Delayed projects in Palghar
362 MahaRERA projects in Palghar are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 4 of 8.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Avani HillviewAvani hill View | Varangade | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Atharva ClassicShree Siddhivinayak Developers | Vasaivirar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Cosmos SolitaireCosmos Prime Projects Ltd | Virar | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Fia TulipNimish Laxmichand Pasad | Mahim | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Flower Valley ComplexSheru Shamsher Khan | Birwadi | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| Fort Maurice Apartment And AakankshaPrasadam Associates | Vasai Virar City (M Corp) | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| Ipsit Paradise Phase 2Dreamland Developers | Tokare | Dec 2022 | Apr 2026 | 3 yrs 11 mo late |
| Mahavir Shopping CentreMahavir Builders & Developers | Umroli | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Om Sai ApartmentShree Sai Builders & Developers | Betegaon | Dec 2022 | Dec 2025 | 3 yrs 11 mo late |
| Om Sai Heights IIShree Sai Shakti Properties | Vasai Virar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Om Sai Heights IISai Shakti Enterprises | Vasaivirar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Om Sai Heights IISai Shakti Constructions | Vasaivirar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Rashmi Hill ViewRashmi Housing Private Limited | Vasai Virar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Sadguru HeightsSadguru Devlopers | Umroli | Dec 2022 | Dec 2023 | 3 yrs 11 mo late |
| Shree Sai ApartmentShree Sai Jivdani Developers | Umroli | Dec 2022 | Jul 2026 | 3 yrs 11 mo late |
| Siddhivinayaksamruddhi realtor and construction | Mahim | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Vatsalya ViharShri Parshva Developers | Vasaivirar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Yashodhan ResidencyKadar Gaffar Kargathra | Jawhar (M Cl) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Yashwant Heights Phase 1Versatilerealtorsprivatelimited | Mori | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Yashwant Heights Phase 2Versatilerealtorsprivatelimited | Vasaivirar City (M Corp) | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Dream VillaShrinath Infra | Aadne | Dec 2022 | Dec 2022 | 3 yrs 11 mo late |
| Matru KrupaVikram Palabhai Chhuchhar | Mahim | Mar 2023 | Mar 2023 | 3 yrs 8 mo late |
| Paramount Enclave Bldg 02Swastik Enterprises | Mahim | Mar 2023 | Dec 2025 | 3 yrs 8 mo late |
| Paramount Enclave Bldg No 4Av Affordable Housing LLP | Mahim | Mar 2023 | Mar 2026 | 3 yrs 8 mo late |
| Paramount Enclave Bldg No 5aOmkar Developers | Mahim | Mar 2023 | Mar 2026 | 3 yrs 8 mo late |
| Sheetal SonaD.g.s Township Private Limited | Vasaivirar City (M Corp) | Mar 2023 | May 2025 | 3 yrs 8 mo late |
| Sathya Lifestyles Building No 12Santosh Arjun Naik | Shelwali | Mar 2023 | Nov 2025 | 3 yrs 8 mo late |
| Hari Om Villa | Palghar | May 2023 | May 2023 | 3 yrs 6 mo late |
| Shyam RegencyShobha Relators | Dhansar | May 2023 | May 2023 | 3 yrs 6 mo late |
| Chetna ResidencyParag Hasmukhlal Doshi | Palghar | Jun 2023 | Dec 2025 | 3 yrs 5 mo late |
| Highstreet VasaiGanadhar Infra Developers Pvt. Ltd | Vasaivirar City (M Corp) | Jun 2023 | Jun 2024 | 3 yrs 5 mo late |
| Prithvi Shopping CenterJanardan Rampalat Yadav | Palghar | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Priti ChaayaRajlaxmi Developers | Makane | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| RajlaxmiKaushik Ashok Sharma Prop of Rajlaxmi Developers | Sutarpada | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Savewadi-3Kawali Builders | Vasaivirar City (M Corp) | Jun 2023 | Jun 2023 | 3 yrs 5 mo late |
| Shubh AarambhVisharia Sadguru Bhoomi LLP | Makane | Jun 2023 | Jun 2024 | 3 yrs 5 mo late |
| Sheetal HeightD G Land Developers Private Limited | Vasai Virar City (M Corp) | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Sheetal JyotD G Land Developers Private Limited | Vasaivirar City (M Corp) | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Mount ViewStar Builder & Developers | Palghar | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Orchid-Hans HeritageHans Realtors | Kurgaon | Jul 2023 | Jul 2023 | 3 yrs 4 mo late |
| Ramchandra Residency Building No. 2Himali Construction | Kopri | Jul 2023 | Jul 2025 | 3 yrs 4 mo late |
| Shivshakti Apartment 2Sanjay Patil | Vasaivirar City (M Corp) | Sep 2023 | Sep 2023 | 3 yrs 2 mo late |
| Mahira TowerNew Sky Developers | Vasaivirar City (M Corp) | Sep 2023 | Sep 2023 | 3 yrs 2 mo late |
| Rustomjee Virar Avenue L1-L2 and L4 Wing I J and RetailKeystone Infrastructure Private Limited | Dongare | Sep 2023 | Dec 2025 | 3 yrs 2 mo late |
| Sai Krishna AanandiSai Krishna Signature Homes LLP | Palghar | Oct 2023 | Dec 2025 | 3 yrs 1 mo late |
| Narayani Darshan Building No-7Narayani | Saphale | Oct 2023 | Oct 2025 | 3 yrs 1 mo late |
| Ekaakshara CreatorEkaakshara Creator | Vasai Virar City (M Corp) | Nov 2023 | Nov 2023 | 3 yrs late |
| Pride ApartmentFine Homes | Makane | Nov 2023 | Nov 2023 | 3 yrs late |
| AarambhThe Park Realty | Palghar | Dec 2023 | Dec 2023 | 2 yrs 11 mo late |
| adiraj nayan paradiseshri laxmi realtors | Vasaivirar City (M Corp) | Dec 2023 | Dec 2025 | 2 yrs 11 mo late |
Delayed projects by district
All MaharashtraPune · 2,214Thane · 1,157Raigarh · 1,042Mumbai Suburban · 994Nashik · 481Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology