RERA projects in Sutarpada
4 projects under 4 MahaRERA registrations, registered 2019–2025. 50% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
2Completion still due2 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Sutarpada
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aradhya HeightsHarshal Pandit Khairnar | P99000080975 | 19 Sep 2025 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| DwarkaRaj TowersRonak Rajendra Mutha | P99000051888 | 7 Jul 2023 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| RajlaxmiKaushik Ashok Sharma Prop of Rajlaxmi Developers | P99000027121 | 19 Nov 2020 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| Dwarka EnclaveRekha Bharat Mehta | P99000021077 | 31 May 2019 | 27 Dec 2022 | 27 Dec 2022 | Promised date passed | 0 |
Other localities in Talasari
Most active promoters
By projects registered here, as named on MahaRERA.
- Harshal Pandit Khairnar1 project
- Kaushik Ashok Sharma Prop of Rajlaxmi Developers1 project
- Rekha Bharat Mehta1 project
- Ronak Rajendra Mutha1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology