Aradhya Heights
Deedo IDDP-PAL-E2Q6Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Sutarpada, Palghar 401606 · by Harshal Pandit Khairnar
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 19 Sep 2025, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000080975
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000080975 | 19 Sep 2025 | 31 Dec 2026 | 30 Apr 2027 | Harshal Pandit Khairnar | Project page |
Documents64
2 documents held by Deedo, 62 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
Show all 64 documentsShow fewer documents
Legal
- Other – LegalCA CERTIFICATE SCANNED.pdf · uploaded 4 Aug 2025Source
Migrated
- 1 PAN CardPan Card.pdf · uploaded 4 May 2025Source
- 1 Copy of the legal title reportLegal Title Report_11zon.pdf · uploaded 4 May 2025Source
- 1 a Details of encumbrances concerned to FinanceKaagaz_20250227_191938626165.pdf · uploaded 4 May 2025Source
- 2 a Details of encumbrances concerned to FinanceKaagaz_20250227_192112449714.pdf · uploaded 4 May 2025Source
- 1 Copy of Layout Approval (in case of layout)1709619274.pdf · uploaded 4 May 2025Source
- 1 Declaration in FORM BRera Stamp Paper Harshaleela.pdf · uploaded 4 May 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architech certificate_11zon.pdf · uploaded 4 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate_11zon.pdf · uploaded 4 May 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCert_RB_363754_348VshWySign.pdf · uploaded 4 May 2025Source
- 1 Building Plan Approval / NA Order for plotted development1709619274.pdf · uploaded 4 May 2025Source
- 1 Declaration about Commencement CertificateKaagaz_20250227_192223593208.pdf · uploaded 4 May 2025Source
- 1 CERSAI detailsponit no 05 CERSAI REPORT.pdf · uploaded 4 May 2025Source
- 1 Deviation Report with respect to Allotment letterKaagaz_20250227_192951437788.pdf · uploaded 4 May 2025Source
- 1 b Details of encumbrances concerned to LegalKaagaz_20250227_191938626165.pdf · uploaded 4 May 2025Source
- 2 b Details of encumbrances concerned to LegalKaagaz_20250227_192112449714.pdf · uploaded 4 May 2025Source
- 1 Deviation Report with respect to model copy of AgreementKaagaz_20250227_192648414311.pdf · uploaded 4 May 2025Source
- 1 Proforma of Agreement for saleRERA -AGREEMENT HARSHLEELA FINAL.pdf · uploaded 4 May 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsKaagaz_20250227_192541147949.pdf · uploaded 4 May 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectKaagaz_20250227_191938626165.pdf · uploaded 4 May 2025Source
- 3 a Details of encumbrances concerned to Financeponit no 04 NON ENCUMBRANCE FINANCE DECLARATION.pdf · uploaded 21 Jun 2025Source
- 2 Declaration about Commencement CertificateCC EMAIL LATEST PDF.pdf · uploaded 21 Jun 2025Source
- 3 b Details of encumbrances concerned to Legalponit no 04 NON ENCUMBRANCE FINANCE DECLARATION.pdf · uploaded 21 Jun 2025Source
- 1 Other – Financepoint no 03 SECURED UNSECURED.pdf · uploaded 21 Jun 2025Source
- 2 Copy of the legal title reportSearch Report Talasari.pdf · uploaded 7 Jul 2025Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 7 Jul 2025Source
- 2 Declaration in FORM Bform b.pdf · uploaded 7 Jul 2025Source
- 4 Declaration about Commencement CertificatePLINTH CERTIFICATE.pdf · uploaded 7 Jul 2025Source
- 3 Declaration about Commencement CertificateForm D.pdf · uploaded 7 Jul 2025Source
- 1 Other – TechnicalAnnexure A.pdf · uploaded 7 Jul 2025Source
- 2 Proforma of Agreement for saleRERA -AGREEMENT HARSHLEELA FINAL.pdf · uploaded 7 Jul 2025Source
- 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 4 Aug 2025Source
- 1 Other – LegalCA CERTIFICATE SCANNED.pdf · uploaded 4 Aug 2025Source
- 5 Declaration about Commencement CertificateCC EMAIL LATEST PDF.pdf · uploaded 4 Aug 2025Source
- 3 Proforma of Agreement for saleAGREEMENT FOR SALE LATEST PDF.pdf · uploaded 4 Aug 2025Source
- 3 Proforma of Allotment letterAllotment Letter new.pdf · uploaded 28 Aug 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentcc email confirmation latest.pdf · uploaded 28 Aug 2025Source
- 3 Commencement Certificates / NA Order for plotted developmentCC authorization letter from talasari authority.pdf · uploaded 28 Aug 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE SCANNED.pdf · uploaded 11 Sep 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Self declaration landowner for self consumption.pdf · uploaded 11 Sep 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)bank declaration format b new.pdf · uploaded 11 Sep 2025Source
- 2 Disclosure for secured/unsecured finance availed for the projectpoint no 03 SECURED UNSECURED.pdf · uploaded 11 Sep 2025Source
- 2 Declaration about all RERA Designated Bank Accounts (Format A)Format A Sep 16, 2025.pdf · uploaded 17 Sep 2025Source
- Form 1Architech certificate as on 30-09-2025.pdf · uploaded 4 Nov 2025Source
- Form 2Engineer Certificate as on 30-09-2025.pdf · uploaded 4 Nov 2025Source
- Form 3CA Certificate as on 30-09-2025.pdf · uploaded 4 Nov 2025Source
- Disclosure of Sold and Booked Inventorysold unsold inventory as on 30-09-2025.pdf · uploaded 4 Nov 2025View
- Form 1Form 1 as on 31-12-2025_compressed.pdf · uploaded 1 Jul 2026Source
- Form 2Form 2 as on 31-12-2025.pdf · uploaded 1 Jul 2026Source
- Form 3Form 3 as on 31-12-2025.pdf · uploaded 1 Jul 2026Source
- Disclosure of Sold and Booked InventorySold Unsold as on 31-12-2025.pdf · uploaded 1 Jul 2026View
Technical
Technical (Architect)
- Documentarchitech certificate_11zon.pdf · uploaded 4 May 2025Source
Technical (Engineer)
- Documentengineer certificate_11zon.pdf · uploaded 4 May 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO 23/2/5/1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Landowner 1BHK, Landowner 2BHK, Landowner Office, Landowner Shop, Office space, Shop33 units in all
- Address
- Survey No 23/2/5/1, Sutarpada, SutarpadaPIN 401606
- Village
- Sutarpada, Talasari taluka
- Location
- 20.11839, 72.91633
- Land area for this project
- 1,250 sq m (13,455 sq ft)
- Permissible built-up area
- 1,884 sq m (20,274 sq ft)
- Sanctioned built-up area
- 1,884 sq m (20,274 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 159
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO 23/2/5/1
Boundaries
- North
- S No 23 Land
- South
- Road Towards Haladpada
- East
- National Highway 48 And Service Road
- West
- S No 23 Land
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking33 units
0 of 33 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 55.06 sq m · 593 sq ft | 2 | 0 |
| 1BHK | 55.26 sq m · 595 sq ft | 4 | 0 |
| 2BHK | 67.88 sq m · 731 sq ft | 3 | 0 |
| 2BHK | 69.53 sq m · 748 sq ft | 1 | 0 |
| 2BHK | 70.04 sq m · 754 sq ft | 1 | 0 |
| Landowner 1BHK | 55.26 sq m · 595 sq ft | 2 | 0 |
| Landowner 2BHK | 66.89 sq m · 720 sq ft | 1 | 0 |
| Landowner 2BHK | 69.53 sq m · 748 sq ft | 2 | 0 |
Show all 21 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Landowner Office | 27.67 sq m · 298 sq ft | 1 | 0 |
| Landowner Shop | 17.45 sq m · 188 sq ft | 1 | 0 |
| Landowner Shop | 20.77 sq m · 224 sq ft | 1 | 0 |
| Landowner Shop | 20.89 sq m · 225 sq ft | 1 | 0 |
| Landowner Shop | 26.65 sq m · 287 sq ft | 1 | 0 |
| Office space | 21.43 sq m · 231 sq ft | 1 | 0 |
| Shop | 13.77 sq m · 148 sq ft | 1 | 0 |
| Shop | 16.58 sq m · 178 sq ft | 2 | 0 |
| Shop | 17.41 sq m · 187 sq ft | 2 | 0 |
| Shop | 18.34 sq m · 197 sq ft | 2 | 0 |
| Shop | 22.06 sq m · 237 sq ft | 1 | 0 |
| Shop | 23.19 sq m · 250 sq ft | 2 | 0 |
| Shop | 33.37 sq m · 359 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Suchit Jagdish Raut | — |
| Chartered accountant | A S Suterwala & Co | — |
| Engineer | Yash Jobanputra | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Sutarpada
- DwarkaRaj TowersRERA P99000051888
- RajlaxmiRERA P99000027121
- Dwarka EnclaveRERA P99000021077
All 4 projects in Sutarpada · Compare Aradhya Heights with another project