Manohar ResidencyManohar Civil ServicesBanerJun 2024Jun 20242 yrs 5 mo late
N V Business CenterN V Construction CompanySomataneJun 2024Jun 20242 yrs 5 mo late
North East Business CapitalShiv PropertiesChikhaliJun 2024Jun 20242 yrs 5 mo late
North East Business CornerShiv PropertiesChikhaliJun 2024Jun 20242 yrs 5 mo late
NayanaGokhale Promoters LLPKothrudJun 2024Jun 20242 yrs 5 mo late
Nexus WestprideNexus BuildtechPunawaleJun 2024Jun 20242 yrs 5 mo late
Nyati Enthral INyati Landmark Projects LLPKharadiJun 2024Jun 20242 yrs 5 mo late
Om Ganesh CornerJai Ganesh DevelopersSasvad (M Cl)Jun 2024Jun 20242 yrs 5 mo late
Onnyyx AurrumOnnyyx RealtorsPune (M Corp.)Jun 2024Jun 20242 yrs 5 mo late
ParadiseAmarnath BuildconCharholiJun 2024Jun 20242 yrs 5 mo late
Purvanchal F BuildingVTP Corpartion LLPKesnandJun 2024Jun 20252 yrs 5 mo late
Ramanand ComplexDisha ConstructionsTalegaon Dabhade (M Cl)Jun 2024Jun 20242 yrs 5 mo late
Royal ResidencyAbdul Rehman DurraniVadgaonsheriJun 2024Jun 20242 yrs 5 mo late
Rivers Edge Wing BKokane BuildersPimpri Chinchawad (M Corp.)Jun 2024Jun 20242 yrs 5 mo late
Sai Anirudha DhamSmw Builders And DevelopersWadagaon (Ct)Jun 2024Jun 20252 yrs 5 mo late
Sai KrupaAditya AssociatesTalegaon Dabhade (R)Jun 2024Jun 20242 yrs 5 mo late
Sai SadanAbhishek EnterprisesKondhwa BkJun 2024Jun 20242 yrs 5 mo late
Sai VatsalyaShree Sai AssociatesHadapsarJun 2024Jun 20242 yrs 5 mo late
Samarth ResidencyShree Swami DevelopersPune CityJun 2024Jun 20242 yrs 5 mo late
Shanti KunjAditya AssociatesTalegaon Dabhade (R)Jun 2024Jun 20242 yrs 5 mo late
Shiv Hills Phase 2Trimurti DevelopersWagholiJun 2024Jun 20252 yrs 5 mo late
Shradha ApartmentTrisha DevelopersKothrudJun 2024Jun 20242 yrs 5 mo late
Shubh Global StreetShubh CapitalVadgaonsheriJun 2024Jun 20242 yrs 5 mo late
Sidheshwar ComplexManisha Balkrishna JadhavKorhale BkJun 2024Jun 20242 yrs 5 mo late
SpectrumJoshi Buildcon LandmarksPune (M Corp.)Jun 2024May 20252 yrs 5 mo late
Suraj ResidencySanghavi ConstructionsRavetJun 2024Jun 20242 yrs 5 mo late
Swanand ApartmentArsya Creations LLPPune (M Corp.)Jun 2024Jun 20242 yrs 5 mo late
Sahyadri HeightsV. K. DevelopersDhankawadiJun 2024May 20252 yrs 5 mo late
Siddhi IrisJai Ganesh ConstructionPimpale GuravJun 2024Jun 20242 yrs 5 mo late
Sun VistaMittal Vastushilp LLPWadgaon BkJun 2024Jun 20242 yrs 5 mo late
Trimurti ParkSiddhanath DevelopersPune (M Corp.)Jun 2024Dec 20252 yrs 5 mo late
The Greater GoodSai InfraMohammadwadiJun 2024Jun 20242 yrs 5 mo late
Up-Life-Phase-1-VeronicaAvior Shelters LLPUravadeJun 2024Jun 20252 yrs 5 mo late
VasundharaGreystone VentureDudulgaonJun 2024Jun 20242 yrs 5 mo late
Vidyanjani ApartmentsPradeep Gopal SabanePune (M Corp.)Jun 2024Jun 20242 yrs 5 mo late
Villagio ToscanaDasscon Realty Private LimitedPune (M Corp.)Jun 2024Dec 20242 yrs 5 mo late
VivantaShree Sonigara Punamiya AssociatesPimpri Chinchawad (M Corp.)Jun 2024Jun 20242 yrs 5 mo late
Vande MataramShree Sai Samarth DevelopersPimpri Chinchawad (M Corp.)Jun 2024Jun 20242 yrs 5 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology