Deedo IDDP-PAL-P982

Completion was pushed back 3 years and 4 months to Apr 2026, and that date has passed too; no MahaRERA orders on record; 100% of its units are booked.

Tokare, Palghar 401208 · by Dreamland Developers

Delivery3 yrs 11 mo latePromised Dec 2022 · revised Apr 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked5 of 5 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 3 years and 4 months to Apr 2026, and that date has passed too

  • This projectRegistered 31 Aug 2017, completion promised 30 Dec 2022, revised to 30 Apr 2026, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000010582
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900001058231 Aug 201730 Dec 202230 Apr 2026Dreamland DevelopersProject page
Documents76

3 documents held by Deedo, 73 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN Carddd pan.pdf · uploaded 30 Jul 2017Source

Legal

  • Legal Title reportcompress title.pdf · uploaded 30 Jul 2017Source
  • Declaration Form Bdreamland p 2 form b.pdf · uploaded 30 Jul 2017Source
  • Declaration Form BFORM B PHASE2 RERA EXTENTION.pdf · uploaded 1 Jun 2024Source

Migrated

  • 1 PAN Carddd pan.pdf · uploaded 30 Jul 2017Source
Show all 76 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportcompress title.pdf · uploaded 30 Jul 2017Source
  • 1 Details of encumbrancesdreamland p2 encum.pdf · uploaded 30 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)ilovepd final.pdf · uploaded 30 Jul 2017Source
  • 1 Building Plan Approval (IOD)ilovepd final.pdf · uploaded 30 Jul 2017Source
  • 1 Declaration in FORM Bdreamland p 2 form b.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)compress arch.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)compressed eng.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of CA (Form 3)DD CA Certificate (1).pdf · uploaded 30 Jul 2017Source
  • 1 Proforma of Allotment letteral dd.pdf · uploaded 30 Jul 2017Source
  • 2 Certificates of CA (Form 3)dd PHASE 2 ca.pdf · uploaded 21 Dec 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)dreamland phase 2 compressed.pdf · uploaded 22 Dec 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)compressed DD PHASE 2 ENG.pdf · uploaded 25 Dec 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH P2 COMP.pdf · uploaded 1 Mar 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG P2 COMP.pdf · uploaded 1 Mar 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentDD NA compressed FINAL.pdf · uploaded 3 Mar 2018Source
  • 3 Certificates of CA (Form 3)CA D2 compressed.pdf · uploaded 13 Apr 2018Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH DD 2.pdf · uploaded 22 Jun 2018Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG DD 2.pdf · uploaded 22 Jun 2018Source
  • 4 Certificates of CA (Form 3)CA DD 2.pdf · uploaded 22 Jun 2018Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch d2.pdf · uploaded 24 Aug 2018Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng d2.pdf · uploaded 24 Aug 2018Source
  • 5 Certificates of CA (Form 3)DD IPSIT PARADISE PHASE II.pdf · uploaded 10 Sep 2018Source
  • 1 Certificates of CA (Form 5)D PHASE 2.pdf · uploaded 8 Oct 2018Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)dream land p 2 arch.pdf · uploaded 22 Dec 2018Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)D2 COMP.pdf · uploaded 22 Dec 2018Source
  • 6 Certificates of CA (Form 3)d2.pdf · uploaded 22 Dec 2018Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 12 21.pdf · uploaded 9 May 2024Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 12 22.pdf · uploaded 9 May 2024Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 03 23.pdf · uploaded 9 May 2024Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 06 23.pdf · uploaded 9 May 2024Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 09 23.pdf · uploaded 9 May 2024Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 12 23.pdf · uploaded 9 May 2024Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1 03 24.pdf · uploaded 9 May 2024Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 12 21.pdf · uploaded 9 May 2024Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 12 22.pdf · uploaded 9 May 2024Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 03 23.pdf · uploaded 9 May 2024Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 06 23.pdf · uploaded 9 May 2024Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 09 23.pdf · uploaded 9 May 2024Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 12 23.pdf · uploaded 9 May 2024Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 03 24.pdf · uploaded 9 May 2024Source
  • 7 Certificates of CA (Form 3)form 3 12 20.pdf · uploaded 9 May 2024Source
  • 8 Certificates of CA (Form 3)form 3 12 21.pdf · uploaded 9 May 2024Source
  • 9 Certificates of CA (Form 3)form 3 12 22.pdf · uploaded 9 May 2024Source
  • 10 Certificates of CA (Form 3)form 3 03 23.pdf · uploaded 9 May 2024Source
  • 11 Certificates of CA (Form 3)form 3 06 23.pdf · uploaded 9 May 2024Source
  • 12 Certificates of CA (Form 3)form 3 09 23.pdf · uploaded 9 May 2024Source
  • 13 Certificates of CA (Form 3)form 3 12 23.pdf · uploaded 9 May 2024Source
  • 14 Certificates of CA (Form 3)form 3 03 24.pdf · uploaded 9 May 2024Source
  • 1 Declaration about Commencement CertificatePHASE 2 EXTENTION DD DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 1 Jun 2024Source
  • 2 Declaration in FORM BFORM B PHASE2 RERA EXTENTION.pdf · uploaded 1 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)engineer certificate form 2A PHASE 2 (23-24.pdf · uploaded 1 Jun 2024Source
  • 1 CERSAI detailsPHASE 2 EXTENSION cERSAI dECLARATION.pdf · uploaded 1 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM - 5 DD PHASE 2 FY 23-24.pdf · uploaded 1 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 19-20.pdf · uploaded 6 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 20-21.pdf · uploaded 6 Jun 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 20-21.pdf · uploaded 6 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 21-22.pdf · uploaded 6 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 22-23.pdf · uploaded 6 Jun 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of inventory.pdf · uploaded 7 Jun 2024View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form 5 19-20.pdf · uploaded 7 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 20-21.pdf · uploaded 7 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5 21-22.pdf · uploaded 7 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5 22-23.pdf · uploaded 7 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CA Form 5 Ipsit Paradise Phase 2 ( 2018-29).pdf · uploaded 10 Jun 2024Source

Technical

  • Documentilovepd final.pdf · uploaded 30 Jul 2017Source
  • Documentilovepd final.pdf · uploaded 30 Jul 2017Source

Technical (Architect)

  • Documentform 1 03 24.pdf · uploaded 9 May 2024Source

Technical (Engineer)

  • Documentform 2 03 24.pdf · uploaded 9 May 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO 80

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Bungalow no 11 to 12, Bungalow no 13 to 155 units in all
Address
S No 80PIN 401208
Village
Tokare, Vasai taluka
Land area for this project
2,042 sq m (21,979 sq ft)
Permissible built-up area
1,910 sq m (20,555 sq ft)
Sanctioned built-up area
1,910 sq m (20,555 sq ft)
Designated bank account
43
Developed in phases
No

Survey, CTS, gat or plot numbers

S NO 80

Land as published on MahaRERA's project page

S NO 80

Boundaries

North
Land Of Mr Samant
South
Virar Kaver State Highway
East
Adivasi Land
West
Internal Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking5 units

5 of 5 units booked (100%), as the promoter reported to MahaRERA

Bungalow no 11 to 12 · 2 unitsBungalow no 13 to 15 · 3 units
TypeCarpet areaUnitsBooked
Bungalow no 11 to 1289.97 sq m · 968 sq ft22
Bungalow no 13 to 1595.51 sq m · 1,028 sq ft33

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAbhay Raut—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Tokare

All 2 projects in Tokare · Compare Ipsit Paradise Phase 2 with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology