RERA projects in Sinhgad Road

6 projects under 6 MahaRERA registrations, registered 2017–2020. 33% have a completion date extended beyond the one promised.

6RERA projects
6Registrations
0Completion still due6 past their completion date
40 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20182
20190
20201

Projects in Sinhgad Road

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Manik VillaSamarth AssociatesP521000273918 Dec 202030 Jun 2024—Promised date passed0
AadrikaDK AssociatesP5210001849312 Nov 201830 Dec 202230 Dec 2024Extended 24 mo0
Narayan Complex AN K Jagtap DevelopersP521000149944 May 201830 Jun 2018—Promised date passed0
Monte RosaTushar Builders & BKP Infra LLPP521000134427 Oct 201730 Dec 2023—Promised date passed0
Aishwarya VillaAishwarya DevelopersP5210001103531 Aug 201730 Sep 2018—Promised date passed0
Shashitara HillsShrikant Shashikant JagtapP5210000811918 Aug 201731 Jan 201830 Sep 2022Extended 56 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Aishwarya Developers1 project
  2. DK Associates1 project
  3. N K Jagtap Developers1 project
  4. Samarth Associates1 project
  5. Shrikant Shashikant Jagtap1 project
  6. Tushar Builders & BKP Infra LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology