RERA projects in Talasari

14 projects under 14 MahaRERA registrations, registered 2017–2026. None has an extended completion date on record.

14RERA projects
14Registrations
5Completion still due5 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20191
20201
20211
20220
20231
20240
20252
20262

Projects in Talasari

14 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Umiya VillasUmiya VillasPR124000260134529 Jul 202631 Mar 2029—Not yet due0
Lotus GardenOmkar InfraPR124000260093325 Jun 202631 Dec 2029—Not yet due0
Aradhya HeightsHarshal Pandit KhairnarP9900008097519 Sep 202531 Dec 2026—Not yet due0
Ajit Shanti Industrial ParkAamgaon 1 Infra Private LimitedP9900008060419 Jun 202530 Sep 2026—Promised date passed0
DwarkaRaj TowersRonak Rajendra MuthaP990000518887 Jul 202331 Dec 2029—Not yet due0
Shivalaya ComplexSwastik Builders And DevelopersP9900003233429 Dec 202130 Nov 2028—Not yet due0
RajlaxmiKaushik Ashok Sharma Prop of Rajlaxmi DevelopersP9900002712119 Nov 202030 Jun 2023—Promised date passed0
Dwarka EnclaveRekha Bharat MehtaP9900002107731 May 201927 Dec 2022—Promised date passed0
Suman Vastu ApartmentFamid Himamudin ShaikhP9900001005023 Aug 201731 Mar 2018—Promised date passed0
Relax HomesMohd Sajid Abdul Salam PashaP9900000769617 Aug 201731 Dec 2017—Promised date passed0
P99000081040P99000081040————0
R K ApartmentP99000005413————0
R K Apartment 2P99000016268————0
Shubham PropertiesP99000024813————0

Other talukas in Palghar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Aamgaon 1 Infra Private Limited1 project
  2. Famid Himamudin Shaikh1 project
  3. Harshal Pandit Khairnar1 project
  4. Kaushik Ashok Sharma Prop of Rajlaxmi Developers1 project
  5. Mohd Sajid Abdul Salam Pasha1 project
  6. Omkar Infra1 project
  7. Rekha Bharat Mehta1 project
  8. Ronak Rajendra Mutha1 project
  9. Swastik Builders And Developers1 project
  10. Umiya Villas1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology